← Back
BuildNYC
Two family frame
169-10 HIGHLAND AVENUE
QUEENS · BIN 4210553
💬 Discuss this project
1920Year Built
2.5Stories
B2Building Class
R4AZoning
3,048 sfGross Floor Area
2Units
Rent Stabilized0 Active ViolationsFDNY Report ↗
Two family frame · 3,706 sf lot · 0.82 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 216p · 1 filing · 20 docs
Floor 112p · 1 filing · 20 docs
Cellar13p · 1 filing · 20 docs
Site & exterior10p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Kenny Lee Architect601/23/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Korman Design & Build1203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Kle ConstructionGeneral Contractor303/21/2026
Kle Constructionspecialty_contractor303/21/2026
C.R.U. Mechan & HeatingPlumbing207/08/2026
V&B Electrical ContngElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Korman Design & Build2055601/23/2025
Building Lifecycle
12/30/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/10/2025
Signed off — Alteration CO
INSTALLATION OF PLUMBING FIXTURES AND GAS BOILER WORK .
Q00667747-S1
06/23/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/16/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/10/2025
Special inspection requirement — Mechanical Systems
DAVID UH
47 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offC.R.U. Mechan & Heating11/18/2024
DOB NOWMechanical SystemsPermit IssuedKle Construction11/15/2024
DOB NOWGeneral ConstructionPermit IssuedKle Construction03/09/2023
DOB NOWPlumbingSigned-offC.R.U. Mechan & Heating03/01/2023
1 project · most recent 01/23/2025
Ventilation Systems
FiledStatusContractorScope
01/23/2025Permit IssuedKle ConstructionVentilation Systems
1 project · most recent 01/23/2025
Gas Water/Sanitary
FiledStatusContractorScope
01/23/2025Signed-offC.R.U. Mechan & HeatingGas, Water/Sanitary
3 projects · most recent 10/19/2026
General Wiring
FiledStatusContractorScope
10/19/2026Permit IssuedV&B Electrical ContngGeneral Wiring
01/13/2026CompleteV&B Electrical ContngGeneral Wiring
05/21/2025CompleteV&B Electrical ContngGeneral Wiring
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
12/30/2025Pass-Final CND-Occupancy InspectionPassView ↗
06/23/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/16/2025Pass-Final CND-Occupancy InspectionPassView ↗
01/09/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/12/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
12/12/2024Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
12/12/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 24
DateRequirementInspectorRole
02/10/2025Mechanical SystemsDAVID UHspecial
02/10/2025Fire-Resistant Penetrations and JointsDAVID UHspecial
02/10/2025FinalDAVID UHprogress
02/10/2025Energy Code Compliance InspectionsDAVID UHprogress
02/10/2025HVAC-R and service water piping design and insulationDAVID UHenergy_progress
02/10/2025HVAC-R and service water heating equipmentDAVID UHenergy_progress
02/10/2025HVAC-R and service water heating system controlsDAVID UHenergy_progress
02/10/2025Fenestration areasDAVID UHenergy_progress
02/10/2025Fenestration air leakageDAVID UHenergy_progress
02/10/2025Fenestration and door U-factor and product ratingsDAVID UHenergy_progress
02/10/2025Air barrier - visual inspectionDAVID UHenergy_progress
01/13/2025HVAC-R and service water piping design and insulationDAVID UHenergy_progress
01/13/2025Fire-Resistant Penetrations and JointsDAVID UHspecial
01/13/2025Energy Code Compliance InspectionsDAVID UHprogress
01/13/2025HVAC-R and service water heating system controlsDAVID UHenergy_progress
01/13/2025HVAC-R and service water heating equipmentDAVID UHenergy_progress
03/21/2023Fenestration and door U-factor and product ratingsDAVID UHenergy_progress
03/21/2023Air barrier - visual inspectionDAVID UHenergy_progress
03/21/2023Fenestration areasDAVID UHenergy_progress
03/21/2023Fire-Resistant Penetrations and JointsDAVID UHspecial
03/21/2023Mechanical SystemsDAVID UHspecial
03/21/2023Energy Code Compliance InspectionsDAVID UHprogress
03/21/2023FinalDAVID UHprogress
03/21/2023Fenestration air leakageDAVID UHenergy_progress
48 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account