| Owner | Filings | Most Recent |
|---|---|---|
| URENA CONSTRUCTION & DESIGN | 13 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| SOTIR ASSOCIATES | 4 | 11/13/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| URENA CONSTRUCTION & DESIGN | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| URENA CONST & DESIGN INC | General Contractor | 3 | 04/09/2026 |
| INFINITI ESC PLUMBING COR | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ENGINEERING CONSULTING SE | 2050 | 3 | 11/13/2025 |
| SOTIR ASSOCIATES | 7473 | 1 | 11/13/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | URENA CONST & DESIGN INC | 11/24/2025 |
| DOB NOW | General Construction | Signed-off | URENA CONST & DESIGN INC | 03/20/2025 |
| DOB NOW | Plumbing | Signed-off | INFINITI ESC PLUMBING COR | 02/18/2025 |
| DOB NOW | General Construction | Signed-off | URENA CONST & DESIGN INC | 01/27/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/05/2025 | Complete | DD&G ELECTRICAL CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 12/08/2025 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 09/22/2025 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 09/09/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 08/25/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 08/21/2025 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 03/21/2025 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/21/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/19/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 11/17/2025 | Fire-Resistance Rated Construction | PAUL MARINO | progress |
| 11/17/2025 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 11/17/2025 | Protection of exposed foundation insulation | PAUL MARINO | energy_progress |
| 11/17/2025 | Fenestration and door U-factor and product ratings | PAUL MARINO | energy_progress |
| 11/17/2025 | Fenestration air leakage | PAUL MARINO | energy_progress |
| 11/17/2025 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 11/17/2025 | Structural Stability – Alterations of existing buildings | PAUL MARINO | special |
| 11/12/2025 | Mechanical Systems | Hany Demetry | special |
| 11/12/2025 | Final | Mina Eskaros | progress |
| 11/12/2025 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 11/12/2025 | Structural Stability – Alterations of existing buildings | PAUL MARINO | special |
| 11/12/2025 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 11/12/2025 | Fire-Resistance Rated Construction | PAUL MARINO | progress |
| 11/12/2025 | Fenestration and door U-factor and product ratings | PAUL MARINO | energy_progress |
| 11/12/2025 | Fenestration air leakage | PAUL MARINO | energy_progress |
| 11/12/2025 | Protection of exposed foundation insulation | PAUL MARINO | energy_progress |
| 12/13/2024 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 12/13/2024 | Energy Code Compliance Inspections | PAUL MARINO | progress |