| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/01/2023 | Permit Issued | ADVANCED PLUMBING LLC | 1 heads, 2 outlets |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/14/2024 | Complete | A.S.K. ELECTRICAL CORP | General Wiring |
| 12/04/2023 | Complete | A.S.K. ELECTRICAL CORP | — |
| 04/24/2022 | Permit Issued | V. VASS ELECTRIC CORP | — |
| 11/26/2019 | Complete | T. MCCAFFREY-T. MCGOVERN | — |
| 04/29/2019 | Permit Issued | DIDONATO & SONS ELCL CONT | HVAC Wiring |
| 05/21/2018 | Permit Issued | DIDONATO & SONS ELCL CONT | 2 meters, 2 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/09/2026 | — | — | 1 scope_items |
| 06/22/2026 | Permit Issued | MNR RESTORATION GROUP INC | Steel, Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/04/2026 | Permit Issued | CONSOLIDATED SCAFFOLDING | Scaffold |
| 07/02/2026 | Permit Issued | MNR RESTORATION GROUP INC | Scaffold |
| 02/22/2023 | Permit Issued | CONSOLIDATED SCAFFOLDING | Scaffold, Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/22/2026 | Permit Issued | MNR GROUP INC | Suspended Scaffold (SC) |
| Owner | Filings | Most Recent |
|---|---|---|
| CBE | 6 | 08/29/2026 |
| JERRICK ASSOCIATES | 10 | 07/08/2026 |
| TAURINO MANAGEMENT | 6 | 03/22/2026 |
| SEVENTEEN DEVELOPMENT | 2 | 03/22/2026 |
| ARQ PAITING CONTRA. CO. | 1 | 03/22/2026 |
| OWNER OF PREMISES | 1 | 03/22/2026 |
| SEAN PRECISION CONSTRUCTION OF NEW YORK INC. | 1 | 03/22/2026 |
| PROCIDA CONSTRUCTION | 2 | 03/21/2026 |
| 17 DEVELOPMENT | 6 | 03/21/2026 |
| 271 NASSAU RLTY | 1 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| PAUL G. JONES, P.E. | 2 | 08/04/2026 |
| MAYTA + SEBASTIAN ARCHITECTURE DPC | 2 | 07/09/2026 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 07/02/2026 |
| SONI ENGINEERING CONSULTING | 1 | 05/22/2026 |
| GILSANZ MURRAY STEFICEK LLP | 3 | 11/18/2025 |
| TULLER/MCNEALUS/FELD | 1 | 04/01/2024 |
| ALTIERISEBORWIEBER LLC | 6 | 03/20/2024 |
| MURPHY BURNHAM & BUTTRICK ARCHITECT | 2 | 03/20/2024 |
| ASHRAF CORP | 1 | 01/18/2024 |
| EP ENGINEERING LLC | 3 | 11/01/2023 |
| SYED ENGINEERING, P.C. | 1 | 04/22/2022 |
| SAHEB ARCHITECTURE | 5 | 02/21/2020 |
| DOOLING & COMPANY ARCHITECTS | 1 | 11/18/2019 |
| PATUXENT ENGINEERING LLC | 1 | 10/30/2018 |
| BAILEYS ENGINEERING PC | 1 | 11/15/2017 |
| Representative | Filings | Most Recent |
|---|---|---|
| RPO | 28 | 03/21/2026 |
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| JNG ARCH | 3 | 03/21/2026 |
| PATUXENT ENGINEERING | 2 | 03/21/2026 |
| CONSOLIDATED SCAFFOLD BRIDGE | 2 | 03/21/2026 |
| DOMANI CONSULTING | 1 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CONSOLIDATED SCAFFOLDING | General Contractor | 22 | 08/26/2026 |
| TAURINO MANAGEMENT, INC | General Contractor | 12 | 07/08/2026 |
| JERRICK ASSOCIATES INC | General Contractor | 11 | 07/08/2026 |
| SILVERCUP SCFFLDNG I LLC | General Contractor | 6 | 03/21/2026 |
| ADVANCED PLUMBING LLC | Fire Protection | 4 | 07/08/2026 |
| ANDAMIO SCAFFOLDING LLC | General Contractor | 3 | 03/21/2026 |
| DEMAR MECHANICAL INC | Plumbing | 2 | 03/22/2026 |
| MNR RESTORATION GROUP INC | General Contractor | 2 | 08/05/2026 |
| PARISH PROPERTY MANAGEMENT | General Contractor | 2 | 07/03/2026 |
| A S K ELECTRICAL CORP 005034 | General Contractor | 1 | 03/22/2026 |
| DEMAR PLUMBING CORP | Fire Protection | 1 | 07/08/2026 |
| DAVID KLEEMAN | Electrical | 1 | 03/21/2026 |
| GREGORY PAPANTONIOU | Electrical | 1 | 03/21/2026 |
| LELIS, ARILSON | Electrical | 1 | 03/21/2026 |
| NEU, RICHARD | Electrical | 1 | 03/21/2026 |
| OTTEN, GERALD | Electrical | 1 | 03/21/2026 |
| SERGIO GIANNACHI | Electrical | 1 | 03/21/2026 |
| T. MCCAFFREY-T. MCGOVERN | Electrical | 1 | 03/22/2026 |
| BEHNAMBAKHSH, SHAYAN | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| MAYTA + SEBASTIAN ARCHITE | 5890 | 2 | 07/09/2026 |
| KADAN CORP. | 5956 | 1 | 06/22/2026 |
| SONI ENGINEERING CONSULTI | 9819 | 1 | 05/22/2026 |
| AK ENGINEERING PC | 678 | 11 | 11/18/2025 |
| EP INSPECTIONS AND COMMIS | 7079 | 1 | 09/11/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Supported Scaffold | Permit Issued | CONSOLIDATED SCAFFOLDING | 08/04/2026 |
| DOB NOW | Structural | Permit Issued | MNR RESTORATION GROUP INC | 08/04/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | CONSOLIDATED SCAFFOLDING | 08/03/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | MNR RESTORATION GROUP INC | 07/09/2026 |
| DOB NOW | Structural | Signed-off | PARISH PROPERTY MANAGEMENT | 07/01/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | CONSOLIDATED SCAFFOLDING | 06/01/2026 |
| DOB NOW | Suspended Scaffold | Permit Issued | MNR GROUP INC | 05/27/2026 |
| DOB NOW | Structural | Signed-off | PARISH PROPERTY MANAGEMEN | 11/28/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | CONSOLIDATED SCAFFOLDING | 06/25/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | CONSOLIDATED SCAFFOLDING | 06/28/2024 |
| DOB NOW | Supported Scaffold | Signed-off | ANDAMIO SCAFFOLDING LLC | 01/22/2024 |
| DOB NOW | Sprinklers | Signed-off | DEMAR PLUMBING CORP | 01/03/2024 |
| DOB NOW | Structural | Signed-off | TAURINO MANAGEMENT, INC | 01/02/2024 |
| DOB NOW | Mechanical Systems | Signed-off | TAURINO MANAGEMENT, INC | 01/02/2024 |
| DOB NOW | General Construction | Signed-off | TAURINO MANAGEMENT, INC | 01/02/2024 |
| DOB NOW | Plumbing | Signed-off | DEMAR MECHANICAL INC | 12/07/2023 |
| DOB NOW | Mechanical Systems | Signed-off | TAURINO MANAGEMENT, INC | 12/06/2023 |
| DOB NOW | Structural | Signed-off | TAURINO MANAGEMENT, INC | 12/06/2023 |
| DOB NOW | General Construction | Signed-off | TAURINO MANAGEMENT, INC | 12/06/2023 |
| DOB NOW | Supported Scaffold | Signed-off | CONSOLIDATED SCAFFOLDING | 07/13/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | CONSOLIDATED SCAFFOLDING | 07/12/2023 |
| DOB NOW | Supported Scaffold | Signed-off | CONSOLIDATED SCAFFOLDING | 07/11/2023 |
| DOB NOW | Sprinklers | Permit Issued | ADVANCED PLUMBING LLC | 04/18/2023 |
| DOB NOW | Standpipe | Signed-off | ADVANCED PLUMBING LLC | 04/18/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSOLIDATED SCAFFOLDING | 04/05/2023 |
| DOB NOW | Sidewalk Shed | Permit Issued | CONSOLIDATED SCAFFOLDING | 02/22/2023 |
| DOB NOW | Supported Scaffold | Signed-off | CONSOLIDATED SCAFFOLDING | 04/22/2022 |
| DOB NOW | Sidewalk Shed | Signed-off | CONSOLIDATED SCAFFOLDING | 04/22/2022 |
| DOB NOW | Sprinklers | Permit Issued | ADVANCED PLUMBING LLC | 08/13/2021 |
| DOB NOW | Standpipe | Signed-off | ADVANCED PLUMBING LLC | 08/13/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 03/17/2021 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 03/18/2020 |
| DOB NOW | Supported Scaffold | Permit Issued | GE 2A CONSTRUCTION | 03/17/2020 |
| DOB NOW | Supported Scaffold | Permit Issued | GE 2A CONSTRUCTION | 11/19/2019 |
| DOB NOW | Supported Scaffold | Permit Issued | SILVERCUP SCFFLDNG I LLC | 07/29/2019 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 04/11/2019 |
| DOB NOW | Supported Scaffold | Permit Issued | SILVERCUP SCFFLDNG I LLC | 10/31/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 03/29/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | GE 2A CONSTRUCTION | 11/15/2017 |
| BIS | OT | ISSUED | JERRICK ASSOCIATES INC | 03/19/2021 |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/24/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/03/2024 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/08/2024 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 05/03/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 05/03/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 02/08/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/01/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 11/29/2023 | Pass-Final SD - Up to 3 Requested Floors | Pass | View ↗ |
| 10/16/2023 | Pass-Final SD - Up to 3 Requested Floors | Pass | View ↗ |
| 10/16/2023 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 10/10/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/10/2023 | Certified StandPipe-SD-Piping-Hydrostatic Test | Certified | View ↗ |
| 10/09/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/06/2023 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/12/2026 | Post-installed Anchors | Raul Mayta | special |
| 06/12/2026 | Masonry | Raul Mayta | special |
| 06/12/2026 | Structural Steel - Details | GEORGE OZAETA | special |
| 06/12/2026 | Structural Steel - Welding | GEORGE OZAETA | special |
| 06/12/2026 | Structural Steel - High Strength Bolting | GEORGE OZAETA | special |
| 06/12/2026 | Structural Stability – Alterations of existing buildings | GEORGE OZAETA | special |
| 04/03/2026 | Structural Stability – Alterations of existing buildings | — | special |
| 04/03/2026 | Post-installed Anchors | Raul Mayta | special |
| 03/30/2026 | Final | — | progress |
| 02/23/2026 | Final | Raul Mayta | progress |
| 04/11/2024 | Structural Steel - Welding | Ari Kamo | special |
| 04/11/2024 | Structural Steel - Details | Ari Kamo | special |
| 04/11/2024 | Structural Steel - High Strength Bolting | Ari Kamo | special |
| 04/11/2024 | Concrete - Cast-In-Place | Ari Kamo | special |
| 04/11/2024 | Structural Stability – Alterations of existing buildings | Ari Kamo | special |
| 04/11/2024 | Construction Operations Influencing Adjacent Structures | Ari Kamo | special |
| 04/11/2024 | Sprayed fire-resistant materials | Ari Kamo | special |
| 04/11/2024 | Final | Ari Kamo | progress |
| 03/29/2024 | Fire-Resistance Rated Construction | Ari Kamo | progress |
| 03/29/2024 | Sprayed fire-resistant materials | Ari Kamo | special |
| 03/29/2024 | Final | Ari Kamo | progress |
| 03/29/2024 | Fire-Resistant Penetrations and Joints | Ari Kamo | special |
| 03/28/2024 | Heating Systems | Ari Kamo | special |
| 03/28/2024 | Mechanical Systems | Ari Kamo | special |
| 03/28/2024 | Final | Ari Kamo | progress |