| Owner | Filings | Most Recent |
|---|---|---|
| BBM CONSTRUCTION | 93 | 07/08/2026 |
| OWNERS REP | 12 | 07/08/2026 |
| 1619 SHEEPSHEAD BAY LLC | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| STUDIO GALLOS | 18 | 11/27/2024 |
| ELEVATED ENGINEERING NYC | 11 | 05/20/2024 |
| FL&M ENGINEERING DESIGN &INSPECTION | 2 | 04/13/2024 |
| PAUL PERDEK, PROF. ENG. PLLC | 1 | 12/13/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| SPEEDY EXPEDITING | 56 | 03/21/2026 |
| BSGNY | 2 | 03/21/2026 |
| THE GREEN STUDIO | 2 | 03/21/2026 |
| AE DESIGN SOLUTION | 2 | 03/21/2026 |
| MILLENNIUM DESIGNS | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BBM CONSTRUCTION CORP | General Contractor | 26 | 07/08/2026 |
| YOSEF BLAU | Electrical | 6 | 03/21/2026 |
| S R ELECTRICAL MECHANIC 005147 | General Contractor | 6 | 03/22/2026 |
| MANHATTAN D ENTERPRISES | General Contractor | 4 | 07/08/2026 |
| GWT ENTERPRISES INC | General Contractor | 2 | 07/08/2026 |
| CREATIVE PLUMBING IN | Plumbing | 1 | 07/08/2026 |
| METFLOW FIRE CONTROL LLC | Fire Protection | 1 | 07/08/2026 |
| POWERS BRIDGING & SCAFFOLDING | General Contractor | 1 | 07/08/2026 |
| FRANCISCO A NUNEZ | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 14 | 11/27/2024 |
| REGIONAL TESTING CORP. | 394 | 4 | 09/28/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Signed-off | BBM CONSTRUCTION CORP | 07/31/2024 |
| DOB NOW | Curb Cut | Signed-off | BBM CONSTRUCTION CORP | 07/24/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | BBM CONSTRUCTION CORP | 05/20/2024 |
| DOB NOW | Protection and Mechanical Methods | Signed-off | GWT ENTERPRISES INC | 04/15/2024 |
| DOB NOW | Support of Excavation | Signed-off | BBM CONSTRUCTION CORP | 04/05/2024 |
| DOB NOW | General Construction | Permit Issued | BBM CONSTRUCTION CORP | 04/05/2024 |
| DOB NOW | General Construction | Permit Issued | BBM CONSTRUCTION CORP | 02/21/2024 |
| DOB NOW | Mechanical Systems | Signed-off | BBM CONSTRUCTION CORP | 02/21/2024 |
| DOB NOW | Plumbing | Signed-off | AB PLUMBING INC | 02/20/2024 |
| DOB NOW | Sprinklers | Signed-off | METFLOW FIRE CONTROL LLC | 02/20/2024 |
| DOB NOW | Supported Scaffold | Signed-off | GWT ENTERPRISES INC | 01/06/2024 |
| DOB NOW | Supported Scaffold | Signed-off | MANHATTAN D ENTERPRISES | 01/02/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | MANHATTAN D ENTERPRISES | 01/02/2024 |
| DOB NOW | Structural | Signed-off | BBM CONSTRUCTION CORP | 12/18/2023 |
| DOB NOW | Support of Excavation | Signed-off | BBM CONSTRUCTION CORP | 12/01/2023 |
| DOB NOW | Support of Excavation | Signed-off | BBM CONSTRUCTION CORP | 08/08/2023 |
| DOB NOW | Support of Excavation | Signed-off | BBM CONSTRUCTION CORP | 08/07/2023 |
| DOB NOW | Earth Work | Signed-off | BBM CONSTRUCTION CORP | 08/04/2023 |
| DOB NOW | Construction Fence | Signed-off | BBM CONSTRUCTION CORP | 08/04/2023 |
| DOB NOW | Supported Scaffold | Signed-off | POWERS BRIDGING & SCAFFOL | 12/14/2022 |
| DOB NOW | Earth Work | Signed-off | BBM CONSTRUCTION CORP | 05/19/2022 |
| DOB NOW | Support of Excavation | Signed-off | BBM CONSTRUCTION CORP | 05/19/2022 |
| DOB NOW | Construction Fence | Signed-off | BBM CONSTRUCTION CORP | 05/13/2022 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/24/2024 | Complete | S&R ELECTRICAL & MECHANIC | General Wiring |
| 02/23/2024 | Complete | POWER DIRECT ELECTRIC INC | — |
| 02/01/2024 | Complete | S&R ELECTRICAL & MECHANIC | — |
| 12/07/2023 | Complete | SOLAS ELECTRICAL CORP | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/10/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 03/11/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/06/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/26/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/23/2024 | Certified Sprinkler (SP) - Booster Pump Test | Certified | View ↗ |
| 09/23/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/18/2024 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 08/30/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/30/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/28/2024 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 07/16/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/10/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 06/07/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 05/24/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 03/08/2024 | Pass-Final PL - Underground | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/09/2025 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 01/09/2025 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 01/09/2025 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 01/09/2025 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 01/09/2025 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 01/09/2025 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 01/09/2025 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 01/09/2025 | Metering | FAHAD FATEH | energy_progress |
| 01/09/2025 | Maintenance information | FAHAD FATEH | energy_progress |
| 01/09/2025 | Interior lighting power | FAHAD FATEH | energy_progress |
| 01/09/2025 | Fenestration areas | FAHAD FATEH | energy_progress |
| 01/09/2025 | Electrical motors and elevators | FAHAD FATEH | energy_progress |
| 01/09/2025 | Lighting controls | FAHAD FATEH | energy_progress |
| 01/09/2025 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 01/09/2025 | Lowest Floor Elevation | FAHAD FATEH | progress |
| 01/09/2025 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 01/09/2025 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 01/09/2025 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | FAHAD FATEH | special |
| 01/09/2025 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 10/29/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 10/29/2024 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 10/29/2024 | Electrical motors and elevators | FAHAD FATEH | energy_progress |
| 10/29/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 10/29/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 10/29/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |