Roof7p · 4 filings · 8 docs
ArchitectureElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
Installation of 2-Point Suspended Scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
On file for this project
2 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER DRAWINGS. DEBRIS CHUTE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 4 filings on this floor.
Floor 75p · 3 filings · 6 docs
ArchitectureElectricalEquipmentMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
Installation of 2-Point Suspended Scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER DRAWINGS. DEBRIS CHUTE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 65p · 3 filings · 6 docs
ArchitectureElectricalEquipmentMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
Installation of 2-Point Suspended Scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER DRAWINGS. DEBRIS CHUTE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 56p · 3 filings · 6 docs
ArchitectureElectricalEquipmentMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
Installation of 2-Point Suspended Scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
On file for this project
2 documents · 1 drawing sheet
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER DRAWINGS. DEBRIS CHUTE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 45p · 3 filings · 6 docs
ArchitectureElectricalEquipmentMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
Installation of 2-Point Suspended Scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER DRAWINGS. DEBRIS CHUTE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Floor 36p · 6 filings · 12 docs
ArchitectureElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
Installation of 2-Point Suspended Scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER DRAWINGS. DEBRIS CHUTE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 6 filings on this floor.
Floor 26p · 6 filings · 12 docs
ArchitectureElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
Installation of 2-Point Suspended Scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER DRAWINGS. DEBRIS CHUTE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 6 filings on this floor.
Floor 113p · 9 filings · 20 docs
ArchitectureElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold
Installation of 2-Point Suspended Scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
On file for this project
2 documents
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER DRAWINGS. DEBRIS CHUTE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Latest 3 of 9 filings on this floor.
Cellar9p · 1 filing · 4 docs
Plumbing
Issued Permit Scope
Plumbing
UNDERGROUND PLUMBING AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB# 123172716
On file for this project
4 documents
Basement1p · 1 filing · 4 docs
Plumbing
UNDERGROUND PLUMBING AS PER PLANS FILED. FILED IN CONJUNCTION WITH NB# 123172716
On file for this project
4 documents · 1 drawing sheet
Sub-Basement2p · 2 filings · 4 docs
ArchitectureStructural
Issued Permit Scope
Protection and Mechanical Methods · Supported Scaffold
INSTALLATION OF TEMPORARY PIPE SCAFFOLD AS PER DRAWINGS. SCAFFOLD SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
INSTALLATION OF TEMPORARY DEBRIS CHUTE AS PER DRAWINGS. DEBRIS CHUTE SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
2 documents
Site & exterior19p · 12 filings · 20 docs
ArchitectureElectricalEquipmentGeneralMechanicalStructural
Issued Permit Scope
Construction Fence · Protection and Mechanical Methods · Sidewalk Shed · Supported Scaffold
INSTALLATION OF PYLWOOD FENCE AS PER PLANS. PLYWOOD FENCE SHALL COMPLY WITH CHAPTER #33 OF THE 2014 CODE NO CHANGE IN USE, EGRESS OR OCCUPANCY UNDER THIS APPLICATION.
On file for this project
2 documents · 4 drawing sheets
INSTALLATION OF HEAVY DUTY SIDEWALK SHED DURING NB CONST, FILED SEP. SIDEWALK SHED SHALL COMPLY WITH CH #33 OF THE NYC BC. NO CHANGE IN USE, OCCUPANCY OR EGRESS UNDER THIS APPLICATION.
On file for this project
6 documents · 5 drawing sheets
Installation of 2-Point Suspended Scaffolding as per plan and in accordance with Chapter 33 of NYC Building Code. No change in use, egress or occupancy.
On file for this project
2 documents · 5 drawing sheets
Latest 3 of 12 filings on this floor.
Filed — no permit issued1p · 1 filing · 2 docs
Landscape
APPLICATION FIELD TO INSTALL A 8' CONSTRUCTION FENCE IN CONJUNCTION WITH NB. TOTAL STREET FRONTAGE 58.33'
On file for this project
2 documents · 1 drawing sheet