| Owner | Filings | Most Recent |
|---|---|---|
| WEEKS CAPITAL ASSOCIATES LLC | 15 | 07/08/2026 |
| MJH CONSTRUCTION | 1 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/12/2024 | $800K | — | THE BRONX CHURCH OF GOD IN CHRIST → HOP PROPERTIES LLC | $254/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| ADB ASSOCIATES | 4 | 06/07/2024 |
| VASILIOS ARTEMIOU PE | 1 | 01/09/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| NYC DESIGN FILE | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MJH CONSTRUCTION CORP | General Contractor | 2 | 07/08/2026 |
| S&R ELECTRICAL & MECHANIC | Electrical | 1 | 03/22/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| A. M. PLUMBING COMPANY | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 5 | 06/07/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | A. M. PLUMBING COMPANY | 03/04/2024 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 03/01/2024 |
| DOB NOW | General Construction | Permit Issued | MJH CONSTRUCTION CORP | 02/29/2024 |
| DOB NOW | Mechanical Systems | Signed-off | MJH CONSTRUCTION CORP | 02/27/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 06/07/2024 | Permit Issued | MJH CONSTRUCTION CORP | Associated Ducts and Piping, Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Daikin RX12BXVJU 12,000 BTU · Heat Pump Outdoor ×8 RX12AXVJU 12,000 BTU · Condensing Unit ×6 3MXS24WMVJU9 24,000 BTU · Heat Pump Outdoor ×4 2MXS18WMVJU9 18,000 BTU · Heat Pump Outdoor ×2 Ventilation Ducts & Piping Masterflow masterflow 1 CFM ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/07/2024 | Signed-off | PRIME PIPING & HEATING IN | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/07/2024 | Signed-off | A. M. PLUMBING COMPANY | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/06/2024 | Complete | S&R ELECTRICAL & MECHANIC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/12/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 07/24/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/24/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/17/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 05/17/2024 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 05/14/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 05/14/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/08/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 03/27/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/11/2024 | Heating Systems | FAHAD FATEH | special |
| 06/11/2024 | Mechanical Systems | FAHAD FATEH | special |
| 06/11/2024 | Post-installed Anchors | FAHAD FATEH | special |
| 06/11/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 06/11/2024 | Final | FAHAD FATEH | progress |
| 06/11/2024 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 06/11/2024 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 06/11/2024 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 06/11/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 05/16/2024 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 05/16/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 05/16/2024 | Heating Systems | FAHAD FATEH | special |
| 05/16/2024 | Mechanical Systems | FAHAD FATEH | special |
| 05/16/2024 | Post-installed Anchors | FAHAD FATEH | special |
| 05/16/2024 | Final | FAHAD FATEH | progress |
| 05/16/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 05/16/2024 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 05/16/2024 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 01/08/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 01/08/2024 | Post-installed Anchors | FAHAD FATEH | special |
| 07/06/2023 | Sprinkler Systems | FAHAD FATEH | special |
| 05/24/2023 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 05/24/2023 | Fenestration areas | FAHAD FATEH | energy_progress |
| 05/24/2023 | Interior lighting power | FAHAD FATEH | energy_progress |
| 05/24/2023 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |