← Back
One family attached or semi-detached
169 SEELEY STREET
BROOKLYN · Windsor Terrace-South Slope · BIN 3121834
💬 Discuss this project
1925Year Built
2Stories
A5Building Class
R5BZoning
1,336 sfGross Floor Area
1Units
One family attached or semi-detached · 1,280 sf lot · 1.04 FAR built · Flood zone X
Locations of Work
Architecture
Roof2p · 1 filing · 7 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
UNISOLAR103/17/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
CENTURION SOLAR ENERGYGeneral Contractor104/09/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CENTURION SOLAR ENERGY LL9475103/17/2025
Building Lifecycle
All (14)Filed (1)Permit Issued (1)Signed Off (1)Objection (6)Special Inspection (5)
04/03/2026
Signed off — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
B01193203-I1
04/08/2025
Permit issued — Solar
B01193203-I1-SL
03/28/2025
Objection resolved — Addressed
03/28/2025
Objection resolved — Addressed
03/28/2025
Objection resolved — Addressed
03/26/2025
Objection raised — Fire_Protection
03/26/2025
Objection raised — Structural
03/26/2025
Objection raised — Electrical
03/17/2025
Filed — Alteration
SCOPE OF WORK IS SOLELY FOR THE INSTALLATION OF THE SOLAR ELECTRONICGENERATING SYSTEM. ALL OTHER WORK IS NOT TO BE RELIED UPON AS BEINGAPPROVED AND/OR PERMITTED BY THE NYC DEPARTMENT OF BUILDINGS.*NO CHANGE TO USE, EGRESS OR OCCUPANCY.*
B01193203-I1
03/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Andres Arias Londono
03/11/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Andres Arias Londono
03/11/2025
Special inspection requirement — Energy Code Compliance Inspections
Andres Arias Londono
03/11/2025
Special inspection requirement — Final
Andres Arias Londono
03/11/2025
Special inspection requirement — Air barrier - visual inspection
Andres Arias Londono
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offCENTURION SOLAR ENERGY04/08/2025
3 projects · most recent 12/05/2025
General Wiring
FiledStatusContractorScope
12/05/2025Permit IssuedVILLAGE ELECTL CONTRS INC1 meters, 1 new_meters
03/20/2025CompleteVILLAGE ELECTL CONTRS INCGeneral Wiring
03/12/2025CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/11/2025Fire-Resistant Penetrations and JointsAndres Arias Londonospecial
03/11/2025Structural Stability – Alterations of existing buildingsAndres Arias Londonospecial
03/11/2025Energy Code Compliance InspectionsAndres Arias Londonoprogress
03/11/2025FinalAndres Arias Londonoprogress
03/11/2025Air barrier - visual inspectionAndres Arias Londonoenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/22/2026B01193203-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/29/2026B01193203-I1Open ↗
08/29/2026B01193203-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026B01193203-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/29/2026B01193203-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B01193203-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01193203-I1Open ↗