← Back
Three families
1715 BOGART AVENUE
BRONX · Morris Park · BIN 2044495
💬 Discuss this project
1920Year Built
2Stories
C0Building Class
R4-1Zoning
2,807 sfGross Floor Area
3Units
Rent Stabilized0 Open Violations
Three families · 2,500 sf lot · 1.12 FAR built · Flood zone X
Locations of Work
ArchitectureMechanicalPlumbing
Floor 215p · 1 filing · 20 docs
Floor 114p · 1 filing · 20 docs
Cellar16p · 1 filing · 20 docs
Site & exterior4p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
URENA CONSTRUCTION & DESIGN1307/08/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
SOTIR ASSOCIATES411/13/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
URENA CONSTRUCTION & DESIGN403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
URENA CONST & DESIGN INCGeneral Contractor304/09/2026
INFINITI ESC PLUMBING CORPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
ENGINEERING CONSULTING SE2050311/13/2025
SOTIR ASSOCIATES7473111/13/2025
Building Lifecycle
All (55)Filed (4)Permit Issued (4)Signed Off (3)Violation (4)Inspection (8)Objection (14)Special Inspection (18)
12/17/2025
Signed off — Alteration
Proposed interior renovations of existing two-family walk-up apartment building to repair fire damage.
X01155530-S2
12/09/2025
Signed off — Alteration
Proposed interior renovations of existing two-family walk-up apartment building to repair fire damage.
X01155530-I1
12/08/2025
Inspection — Pass-Final General Construction Non-Directive 14
Pass
View inspection ↗
11/28/2025
Signed off — Alteration
Proposed interior renovations of existing two-family walk-up apartment building to repair fire damage.
X01155530-S1
11/24/2025
Permit issued — Mechanical Systems
X01155530-S2-MS
11/17/2025
Objection resolved — Addressed
11/17/2025
Special inspection requirement — Fire-Resistance Rated Construction
PAUL MARINO
11/17/2025
Special inspection requirement — Energy Code Compliance Inspections
PAUL MARINO
11/17/2025
Special inspection requirement — Protection of exposed foundation insulation
PAUL MARINO
11/17/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
PAUL MARINO
11/17/2025
Special inspection requirement — Fenestration air leakage
PAUL MARINO
11/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
11/17/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
PAUL MARINO
11/14/2025
Objection raised — Cost
11/13/2025
Filed — Alteration
Proposed interior renovations of existing two-family walk-up apartment building to repair fire damage.
X01155530-S2
11/13/2025
Filed — Alteration
Proposed interior renovations of existing two-family walk-up apartment building to repair fire damage.
X01155530-P1
11/12/2025
Special inspection requirement — Mechanical Systems
Hany Demetry
11/12/2025
Special inspection requirement — Final
Mina Eskaros
11/12/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
11/12/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
PAUL MARINO
11/12/2025
Special inspection requirement — Energy Code Compliance Inspections
PAUL MARINO
11/12/2025
Special inspection requirement — Fire-Resistance Rated Construction
PAUL MARINO
11/12/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
PAUL MARINO
11/12/2025
Special inspection requirement — Fenestration air leakage
PAUL MARINO
11/12/2025
Special inspection requirement — Protection of exposed foundation insulation
PAUL MARINO
09/22/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
09/09/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
08/25/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
08/21/2025
Inspection — Fail-Final General Construction Non-Directive 14
Fail
View inspection ↗
03/21/2025
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
03/21/2025
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
03/20/2025
Permit issued — General Construction
X01155530-I1-GC
03/19/2025
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
02/18/2025
Permit issued — Plumbing
X01155530-S1-PL
01/27/2025
Permit issued — General Construction
X01155530-I1-GC
01/23/2025
Objection resolved — Addressed
01/23/2025
Objection resolved — Addressed
01/20/2025
Objection resolved — Addressed
01/14/2025
Objection raised — Zoning
01/10/2025
Objection resolved — Addressed
12/31/2024
Objection resolved — Addressed
12/31/2024
Objection resolved — Addressed
12/18/2024
Objection raised — Scope
12/18/2024
Objection raised — Scope
12/18/2024
Objection raised — Scope
12/18/2024
Objection raised — Scope
12/18/2024
Objection raised — Scope
12/13/2024
Filed — Alteration
Proposed interior renovations of existing two-family walk-up apartment building to repair fire damage.
X01155530-I1
12/13/2024
Filed — Alteration
Proposed interior renovations of existing two-family walk-up apartment building to repair fire damage.
X01155530-S1
12/13/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
PAUL MARINO
12/13/2024
Special inspection requirement — Energy Code Compliance Inspections
PAUL MARINO
12/03/2024
Violation issued (HPD, closed)
I
11/27/2023
Violation issued (HPD, closed)
I
11/16/2022
Violation issued (HPD, closed)
I
08/22/2008
Violation issued (ECB, closed)
Construction
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWMechanical SystemsSigned-offURENA CONST & DESIGN INC11/24/2025
DOB NOWGeneral ConstructionSigned-offURENA CONST & DESIGN INC03/20/2025
DOB NOWPlumbingSigned-offINFINITI ESC PLUMBING COR02/18/2025
DOB NOWGeneral ConstructionSigned-offURENA CONST & DESIGN INC01/27/2025
1 project · most recent 03/05/2025
General Wiring
FiledStatusContractorScope
03/05/2025CompleteDD&G ELECTRICAL CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
12/08/2025Pass-Final General Construction Non-Directive 14PassView ↗
09/22/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
09/09/2025Fail-Final General Construction Non-Directive 14FailView ↗
08/25/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
08/21/2025Fail-Final General Construction Non-Directive 14FailView ↗
03/21/2025Certified Gas-Gas-Piping-RoughingCertifiedView ↗
03/21/2025Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
03/19/2025Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
11/17/2025Fire-Resistance Rated ConstructionPAUL MARINOprogress
11/17/2025Energy Code Compliance InspectionsPAUL MARINOprogress
11/17/2025Protection of exposed foundation insulationPAUL MARINOenergy_progress
11/17/2025Fenestration and door U-factor and product ratingsPAUL MARINOenergy_progress
11/17/2025Fenestration air leakagePAUL MARINOenergy_progress
11/17/2025Fire-Resistant Penetrations and JointsPAUL MARINOspecial
11/17/2025Structural Stability – Alterations of existing buildingsPAUL MARINOspecial
11/12/2025Mechanical SystemsHany Demetryspecial
11/12/2025FinalMina Eskarosprogress
11/12/2025Fire-Resistant Penetrations and JointsPAUL MARINOspecial
11/12/2025Structural Stability – Alterations of existing buildingsPAUL MARINOspecial
11/12/2025Energy Code Compliance InspectionsPAUL MARINOprogress
11/12/2025Fire-Resistance Rated ConstructionPAUL MARINOprogress
11/12/2025Fenestration and door U-factor and product ratingsPAUL MARINOenergy_progress
11/12/2025Fenestration air leakagePAUL MARINOenergy_progress
11/12/2025Protection of exposed foundation insulationPAUL MARINOenergy_progress
12/13/2024Fire-Resistant Penetrations and JointsPAUL MARINOspecial
12/13/2024Energy Code Compliance InspectionsPAUL MARINOprogress
▾Documents — 24 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
08/20/2026X01155530-I1Request digital key ↗
08/20/2026X01155530-S2Request digital key ↗
08/20/2026X01155530-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸Zoning, Tax Lot & Property Records3
▸DOB NOWRestrictive Declaration/Easement 13
08/13/2026X01155530-I1Open ↗
08/13/2026X01155530-P1Open ↗
08/13/2026X01155530-S1Open ↗
▸Seals & Professional Certifications14
▸DOB NOWProgress Inspector Seal & Signature6
09/21/2026X01155530-S2Open ↗
08/27/2026X01155530-S1Open ↗
08/27/2026X01155530-P1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
08/20/2026X01155530-S2Open ↗
08/20/2026X01155530-P1Open ↗
08/20/2026X01155530-S1Open ↗
Showing 3 of 4 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/21/2026X01155530-S2Open ↗
08/27/2026X01155530-S1Open ↗
08/27/2026X01155530-P1Open ↗
Showing 3 of 4 on file for this type
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-20/ACP-21: Asbestos Project Conditional Completion Form/Asbestos Project Completion Form3
08/20/2026X01155530-S2Open ↗
08/20/2026X01155530-S1Open ↗
08/20/2026X01155530-I1Open ↗