| Firm | Filings | Most Recent |
|---|---|---|
| Design Group in H&K | 8 | 08/18/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| Design Group in H K | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Nextcom Construction | General Contractor | 2 | 07/08/2026 |
| Nextcom Construction | Scaffold | 1 | 04/09/2026 |
| Power Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Chong Engineering | 7411 | 7 | 08/18/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | Power Plumbing & Heating | 09/19/2025 |
| DOB NOW | Construction Fence | Signed-off | Nextcom Construction | 09/10/2025 |
| DOB NOW | General Construction | Permit Issued | Nextcom Construction | 09/04/2025 |
| DOB NOW | Mechanical Systems | Signed-off | Nextcom Construction | 09/04/2025 |
| BIS | OT | ISSUED | Trinity Solar | 09/04/2020 |
| BIS | PL | ISSUED | Flint Mechanical | 06/21/2011 |
| BIS | OT | ISSUED | P & A Pinting | 07/22/1999 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Signed-off | Nextcom Construction | Heating and Air Conditioning Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Signed-off | Power Plumbing & Heating | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/08/2025 | Complete | Power Electrical Conts | General Wiring |
| 09/10/2020 | Complete | Redline Electric | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Signed-off | Power Plumbing & Heating | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/18/2026 | Signed-off | Power Plumbing & Heating | Construction Fence |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/10/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 02/26/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 02/06/2026 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| 11/21/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 11/21/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/18/2026 | Interior lighting power | Tae Chong | energy_progress |
| 08/18/2026 | Fire-Resistant Penetrations and Joints | Tae Chong | special |
| 08/18/2026 | Structural Stability – Alterations of existing buildings | Tae Chong | special |
| 08/18/2026 | Energy Code Compliance Inspections | Tae Chong | progress |
| 08/18/2026 | Fire-Resistance Rated Construction | Tae Chong | progress |
| 08/18/2026 | Fenestration areas | Tae Chong | energy_progress |
| 08/18/2026 | Permanent certificate | Tae Chong | energy_progress |
| 08/18/2026 | Insulation placement and R values | Tae Chong | energy_progress |
| 08/18/2026 | Fenestration and door U-factor and product ratings | Tae Chong | energy_progress |
| 08/18/2026 | Air barrier - visual inspection | Tae Chong | energy_progress |
| 08/18/2026 | Fenestration air leakage | Tae Chong | energy_progress |
| 03/16/2026 | Fire-Resistant Penetrations and Joints | Tae Chong | special |
| 03/16/2026 | Structural Stability – Alterations of existing buildings | Tae Chong | special |
| 03/16/2026 | Fire-Resistance Rated Construction | Tae Chong | progress |
| 03/16/2026 | Energy Code Compliance Inspections | Tae Chong | progress |
| 03/16/2026 | Fenestration areas | Tae Chong | energy_progress |
| 03/16/2026 | Insulation placement and R values | Tae Chong | energy_progress |
| 03/16/2026 | Interior lighting power | Tae Chong | energy_progress |
| 03/16/2026 | Fenestration and door U-factor and product ratings | Tae Chong | energy_progress |
| 03/16/2026 | Air barrier - visual inspection | Tae Chong | energy_progress |
| 03/16/2026 | Permanent certificate | Tae Chong | energy_progress |
| 03/16/2026 | Fenestration air leakage | Tae Chong | energy_progress |
| 02/12/2026 | Fire-Resistant Penetrations and Joints | Tae Chong | special |
| 02/10/2026 | Fire-Resistant Penetrations and Joints | Tae Chong | special |
| 03/25/2025 | Final | Tae Chong | progress |