| Owner | Filings | Most Recent |
|---|---|---|
| CENTER ONE REALTY | 16 | 07/08/2026 |
| OWNERS REP | 8 | 07/08/2026 |
| AA DEVELOPERS GROUP | 31 | 04/09/2026 |
| SCG CAPITAL | 8 | 04/09/2026 |
| 1686 DAVIDSON LLC | 1 | 03/22/2026 |
| BONEI BUILDERS | 13 | 03/22/2026 |
| 1385 SUTTER | 2 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/30/2025 | $1.6M | — | AA DEVELOPERS GROUP INC → 1686 DAVIDSON LLC | $77/sf building |
| 03/26/2018 | $450K | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| NIKOLAI KATZ ARCHITECT | 7 | 06/18/2026 |
| A&D ENGINEERING, PLLC | 5 | 04/01/2026 |
| PAUL PERDEK, PROF. ENG. PLLC | 4 | 09/02/2025 |
| ELEVATED ENGINEERING NYC | 4 | 07/29/2025 |
| ANTHONY CUCICH ARCHITECT | 2 | 01/04/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 26 | 03/21/2026 |
| ACCRETE CONSTRUCTION | 4 | 03/21/2026 |
| AE DESIGN SOLUTION | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ACCRETE CONSTRUCTION GROUP | General Contractor | 8 | 04/09/2026 |
| LEAD IT BUILDERS, LLC | General Contractor | 8 | 07/08/2026 |
| BONEI BUILDERS LLC | General Contractor | 5 | 04/09/2026 |
| TOVIA WERZBERGER | Electrical | 4 | 03/21/2026 |
| CORE SCAFFOLD SYSTEMS INC. | General Contractor | 3 | 07/08/2026 |
| CREATIVE PLUMBING IN | Plumbing | 3 | 06/28/2026 |
| METFLOW FIRE CONTROL LLC | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 12 | 06/18/2026 |
| ANTHONY CUCICH ARCHITECT | 6081 | 3 | 01/29/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | LEAD IT BUILDERS, LLC | 05/07/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | LEAD IT BUILDERS, LLC | 03/24/2026 |
| DOB NOW | Construction Fence | Signed-off | LEAD IT BUILDERS, LLC | 02/17/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | BONEI BUILDERS | 11/19/2025 |
| DOB NOW | General Construction | Permit Issued | BONEI BUILDERS | 07/24/2025 |
| DOB NOW | Sprinklers | Signed-off | METFLOW FIRE CONTROL LLC | 07/17/2025 |
| DOB NOW | Supported Scaffold | Signed-off | CORE SCAFFOLD SYSTEMS INC | 07/15/2025 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | CORE SCAFFOLD SYSTEMS INC | 07/15/2025 |
| DOB NOW | Sidewalk Shed | Signed-off | CORE SCAFFOLD SYSTEMS INC | 07/09/2025 |
| DOB NOW | Structural | Signed-off | BONEI BUILDERS | 07/02/2025 |
| DOB NOW | Plumbing | Permit Issued | AB PLUMBING INC | 06/10/2025 |
| DOB NOW | Support of Excavation | Signed-off | LEAD IT BUILDERS, LLC | 06/06/2025 |
| DOB NOW | Foundation | Signed-off | LEAD IT BUILDERS, LLC | 06/04/2025 |
| DOB NOW | Construction Fence | Signed-off | LEAD IT BUILDERS, LLC | 05/07/2025 |
| DOB NOW | Construction Fence | Signed-off | BONEI BUILDERS | 02/20/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | ACCRETE CONSTRUCTION GROU | 07/25/2024 |
| DOB NOW | Construction Fence | Signed-off | ACCRETE CONSTRUCTION GROU | 07/18/2024 |
| DOB NOW | Foundation | Permit Issued | ACCRETE CONSTRUCTION GROU | 03/22/2024 |
| DOB NOW | Construction Fence | Signed-off | ACCRETE CONSTRUCTION GROU | 03/19/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | ACCRETE CONSTRUCTION GROU | 06/13/2023 |
| DOB NOW | Construction Fence | Signed-off | ACCRETE CONSTRUCTION GROU | 05/21/2023 |
| DOB NOW | General Construction | Permit Issued | ACCRETE CONSTRUCTION GROU | 02/17/2023 |
| DOB NOW | Construction Fence | Signed-off | ACCRETE CONSTRUCTION GROU | 07/12/2022 |
| BIS | EQ | ISSUED | N TECH DESIGN OF AMERICA | 02/25/2026 |
| BIS | — | ISSUED | N TECH DESIGN OF AMERICA | 02/26/2025 |
| BIS | — | ISSUED | ACCRETE CONSTRUCTION GROUP | 06/29/2023 |
| BIS | PL | ISSUED | WAGNER ZIV PLUMBING & HEATING | 05/19/2004 |
| BIS | — | ISSUED | MEDITERRANEAN CONSTRUCTION CORP | 04/21/2004 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/18/2026 | Signed-off | LEAD IT BUILDERS, LLC | Air Conditioning Systems, Heating and Air Conditioning Systems | Cooling Mitsubishi Electric MXZ-2C20NAHZ 4 tons · Split System ×6 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2026 | Permit Issued | METFLOW MECHANICAL LLC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/14/2026 | Complete | POWER DIRECT ELECTRIC INC | General Wiring |
| 11/26/2025 | Cancelled | POWER DIRECT ELECTRIC INC | 33 meters, 33 new_meters |
| 09/02/2025 | Permit Issued | POWER DIRECT ELECTRIC INC | — |
| 07/15/2025 | Permit Issued | POWER DIRECT ELECTRIC INC | — |
| 07/03/2025 | Complete | SOLAS ELECTRICAL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2026 | Signed-off | LEAD IT BUILDERS, LLC | 8 scope_items |
| 07/29/2025 | Signed-off | BONEI BUILDERS LLC | Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/18/2026 | Signed-off | LEAD IT BUILDERS, LLC | Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/23/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/10/2026 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 02/19/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 02/04/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/29/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 07/09/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/03/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 07/03/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/25/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 06/20/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/24/2026 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 06/24/2026 | Shutoff dampers | FAHAD FATEH | energy_progress |
| 06/24/2026 | Footing and Foundation | FAHAD FATEH | progress |
| 06/24/2026 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 06/24/2026 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 06/24/2026 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 06/24/2026 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 06/24/2026 | Lighting controls | FAHAD FATEH | energy_progress |
| 06/24/2026 | Maintenance information | FAHAD FATEH | energy_progress |
| 06/24/2026 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 06/24/2026 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 06/24/2026 | Fenestration areas | FAHAD FATEH | energy_progress |
| 06/24/2026 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 06/24/2026 | Interior lighting power | FAHAD FATEH | energy_progress |
| 06/24/2026 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 06/24/2026 | Metering | FAHAD FATEH | energy_progress |
| 06/24/2026 | Duct leakage testing, insulation and design | FAHAD FATEH | energy_progress |
| 06/24/2026 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 06/24/2026 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 06/24/2026 | Air barrier — testing | FAHAD FATEH | energy_progress |
| 06/24/2026 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 06/24/2026 | Subgrade Inspections | FAHAD FATEH | special |
| 06/24/2026 | Mechanical Systems | FAHAD FATEH | special |
| 06/24/2026 | Concrete - Cast-In-Place | FAHAD FATEH | special |
| 06/24/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | FAHAD FATEH | special |