| Owner | Filings | Most Recent |
|---|---|---|
| DIKRAN PROPERTIES | 11 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| RMM DESIGN STUDIO | 1 | 04/02/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| EBC CONSULTING | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| FLOW STATE ELECTRIC, LLC | Electrical | 1 | 03/22/2026 |
| GEORGE CHAVEZ | Electrical | 1 | 03/21/2026 |
| JERON WALKER | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| WORLD DESIGN ARCHITECTURE | 9323 | 1 | 04/02/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| BIS | PL | ISSUED | MJ GENERAL MECHANICAL LLC | 09/06/2023 |
| BIS | PL | ISSUED | MJ GENERAL MECHANICAL LLC | 08/18/2022 |
| BIS | — | ISSUED | MARTE CONSTRUCTION INC | 08/12/2022 |
| BIS | — | ISSUED | MARTE CONSTRUCTION INC | 08/05/2021 |
| BIS | PL | ISSUED | MJ GENERAL MECHANICAL LLC | 02/23/2021 |
| BIS | — | ISSUED | MARTE CONSTRUCTION INC | 08/11/2020 |
| BIS | — | ISSUED | MARTE CONSTRUCTION INC | 01/06/2020 |
| BIS | PL | ISSUED | MJ GENERAL MECHANICAL LLC | 12/24/2019 |
| BIS | PL | ISSUED | SP PLUMBING AND HEATING | 04/02/2019 |
| BIS | — | ISSUED | MARTE CONSTRUCTION INC | 03/19/2019 |
| BIS | PL | ISSUED | EMPIRE STATE PLBG & HTG C | 01/25/2005 |
| BIS | OT | ISSUED | ARTECH RENOV. CORP | 04/14/2004 |
| BIS | OT | ISSUED | QUALITY BUILDING CONTRACTOR INC | 10/16/2003 |
| BIS | MH | ISSUED | CONSTRUX LLC | 05/02/2002 |
| BIS | — | ISSUED | JOSEPHINE BAY PAUL | 04/22/2002 |
| BIS | OT | ISSUED | CONSTRUX LLC | 08/14/2000 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/12/2025 | Complete | GMJ ELECTRIC CORP | General Wiring |
| 09/22/2024 | Cancelled | FLOW STATE ELECTRIC, LLC | — |
| 08/01/2022 | Complete | GMJ ELECTRIC CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/02/2025 | — | — | 27 panels, 14.8 kw, 750.6 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/26/2025 | Fire-Resistant Penetrations and Joints | William Alicea | special |
| 03/26/2025 | Structural Stability – Alterations of existing buildings | William Alicea | special |
| 03/26/2025 | Energy Code Compliance Inspections | William Alicea | progress |
| 03/26/2025 | Final | RICHARD MUESCH JR. | progress |
| 03/26/2025 | Air barrier - visual inspection | William Alicea | energy_progress |