1910Year Built
3Stories
K4Building Class
C6-1GZoning
4,875 sfGross Floor Area
2Units
2 Open Violations 0 unresolved · 2 paperwork only ▸FDNY Report ↗
Predominantly retail with other uses · Owner of record: UNITED 17 DIVISION LLC · 1,756 sf lot · 2.78 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Permit Issued — active, not yet Signed-off
Roof24p · 1 filing · 20 docs
Floor 724p · 1 filing · 20 docs
Floor 626p · 1 filing · 20 docs
Floor 523p · 1 filing · 20 docs
Floor 423p · 1 filing · 20 docs
Floor 3Under Construction28p · 2 filings · 20 docs
Floor 2Under Construction27p · 2 filings · 20 docs
Floor 1Under Construction27p · 2 filings · 20 docs
CellarUnder Construction31p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SAFE-SHIELD ENTERPRISES1107/08/2026
JABBIE INDUSTRIES INCORP*403/22/2026
UNITED 17 DIVISION LLC103/22/2026
W 8 ELECTRIC103/22/2026
ROCKLINE103/22/2026
BELTTECH @ DIVISION # 201103/22/2026
BELTTECH AT DIVISION # 20103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
02/02/2023$3.7M—BELTTECH AT DIVISION, LLC → UNITED 17 DIVISION LLC$759/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
A PLUS DESIGN INC1809/05/2025
JOEL PHAGOO P.E. PLLC112/02/2024
ASHRAF CORP310/27/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
A PLUS DESIGN INC.3603/21/2026
DANICO SERVICES603/21/2026
SAFE-SHIELD ENTERPRISES203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JABBIE INDUSTRIES INCORP*General Contractor2107/08/2026
CATMAN PLUMBING INCPlumbing307/08/2026
SAFE-SHEILD ENTERPRISE INGeneral Contractor207/08/2026
CASE PLUMBING LLCFire Protection107/08/2026
QMB PLUMBING & HEATING INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
SD TESTING & INSPECTION S70101009/05/2025
FRANCISCO D. PEREZ PE3306403/04/2025
JOEL PHAGOO ,PE, PLLC2416112/02/2024
A PLUS DESIGN INC6615202/17/2023
Building Lifecycle
All (134)Filed (22)Permit Issued (16)Signed Off (9)Violation (13)Inspection (24)Objection (20)Special Inspection (30)
04/29/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
ERECT TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT-CO APPLICATION.
M00894540-S4
04/29/2026
Inspection — Fail-Final PL - Up to 9 Requested Floors
Fail
View inspection ↗
04/21/2026
Signed off — ALT-CO - New Building with Existing Elements to Remain
ERECT TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT-CO APPLICATION.
M00894540-S3
04/09/2026
Inspection — Certified Sprinkler (SP) - Booster Pump Test
Certified
View inspection ↗
04/07/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/02/2026
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/26/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/19/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
ERECT TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT-CO APPLICATION.
M00894540-Z1
12/12/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
ERECT TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT-CO APPLICATION.
M00894540-S5
12/10/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/04/2025
Violation issued (FDNY_ORDER, closed)
11/25/2025
Inspection — Fail-Final PL Permit Withdrawal
Fail
View inspection ↗
11/20/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
10/24/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
10/22/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
10/06/2025
Special inspection requirement — Air barrier - visual inspection
XIUCHENG LI
10/06/2025
Special inspection requirement — Insulation placement and R values
XIUCHENG LI
10/06/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIUCHENG LI
10/06/2025
Special inspection requirement — Metering
XIUCHENG LI
10/06/2025
Special inspection requirement — Lighting controls
XIUCHENG LI
10/06/2025
Special inspection requirement — Interior lighting power
XIUCHENG LI
10/06/2025
Special inspection requirement — Maintenance information
XIUCHENG LI
10/06/2025
Special inspection requirement — Energy Code Compliance Inspections
XIUCHENG LI
10/06/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
XIUCHENG LI
10/06/2025
Special inspection requirement — Fenestration areas
XIUCHENG LI
10/06/2025
Special inspection requirement — Fire-Resistance Rated Construction
XIUCHENG LI
10/06/2025
Special inspection requirement — Protection of exposed foundation insulation
XIUCHENG LI
10/06/2025
Special inspection requirement — Fenestration air leakage
XIUCHENG LI
10/06/2025
Special inspection requirement — Air barrier continuity plan testing
XIUCHENG LI
10/06/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
XIUCHENG LI
10/06/2025
Special inspection requirement — Air barrier — testing
XIUCHENG LI
10/06/2025
Special inspection requirement — Exterior lighting power
XIUCHENG LI
10/06/2025
Special inspection requirement — Electrical motors and elevators
XIUCHENG LI
09/24/2025
Objection raised — Scope
09/24/2025
Objection resolved — Addressed
09/10/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
ERECT TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT-CO APPLICATION.
M00894540-S6
09/05/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
ERECT TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT-CO APPLICATION.
M00894540-P9
08/29/2025
Inspection — Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test
Certified
View inspection ↗
08/29/2025
Special inspection requirement — Fenestration air leakage
XIUCHENG LI
08/29/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
XIUCHENG LI
08/29/2025
Special inspection requirement — Fenestration areas
XIUCHENG LI
08/29/2025
Special inspection requirement — Exterior lighting power
XIUCHENG LI
08/29/2025
Special inspection requirement — Air barrier — testing
XIUCHENG LI
08/29/2025
Special inspection requirement — Lighting controls
XIUCHENG LI
08/29/2025
Special inspection requirement — Energy Code Compliance Inspections
XIUCHENG LI
08/29/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
XIUCHENG LI
08/29/2025
Special inspection requirement — Fire-Resistance Rated Construction
XIUCHENG LI
08/29/2025
Special inspection requirement — Air barrier continuity plan testing
XIUCHENG LI
08/29/2025
Special inspection requirement — Electrical motors and elevators
XIUCHENG LI
08/29/2025
Special inspection requirement — Maintenance information
XIUCHENG LI
08/20/2025
Inspection — Certified Sprinkler-SP-Fixtures-Finish
Certified
View inspection ↗
08/11/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
ERECT TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT-CO APPLICATION.
M00894540-P8
06/24/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
06/20/2025
Permit issued — Plumbing
M00894540-S3-PL
06/20/2025
Violation issued (ECB, closed)
Construction
06/20/2025
Violation issued (ECB, closed)
Unknown
06/20/2025
Violation issued (ECB, closed)
Construction
06/11/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
ERECT TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT-CO APPLICATION.
M00894540-P7
06/10/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
ERECT TEMPORARY CONSTRUCTION FENCE IN CONJUNCTION WITH ALT-CO APPLICATION.
M00894540-P5
05/16/2025
Permit issued — Mechanical Systems
M00894540-S5-MS
Latest 60 of 134 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offCATMAN PLUMBING INC06/20/2025
DOB NOWMechanical SystemsSigned-offJABBIE INDUSTRIES INCORP*05/16/2025
DOB NOWGeneral ConstructionPermit IssuedJABBIE INDUSTRIES INCORP*05/14/2025
DOB NOWPlumbingSigned-offQMB PLUMBING & HEATING INC04/09/2025
DOB NOWSprinklersSigned-offS & L PLUMBING INC02/24/2025
DOB NOWSupported ScaffoldSigned-offSAFE-SHEILD ENTERPRISE IN12/03/2024
DOB NOWGeneral ConstructionPermit IssuedJABBIE INDUSTRIES INCORP*10/15/2024
DOB NOWStructuralSigned-offJABBIE INDUSTRIES INCORP*08/06/2024
DOB NOWEarth WorkSigned-offJABBIE INDUSTRIES INCORP*07/16/2024
DOB NOWGeneral ConstructionPermit IssuedJABBIE INDUSTRIES INCORP*07/16/2024
DOB NOWConstruction FenceSigned-offJABBIE INDUSTRIES INCORP*07/15/2024
DOB NOWSidewalk ShedSigned-offSAFE-SHEILD ENTERPRISE IN06/28/2024
DOB NOWPlumbingSigned-offCATMAN PLUMBING INC06/26/2024
DOB NOWGeneral ConstructionPermit IssuedJABBIE INDUSTRIES INCORP*05/23/2024
DOB NOWGeneral ConstructionPermit IssuedJABBIE INDUSTRIES INCORP*04/16/2024
DOB NOWPlumbingPermit IssuedCATMAN PLUMBING INC03/15/2023
BISPLISSUEDPINNACLE PLBG & HTG CORP12/10/2007
BISOTISSUEDYU YE CONTRUCTION INC07/03/2003
BISFPISSUEDNY BUSINESS FIRE SYSTEM INC10/23/2002
BISPLISSUEDAMOK INC09/17/1996
BISFPISSUEDMETFLOW FIRE CONTROL LLC08/30/1996
BISEQISSUEDAMERICAN SCAFFOLD CORP.07/05/1996
BISMHRE-ISSUEDFUNG SHING CONSTRUCTION CORP03/25/1993
BISEQRE-ISSUEDFUNG SHING CONSTRUCTION CORP03/25/1993
BISFPISSUEDIDEAL FIRE CONTROL INC06/05/1992
1 project · most recent 09/05/2025
Heating and Air Conditioning Systems Ventilation Systems
FiledStatusContractorScopeMake / Model / Capacity
09/05/2025Signed-offJABBIE INDUSTRIES INCORP*Heating and Air Conditioning Systems, Ventilation Systems
Heat / Cool
Mitsubishi Electric PLFY-P12NFMU-E 13,500 BTU · Vrf Indoor ×26
PLFY-P08NFMU-E 9,000 BTU · Vrf Indoor ×18
MSZ-SM48NAM2 50,000 BTU · Heat Pump Outdoor ×4
PLFY-P15NFMU-E 17,000 BTU · Vrf Indoor ×8
MXZ-SM60NAM2 66,000 BTU · Heat Pump Outdoor ×6
PLFY-EP24NEMU-E 27,000 BTU · Vrf Indoor ×6
PEFY-P12NMAU-E4 13,500 BTU · Vrf Indoor ×4
SLZ-KF09NA1 11,000 BTU · Vrf Indoor ×4
MSZ-GL12NA 14,400 BTU · Fan Coil Indoor ×2
MUZ-GL12NA 14,400 BTU · Heat Pump Outdoor ×2
MXZ-2C20NA4 22,000 BTU · Heat Pump Outdoor ×2
MXZ-SM36NAM2 41,000 BTU · Heat Pump Outdoor ×2
MXZ-SM48NAM2 50,000 BTU · Heat Pump Outdoor ×4
Daikin FTX12NMVJUA 13,400 BTU · Fan Coil Indoor ×2
RXL12QMVJU9A 13,400 BTU · Heat Pump Outdoor ×2
Ventilation
Greenheck G-095-VG 400 CFM · Exhaust Fan ×2
1 project · most recent 09/05/2025
Sprinkler System
FiledStatusContractorScope
09/05/2025Signed-offCASE PLUMBING LLCSprinkler System
1 project · most recent 09/05/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
09/05/2025Signed-offCATMAN PLUMBING INCGas, Storm, Water/Sanitary
4 projects · most recent 10/17/2025
General Wiring
FiledStatusContractorScope
10/17/2025CompleteW 8 ELECTRIC CORPGeneral Wiring
10/03/2025CompleteW 8 ELECTRIC CORPGeneral Wiring
06/27/2024CompleteK.N.C ELECTRIC INC—
02/22/2023CompleteW 8 ELECTRIC CORPGeneral Wiring
1 project · most recent 09/05/2025
Steel
FiledStatusContractorScope
09/05/2025Signed-offCATMAN PLUMBING INCSteel
1 project · most recent 09/05/2025
Fence
FiledStatusContractorScope
09/05/2025Signed-offCATMAN PLUMBING INCFence
1 project · most recent 09/05/2025
Construction Fence Earthwork
FiledStatusContractorScope
09/05/2025Signed-offCATMAN PLUMBING INCConstruction Fence, Earthwork
▾Field Inspections (DOB CAP) — 24
DateTypeResultReport
04/29/2026Fail-Final PL - Up to 9 Requested FloorsFailView ↗
04/09/2026Certified Sprinkler (SP) - Booster Pump TestCertifiedView ↗
04/07/2026Pass-Final CND-Occupancy InspectionPassView ↗
02/02/2026Pass-Final CND-Occupancy InspectionPassView ↗
12/26/2025Pass-Final CND-Occupancy InspectionPassView ↗
12/10/2025Pass-Final CND-Occupancy InspectionPassView ↗
11/25/2025Fail-Final PL Permit WithdrawalFailView ↗
11/20/2025Pass-Final CND-Occupancy InspectionPassView ↗
10/24/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
10/22/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/29/2025Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic TestCertifiedView ↗
08/20/2025Certified Sprinkler-SP-Fixtures-FinishCertifiedView ↗
06/24/2025Pass-Final CND-Occupancy InspectionPassView ↗
04/30/2025Certified Storm Drainage-ST-Piping-RoughingCertifiedView ↗
04/30/2025Pass-Final CND-Occupancy InspectionPassView ↗
04/24/2025Pass-Final House ConnectionPassView ↗
04/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
12/11/2024Certified Storm Drainage-ST-Piping-UndergroundCertifiedView ↗
12/11/2024Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
09/09/2024Pass-Final CND-Occupancy InspectionPassView ↗
09/06/2024Pass-Final CND-Occupancy InspectionPassView ↗
08/12/2024Pass-Final CND-Occupancy InspectionPassView ↗
08/07/2024Fail-Final CND-Occupancy InspectionFailView ↗
12/01/2022Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 150
DateRequirementInspectorRole
10/06/2025Structural Stability – Alterations of existing buildingsXIUCHENG LIspecial
10/06/2025Fire-Resistant Penetrations and JointsXIUCHENG LIspecial
10/06/2025Fire-Resistance Rated ConstructionXIUCHENG LIprogress
10/06/2025Energy Code Compliance InspectionsXIUCHENG LIprogress
10/06/2025Interior lighting powerXIUCHENG LIenergy_progress
10/06/2025Protection of exposed foundation insulationXIUCHENG LIenergy_progress
10/06/2025Fenestration areasXIUCHENG LIenergy_progress
10/06/2025Maintenance informationXIUCHENG LIenergy_progress
10/06/2025Electrical motors and elevatorsXIUCHENG LIenergy_progress
10/06/2025Insulation placement and R valuesXIUCHENG LIenergy_progress
10/06/2025Air barrier continuity plan testingXIUCHENG LIenergy_progress
10/06/2025Lighting controlsXIUCHENG LIenergy_progress
10/06/2025Air barrier - visual inspectionXIUCHENG LIenergy_progress
10/06/2025MeteringXIUCHENG LIenergy_progress
10/06/2025Fenestration air leakageXIUCHENG LIenergy_progress
10/06/2025Fenestration and door U-factor and product ratingsXIUCHENG LIenergy_progress
10/06/2025Air barrier — testingXIUCHENG LIenergy_progress
10/06/2025Exterior lighting powerXIUCHENG LIenergy_progress
08/29/2025Structural Stability – Alterations of existing buildingsXIUCHENG LIspecial
08/29/2025Insulation placement and R valuesXIUCHENG LIenergy_progress
08/29/2025MeteringXIUCHENG LIenergy_progress
08/29/2025Air barrier - visual inspectionXIUCHENG LIenergy_progress
08/29/2025Fenestration and door U-factor and product ratingsXIUCHENG LIenergy_progress
08/29/2025Protection of exposed foundation insulationXIUCHENG LIenergy_progress
08/29/2025Interior lighting powerXIUCHENG LIenergy_progress
Latest 25 of 150.
▾Documents — 163 on file (BIS + DOB NOW)
▸Plans & Drawings20
▸DOB NOWPlans/Sketch20
08/31/2026M08045150-S1Request digital key ↗
08/31/2026M08045150-I1Request digital key ↗
08/27/2026M00894540-P1Request digital key ↗
Showing 3 of 20 on file for this type
▸Applications & Permits7
▸BISPLAN / WORK APPROVAL APPLICATION6
12/17/2025100597711Open ↗
12/08/2025101375566Open ↗
11/10/2025101333807Open ↗
Showing 3 of 6 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation1
06/20/2025141026645Open ↗
▸Zoning, Tax Lot & Property Records15
▸DOB NOWZD1: DOB Zoning Diagram7
08/27/2026M00894540-A4Open ↗
08/27/2026M00894540-P3Open ↗
08/27/2026M00894540-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWZoning Exhibit form (1-5)7
08/27/2026M00894540-A4Open ↗
08/27/2026M00894540-P3Open ↗
08/27/2026M00894540-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026M00894540-I1Open ↗
▸Seals & Professional Certifications73
▸DOB NOWProgress Inspector Seal & Signature33
08/23/2026M08045150-I1Open ↗
08/23/2026M08045150-I1Open ↗
08/23/2026M08045150-I1Open ↗
Showing 3 of 33 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature20
08/31/2026M08045150-I1Open ↗
08/31/2026M08045150-S1Open ↗
08/27/2026M00894540-S3Open ↗
Showing 3 of 20 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature18
08/25/2026M01085568-I1Open ↗
08/23/2026M08045150-I1Open ↗
08/22/2026M00894540-P3Open ↗
Showing 3 of 18 on file for this type
▸BISAPPLICANT OWNER SIGNATURE1
03/25/2025141026645Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
03/25/2025141026645Open ↗
▸Trade Schedules & Equipment7
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)7
08/27/2026M00894540-A4Open ↗
08/27/2026M00894540-P3Open ↗
08/27/2026M00894540-P2Open ↗
Showing 3 of 7 on file for this type
▸Safety & Tenant Protection4
▸BISBPP: STREET TREES SITE PLAN1
03/25/2025141026645Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026M00894540-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026M00894540-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026M00894540-I1Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form8
08/27/2026M00894540-S2Open ↗
08/27/2026M00894540-S3Open ↗
08/27/2026M00894540-I1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDEP ACP-5: Asbestos Assessment Report2
08/31/2026M08045150-I1Open ↗
08/31/2026M08045150-S1Open ↗
▸Approvals, Objections & Sign-offs1
▸BISBPP-8 - Request Items for Builders Pavement Plan Signoff1
01/05/2026141026645Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
03/25/2025141026645Open ↗
▸Other Documents25
▸DOB NOWSite Survey: Initial7
08/27/2026M00894540-A4Open ↗
08/27/2026M00894540-P3Open ↗
08/27/2026M00894540-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone7
08/27/2026M00894540-A4Open ↗
08/27/2026M00894540-P3Open ↗
08/27/2026M00894540-P2Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWProperty Ownership Certification7
08/27/2026M00894540-A4Open ↗
08/27/2026M00894540-P3Open ↗
08/27/2026M00894540-P2Open ↗
Showing 3 of 7 on file for this type
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
03/25/2025141026645Open ↗
▸BISBPP - SUPPORTING DOCUMENTATION1
03/25/2025141026645Open ↗
▸DOB NOWAdjoining Owners Notification1
08/27/2026M00894540-S1Open ↗
▸DOB NOWFinal Survey1
08/13/2026M00894540-I1Open ↗