| Owner | Filings | Most Recent |
|---|---|---|
| REVAMP NYC | 12 | 07/08/2026 |
| 1712 DAVIDSON HOLDINGS, LLC | 3 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 04/20/2023 | $800K | — | — → — | $209/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| NIKOLAI KATZ ARCHITECT | 3 | 11/28/2023 |
| VASILIOS ARTEMIOU PE | 4 | 09/13/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 14 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| OWNERS GC NY LLC | General Contractor | 6 | 03/21/2026 |
| FRIED ELECTRIC CO. | Electrical | 2 | 03/22/2026 |
| METFLOW FIRE CONTROL LLC | Fire Protection | 1 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 7 | 11/28/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | METFLOW FIRE CONTROL LLC | 09/19/2023 |
| DOB NOW | Mechanical Systems | Signed-off | OWNERS GC NY LLC | 09/08/2023 |
| DOB NOW | Plumbing | Signed-off | PRIME PIPING & HEATING IN | 07/14/2023 |
| DOB NOW | General Construction | Permit Issued | OWNERS GC NY LLC | 07/07/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 11/28/2023 | Signed-off | OWNERS GC NY LLC | Heating and Air Conditioning Systems | Heat / Cool |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/28/2023 | Signed-off | METFLOW FIRE CONTROL LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/28/2023 | Signed-off | A M B MECHANICAL INC | Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/05/2024 | Permit Issued | FRIED ELECTRIC CO. | General Wiring |
| 08/18/2023 | Complete | FRIED ELECTRIC CO. | General Wiring |
| 09/24/2020 | Complete | DUDLEY & ASSOC. LIC. ELEC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/16/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/10/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/28/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/28/2023 | Fail-Final CND-Occupancy Inspection | Fail | View ↗ |
| 09/25/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 09/15/2023 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/15/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 08/15/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/09/2023 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/04/2023 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 12/04/2023 | Maintenance information | FAHAD FATEH | energy_progress |
| 12/04/2023 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 12/04/2023 | Interior lighting power | FAHAD FATEH | energy_progress |
| 12/04/2023 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 12/04/2023 | Metering | FAHAD FATEH | energy_progress |
| 12/04/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 12/04/2023 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 12/04/2023 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 12/04/2023 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 12/04/2023 | Fenestration areas | FAHAD FATEH | energy_progress |
| 09/20/2023 | HVAC-R and service water piping design and insulation | FAHAD FATEH | energy_progress |
| 09/20/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 09/20/2023 | Maintenance information | FAHAD FATEH | energy_progress |
| 09/20/2023 | HVAC-R and service water heating system controls | FAHAD FATEH | energy_progress |
| 09/20/2023 | HVAC-R and service water heating equipment | FAHAD FATEH | energy_progress |
| 08/31/2023 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 08/31/2023 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 08/31/2023 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 08/31/2023 | Maintenance information | FAHAD FATEH | energy_progress |
| 08/31/2023 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 08/31/2023 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 08/31/2023 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 08/31/2023 | Metering | FAHAD FATEH | energy_progress |
| 08/31/2023 | Interior lighting power | FAHAD FATEH | energy_progress |