LL97 Covered12 Active Violations 0 unresolved · 12 paperwork only ▸FDNY Report ↗
Public elementary, junior or senior high · Owner of record: NYC Department of Parks and Recreation · 92,000 sf lot · 0.55 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalEquipmentGeneralOther
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofP.S. 32 Queens8p · 2 filings · 20 docs
Floor 3P.S. 32 Queens6p · 2 filings · 20 docs
Floor 2P.S. 32 Queens8p · 2 filings · 20 docs
Floor 1P.S. 32 Queens7p · 4 filings · 20 docs
CellarP.S. 32 Queens2p · 4 filings · 20 docs
Site & exteriorP.S. 32 Queens4p · 1 filing · 7 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
NYC School Construction Authority6107/08/2026
NYC Department of Education503/22/2026
School Authority103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Velocity Architectural Services PLL1312/04/2025
AK Consulting Services106/21/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Velocity Architecture & Engineering2203/21/2026
AK Consulting Services203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
MPCCGeneral Contractor707/08/2026
PMY ConstructionScaffold203/21/2026
Prince ElectricElectrical103/21/2026
L.P. Davis Electric CoElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Universal Testing and Ins4001012/04/2025
Building Lifecycle
All (119)Filed (14)Permit Issued (6)Signed Off (1)Violation (60)Objection (8)Special Inspection (30)
03/12/2026
Violation issued (ECB, open)
Construction
03/12/2026
Violation issued (ECB, open)
Construction
03/12/2026
Violation issued (ECB, open)
Construction
03/12/2026
Violation issued (ECB, open)
Construction
02/12/2026
Violation issued (FDNY_ORDER, closed)
02/12/2026
Violation issued (FDNY_ORDER, closed)
12/24/2025
Objection resolved — Addressed
12/24/2025
Special inspection requirement — Concrete - Cast-In-Place
NELSON LOPEZ
12/10/2025
Special inspection requirement — Final
NELSON LOPEZ
12/10/2025
Special inspection requirement — Post-installed Anchors
12/10/2025
Special inspection requirement — Mechanical Systems
NELSON LOPEZ
12/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/04/2025
Filed — Alteration
Selective removals furniture, built in, equipment, electrical devices, flooring, partitions, replacement of existing door/frame with new assemblies, new computer cabinetry, new finishes, replace existing opening with new window, remove ext. ramp, Fix lift
Q00663889-P4
12/04/2025
Special inspection requirement — Mechanical Systems
NELSON LOPEZ
12/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
12/04/2025
Special inspection requirement — Final
NELSON LOPEZ
12/04/2025
Special inspection requirement — Post-installed Anchors
10/23/2025
Violation issued (ECB, open)
Construction
10/23/2025
Violation issued (ECB, open)
Construction
10/23/2025
Violation issued (ECB, open)
Construction
10/22/2025
Violation issued (ECB, open)
Construction
09/26/2025
Violation issued (ECB, closed)
Construction
09/26/2025
Violation issued (ECB, closed)
Construction
09/26/2025
Violation issued (ECB, closed)
Construction
09/26/2025
Violation issued (ECB, closed)
Construction
09/26/2025
Violation issued (ECB, closed)
Construction
09/25/2025
Violation issued (FDNY_ORDER, closed)
07/25/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
07/25/2025
Special inspection requirement — Post-installed Anchors
07/25/2025
Special inspection requirement — Sprinkler Systems
07/18/2025
Permit issued — General Construction
Q00982771-I1-GC
07/18/2025
Permit issued — Mechanical Systems
Q00982771-S1-MS
07/15/2025
Permit issued — Mechanical Systems
Q00982771-S1-MS
07/14/2025
Special inspection requirement — Sprinkler Systems
05/19/2025
Objection resolved — Addressed
03/25/2025
Objection raised — Other
03/21/2025
Objection raised — Other
03/20/2025
Filed — Alteration
Selective removals furniture, built in, equipment, electrical devices, flooring, partitions, replacement of existing door/frame with new assemblies, new computer cabinetry, new finishes, replace existing opening with new window, remove ext. ramp, Fix lift
Q00663889-P3
03/19/2025
Filed — Alteration
Selective removals furniture, built in, equipment, electrical devices, flooring, partitions, replacement of existing door/frame with new assemblies, new computer cabinetry, new finishes, replace existing opening with new window, remove ext. ramp, Fix lift
Q00663889-P2
03/19/2025
Filed — Alteration
Selective removals furniture, built in, equipment, electrical devices, flooring, partitions, replacement of existing door/frame with new assemblies, new computer cabinetry, new finishes, replace existing opening with new window, remove ext. ramp, Fix lift
Q00663889-P1
03/19/2025
Special inspection requirement — Masonry
NELSON LOPEZ
03/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/17/2025
Special inspection requirement — Mechanical Systems
NELSON LOPEZ
03/17/2025
Special inspection requirement — Post-installed Anchors
03/17/2025
Special inspection requirement — Final
NELSON LOPEZ
03/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
03/17/2025
Special inspection requirement — Post-installed Anchors
03/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NELSON LOPEZ
03/17/2025
Special inspection requirement — Post-installed Anchors
NELSON LOPEZ
03/17/2025
Special inspection requirement — Fire-Resistance Rated Construction
NELSON LOPEZ
08/22/2024
Permit issued — General Construction
Q00982771-I1-GC
08/22/2024
Permit issued — Mechanical Systems
Q00982771-S1-MS
07/25/2024
Filed — Alteration
Provide new EF-1 on roof and associated ductwork, hangers and support, provide new fin tube radiators including enclosures.
Q00982771-P2
07/23/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
NELSON LOPEZ
07/23/2024
Special inspection requirement — Fire-Resistance Rated Construction
NELSON LOPEZ
07/23/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
NELSON LOPEZ
04/05/2024
Violation issued (ECB, open)
Construction
04/05/2024
Violation issued (ECB, closed)
Construction
04/05/2024
Violation issued (ECB, closed)
Construction
03/28/2024
Filed — Alteration
Provide new EF-1 on roof and associated ductwork, hangers and support, provide new fin tube radiators including enclosures.
Q00982771-P1
Latest 60 of 119 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedMPCC07/18/2025
DOB NOWMechanical SystemsPermit IssuedMPCC07/18/2025
DOB NOWMechanical SystemsPermit IssuedMPCC07/15/2025
DOB NOWGeneral ConstructionPermit IssuedMPCC08/22/2024
DOB NOWMechanical SystemsPermit IssuedMPCC08/22/2024
DOB NOWConstruction FenceSigned-offPMY Construction07/09/2021
BISOTISSUEDEarth Group04/10/2025
BISOTISSUEDEarth Group04/10/2025
BISOTISSUEDEarth Group04/24/2024
BISOTISSUEDEarth Group04/24/2024
BISPLISSUEDMar-Sal Plumbing & Heating06/29/2023
BISOTISSUEDEarth Group06/29/2023
BISOTISSUEDEarth Group05/01/2023
BISOTISSUEDPMY Construction08/31/2022
BISOTISSUEDPMY Construction08/31/2022
BISOTISSUEDPMY Construction08/30/2022
BISOTISSUEDPMY Construction08/30/2022
BISOTISSUEDPMY Construction12/01/2021
BISOTISSUEDPMY Construction12/01/2021
BISMHISSUEDChapman & Evans08/04/2021
BISPLISSUEDMar-Sal Plumbing & Heating07/28/2021
BISOTISSUEDPMY Construction07/28/2021
BISOTISSUEDPMY Construction07/28/2021
BISPLISSUEDMar-Sal Plumbing & Heating07/20/2021
BISOTISSUEDPMY Construction07/20/2021
BISOTISSUEDPMY Construction07/20/2021
BISMHISSUEDVolmar Construction05/27/2020
BISOTISSUEDGold Star Electrical02/20/2018
BISOTISSUEDGold Star Electrical10/24/2016
BISOTISSUEDGold Star Electrical07/11/2016
BISOTISSUEDAll Volts Electrical12/16/2015
BISOTISSUEDN H Construction01/08/2013
BISOTISSUEDN H Construction04/23/2012
BISOTISSUEDPositive Electric Associates10/06/2009
BISEQISSUEDPositive Electric Associates05/18/2009
BISEQISSUEDPositive Electric Associates12/26/2008
BISEQISSUEDYork Scaffold Equipment10/01/2008
BISEQISSUEDM.S.T. General Contracting06/12/2006
BISEQISSUEDJade Scaffolding03/01/2001
BISEQRE-ISSUEDJade Scaffolding01/23/2001
+ 12 more permits on file
2 projects · most recent 12/04/2025
Heating Systems Ventilation Systems Refrigeration Systems
FiledStatusContractorScopeMake / Model / Capacity
12/04/2025——Heating Systems, Refrigeration Systems, Ventilation Systems
Heating
Markel HF 27 kW · Electric Heater ×12
Trane VUV750 750 CFM · Fan Coil Indoor ×12
Qmark QCH1101F 3,413 BTU · Electric Heater ×6
Sterling LVS VC3/4.43 1,652 BTU · Radiant ×3
Ventilation
Titus TMS 395 CFM ×12
350RL 700 CFM · Exhaust Fan ×9
350RF 200 CFM ×3
Greenheck G-097-VG 225 CFM · Exhaust Fan ×6
G-060-VG 70 CFM · Exhaust Fan ×3
G-090-VG 370 CFM · Exhaust Fan ×3
Cube 240CP-VOD-15 1,760 CFM · Exhaust Fan
Beckett CB201TUL 120 kW · Pump ×9
Refrigeration
Lg ZARNU123M2A4 350 CFM · Vrf Indoor ×3
ZARNU243M2A4 620 CFM · Vrf Indoor ×3
ZARNU363B8A4 1,060 CFM · Vrf Indoor ×3
ZRUM036GSSO 36,000 BTU · Vrf Outdoor ×3
ZRUN024GSS0 24,000 BTU · Vrf Outdoor ×3
ZRUN024GSSO 24,000 BTU · Vrf Outdoor ×3
07/25/2024Permit IssuedMPCCHeating Systems, Ventilation Systems
Heating
Vulcan LVS VC3/4-45 2,350 BTU · Radiant ×8
Ventilation
Titus 350RL 420 CFM · Exhaust Fan ×8
Greenheck CUBE-240CP-VGD-15 1,760 CFM · Exhaust Fan ×4
1 project · most recent 12/04/2025
FiledStatusContractorScope
12/04/2025——6 heads
2 projects · most recent 12/04/2025
Water/Sanitary Plumbing-Sprinkler
FiledStatusContractorScope
12/04/2025——Plumbing-Sprinkler, Water/Sanitary
03/31/2020——Water/Sanitary
13 projects · most recent 09/10/2026
General Wiring Lighting
FiledStatusContractorScope
09/10/2026Permit IssuedAbsolute Electrical Contracting ofLighting
11/01/2023CompleteHexagon Construction & Electrical GroupGeneral Wiring
06/22/2023CompleteCharan Electrical Enterp's—
05/25/2023CompleteCharan Electrical Enterp's—
11/09/2022CompleteStanco System Electrical Cont—
08/08/2022CompleteCharan Electrical Enterp's—
03/25/2022Permit IssuedArk Systems ElectricGeneral Wiring
12/13/2021CompleteCharan Electrical Enterp's—
06/28/2021CompleteG & F.a.st ElectricGeneral Wiring
09/11/2019CompleteIag ElectricGeneral Wiring
03/27/2019CompleteInterphase ElectricGeneral Wiring
09/11/2018CompleteCharan Electrical Enterp'sGeneral Wiring
09/11/2018CompleteCharan Electrical Enterp's—
▾Special Inspection Requirements (DOB NOW) — 30
DateRequirementInspectorRole
12/24/2025Concrete - Cast-In-PlaceNELSON LOPEZspecial
12/10/2025FinalNELSON LOPEZprogress
12/10/2025Post-installed Anchors—special
12/10/2025Mechanical SystemsNELSON LOPEZspecial
12/10/2025Fire-Resistant Penetrations and Joints—special
12/04/2025Mechanical SystemsNELSON LOPEZspecial
12/04/2025Fire-Resistant Penetrations and Joints—special
12/04/2025FinalNELSON LOPEZprogress
12/04/2025Post-installed Anchors—special
07/25/2025Fire-Resistant Penetrations and Joints—special
07/25/2025Post-installed Anchors—special
07/25/2025Sprinkler Systems—special
07/14/2025Sprinkler Systems—special
03/19/2025MasonryNELSON LOPEZspecial
03/17/2025Fire-Resistant Penetrations and Joints—special
03/17/2025Mechanical SystemsNELSON LOPEZspecial
03/17/2025Post-installed Anchors—special
03/17/2025FinalNELSON LOPEZprogress
03/17/2025Fire-Resistant Penetrations and Joints—special
03/17/2025Post-installed Anchors—special
03/17/2025Fire-Resistant Penetrations and JointsNELSON LOPEZspecial
03/17/2025Post-installed AnchorsNELSON LOPEZspecial
03/17/2025Fire-Resistance Rated ConstructionNELSON LOPEZprogress
07/23/2024Structural Stability – Alterations of existing buildingsNELSON LOPEZspecial
07/23/2024Fire-Resistance Rated ConstructionNELSON LOPEZprogress
Latest 25 of 30.
▾Tenants in the building
TenantSpaceFloorsRenovation projects
P.S. 32 QueensEducationCellar, Floors 1–3, Roof
Project Q00982771 Alteration · Permit Entire · 01/02/2024
Project Q00663889 Alteration · Approved · 01/19/2022
Project Q00537546 Alteration · LOC Issued · 06/21/2021
Project Q00338676 Alteration · QA Failed · 03/31/2020
Project Q00338726 Alteration · QA Failed · 03/31/2020
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 92 on file (BIS + DOB NOW)
▸Plans & Drawings14
▸DOB NOWPlans/Sketch12
08/23/2026Q00982771-S1Request digital key ↗
08/23/2026Q00982771-I1Request digital key ↗
08/23/2026Q00982771-P2Request digital key ↗
Showing 3 of 12 on file for this type
▸DOB NOWPlans/Sketch - Mechanical Systems1
08/28/2026Q00338726-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Plumbing1
08/28/2026Q00338676-I1Request digital key ↗
▸Seals & Professional Certifications20
▸DOB NOWDPL-1: Design Professional Seal & Signature14
08/28/2026Q00338676-I1Open ↗
08/28/2026Q00338726-I1Open ↗
08/23/2026Q00982771-S1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWProgress Inspector Seal & Signature3
08/28/2026Q00982771-P2Open ↗
08/23/2026Q00982771-P1Open ↗
08/23/2026Q00982771-S1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/28/2026Q00982771-P2Open ↗
08/23/2026Q00982771-P1Open ↗
08/23/2026Q00982771-S1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWNYCSCA - Approved Site Safety Plans1
08/13/2026Q00537546-I1Open ↗
▸Environmental & Asbestos2
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form2
08/28/2026Q00338676-I1Open ↗
08/28/2026Q00338726-I1Open ↗
▸Approvals, Objections & Sign-offs38
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)14
08/28/2026Q00338676-I1Open ↗
08/23/2026Q00982771-I1Open ↗
08/20/2026Q00663889-I1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter14
08/28/2026Q00338676-I1Open ↗
08/28/2026Q00338726-I1Open ↗
08/23/2026Q00982771-S1Open ↗
Showing 3 of 14 on file for this type
▸DOB NOWDesign Commission Sign Off City Owned (Exterior Work)8
08/23/2026Q00982771-I1Open ↗
08/13/2026Q00663889-I1Open ↗
08/13/2026Q00663889-S1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWDEP Variance (V5) letter2
08/23/2026Q00982771-S1Open ↗
08/23/2026Q00982771-I1Open ↗
▸Other Documents17
▸DOB NOWNYCSCA - BCC Plan Examination Transmittal12
08/23/2026Q00982771-I1Open ↗
08/20/2026Q00663889-S1Open ↗
08/20/2026Q00663889-I1Open ↗
Showing 3 of 12 on file for this type
▸DOB NOWProof of Historic Building4
08/23/2026Q00982771-I1Open ↗
08/20/2026Q00663889-I1Open ↗
08/13/2026Q00982771-P2Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWNYCSCA Exhibit 21
08/13/2026Q00537546-I1Open ↗