← Back
Two family converted from one family
1717 AVENUE S
BROOKLYN · BIN 3253803
💬 Discuss this project
1920Year Built
2.5Stories
B3Building Class
R4-1Zoning
2,418 sfGross Floor Area
2Units
Rent Stabilized0 Open ViolationsFDNY Report ↗
Two family converted from one family · 2,842 sf lot · 0.85 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Floor 224p · 1 filing · 20 docs
Floor 124p · 1 filing · 20 docs
Cellar25p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
CITISCAPE CONSULTING LTD2307/08/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
06/02/2023$1.3M—Private party → Private party$548/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CITISCAPE CONSULTING LTD803/05/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
CITISCAPE CONSULTING LTD1603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
JB REMODELING CORPGeneral Contractor404/09/2026
CROWN PLUMBING INCPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CITISCAPE CONSULTING LTD762603/05/2026
Building Lifecycle
All (89)Filed (8)Permit Issued (5)Signed Off (2)Violation (5)Inspection (7)Objection (32)Special Inspection (30)
03/11/2026
Objection resolved — Addressed
03/10/2026
Objection raised — Other
03/05/2026
Filed — Alteration CO
ALT APP INCLUDING EXISTING TWO FAMILY 2 STORY WITH CELLAR CONVERTING TO ONE FAMILY DWELLING AND 2 STORY HORIZONTAL ENLARGEMENT. INTERIOR RENOVATION, NEW EXTERIOR WORK AND FENESTRATION. CHANGE IN USE AND OCCUPANCY. INCREASE IN BULK AND FAR.
B00995908-P5
02/18/2026
Special inspection requirement — Electric vehicle service equipment requirements
Alix Michel
02/18/2026
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
Joe Lieberman
02/18/2026
Special inspection requirement — Structural Stability – Alterations of existing buildings
Joe Lieberman
02/18/2026
Special inspection requirement — Energy Code Compliance Inspections
Joe Lieberman
02/18/2026
Special inspection requirement — Fire-Resistance Rated Construction
Joe Lieberman
02/18/2026
Special inspection requirement — Fenestration areas
Alix Michel
02/18/2026
Special inspection requirement — Fenestration air leakage
Alix Michel
02/18/2026
Special inspection requirement — Air barrier — testing
Alix Michel
02/18/2026
Special inspection requirement — Insulation placement and R values
Alix Michel
02/18/2026
Special inspection requirement — Metering
Alix Michel
02/18/2026
Special inspection requirement — Interior lighting power
Alix Michel
02/18/2026
Special inspection requirement — Fenestration and door U-factor and product ratings
Alix Michel
02/18/2026
Special inspection requirement — Permanent certificate
Alix Michel
02/18/2026
Special inspection requirement — Air barrier - visual inspection
Alix Michel
02/18/2026
Special inspection requirement — Maintenance information
Alix Michel
02/18/2026
Special inspection requirement — Protection of exposed foundation insulation
Alix Michel
02/02/2026
Signed off — Alteration CO
ALT APP INCLUDING EXISTING TWO FAMILY 2 STORY WITH CELLAR CONVERTING TO ONE FAMILY DWELLING AND 2 STORY HORIZONTAL ENLARGEMENT. INTERIOR RENOVATION, NEW EXTERIOR WORK AND FENESTRATION. CHANGE IN USE AND OCCUPANCY. INCREASE IN BULK AND FAR.
B00995908-S2
01/06/2026
Objection resolved — Addressed
01/06/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
Alix Michel
01/06/2026
Special inspection requirement — HVAC-R and service water heating equipment
Alix Michel
01/06/2026
Special inspection requirement — HVAC-R and service water heating system controls
Alix Michel
01/06/2026
Special inspection requirement — Maintenance information
Alix Michel
01/06/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joe Lieberman
12/17/2025
Objection raised — Scope
12/12/2025
Filed — Alteration CO
ALT APP INCLUDING EXISTING TWO FAMILY 2 STORY WITH CELLAR CONVERTING TO ONE FAMILY DWELLING AND 2 STORY HORIZONTAL ENLARGEMENT. INTERIOR RENOVATION, NEW EXTERIOR WORK AND FENESTRATION. CHANGE IN USE AND OCCUPANCY. INCREASE IN BULK AND FAR.
B00995908-P4
12/11/2025
Special inspection requirement — Maintenance information
Alix Michel
12/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joe Lieberman
12/11/2025
Special inspection requirement — HVAC-R and service water heating system controls
Alix Michel
12/11/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
Alix Michel
12/11/2025
Special inspection requirement — HVAC-R and service water heating equipment
Alix Michel
09/25/2025
Signed off — Alteration CO
ALT APP INCLUDING EXISTING TWO FAMILY 2 STORY WITH CELLAR CONVERTING TO ONE FAMILY DWELLING AND 2 STORY HORIZONTAL ENLARGEMENT. INTERIOR RENOVATION, NEW EXTERIOR WORK AND FENESTRATION. CHANGE IN USE AND OCCUPANCY. INCREASE IN BULK AND FAR.
B00995908-S1
09/10/2025
Filed — Alteration CO
ALT APP INCLUDING EXISTING TWO FAMILY 2 STORY WITH CELLAR CONVERTING TO ONE FAMILY DWELLING AND 2 STORY HORIZONTAL ENLARGEMENT. INTERIOR RENOVATION, NEW EXTERIOR WORK AND FENESTRATION. CHANGE IN USE AND OCCUPANCY. INCREASE IN BULK AND FAR.
B00995908-P3
09/10/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Joe Lieberman
09/10/2025
Special inspection requirement — Maintenance information
Alix Michel
09/10/2025
Special inspection requirement — HVAC-R and service water heating system controls
Alix Michel
09/10/2025
Special inspection requirement — HVAC-R and service water heating equipment
Alix Michel
08/15/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/30/2025
Objection resolved — Addressed
07/18/2025
Objection raised — Scope
07/14/2025
Filed — Alteration CO
ALT APP INCLUDING EXISTING TWO FAMILY 2 STORY WITH CELLAR CONVERTING TO ONE FAMILY DWELLING AND 2 STORY HORIZONTAL ENLARGEMENT. INTERIOR RENOVATION, NEW EXTERIOR WORK AND FENESTRATION. CHANGE IN USE AND OCCUPANCY. INCREASE IN BULK AND FAR.
B00995908-P1
05/29/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
05/28/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
04/21/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/30/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
12/06/2024
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
10/02/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
09/30/2024
Permit issued — General Construction
B00995908-I1-GC
09/12/2024
Permit issued — Plumbing
B00995908-S2-PL
06/10/2024
Objection resolved — Addressed
06/06/2024
Objection raised — Energy
05/31/2024
Objection resolved — Addressed
05/31/2024
Objection resolved — Addressed
05/31/2024
Objection resolved — Addressed
05/31/2024
Objection resolved — Addressed
05/31/2024
Objection resolved — Addressed
05/31/2024
Objection resolved — Addressed
05/28/2024
Objection raised — Admin
Latest 60 of 89 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedJB REMODELING09/30/2024
DOB NOWPlumbingSigned-offCROWN PLUMBING INC09/12/2024
DOB NOWPlumbingSigned-offCROWN PLUMBING INC05/21/2024
DOB NOWGeneral ConstructionPermit IssuedJB REMODELING05/13/2024
DOB NOWConstruction FenceSigned-offJB REMODELING05/08/2024
1 project · most recent 03/05/2026
Gas Water/Sanitary
FiledStatusContractorScope
03/05/2026Signed-offCROWN PLUMBING INCGas, Water/Sanitary
1 project · most recent 07/23/2025
General Wiring
FiledStatusContractorScope
07/23/2025CompleteQEC ELECTRICAL SVCE CORPGeneral Wiring
1 project · most recent 03/05/2026
Steel Concrete
FiledStatusContractorScope
03/05/2026Permit IssuedJB REMODELING CORPSteel, Concrete
1 project · most recent 03/05/2026
Fence
FiledStatusContractorScope
03/05/2026Permit IssuedJB REMODELING CORPFence
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
08/15/2025Pass-Final CND-Occupancy InspectionPassView ↗
05/29/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
05/28/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
04/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
12/30/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
12/06/2024Fail-Final PL - Up to 3 Requested FloorsFailView ↗
10/02/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 47
DateRequirementInspectorRole
02/18/2026Electric vehicle service equipment requirementsAlix Michelenergy_progress
02/18/2026Exterior Insulation and Finish Systems (EIFS)Joe Liebermanspecial
02/18/2026Structural Stability – Alterations of existing buildingsJoe Liebermanspecial
02/18/2026Energy Code Compliance InspectionsJoe Liebermanprogress
02/18/2026Fire-Resistance Rated ConstructionJoe Liebermanprogress
02/18/2026Fenestration areasAlix Michelenergy_progress
02/18/2026Fenestration air leakageAlix Michelenergy_progress
02/18/2026Air barrier — testing Alix Michelenergy_progress
02/18/2026Insulation placement and R valuesAlix Michelenergy_progress
02/18/2026MeteringAlix Michelenergy_progress
02/18/2026Interior lighting powerAlix Michelenergy_progress
02/18/2026Fenestration and door U-factor and product ratingsAlix Michelenergy_progress
02/18/2026Permanent certificateAlix Michelenergy_progress
02/18/2026Air barrier - visual inspectionAlix Michelenergy_progress
02/18/2026Maintenance informationAlix Michelenergy_progress
02/18/2026Protection of exposed foundation insulationAlix Michelenergy_progress
01/06/2026HVAC-R and service water piping design and insulationAlix Michelenergy_progress
01/06/2026HVAC-R and service water heating equipmentAlix Michelenergy_progress
01/06/2026HVAC-R and service water heating system controlsAlix Michelenergy_progress
01/06/2026Maintenance informationAlix Michelenergy_progress
01/06/2026Fire-Resistant Penetrations and JointsJoe Liebermanspecial
12/11/2025Maintenance informationAlix Michelenergy_progress
12/11/2025Fire-Resistant Penetrations and JointsJoe Liebermanspecial
12/11/2025HVAC-R and service water heating system controlsAlix Michelenergy_progress
12/11/2025HVAC-R and service water piping design and insulationAlix Michelenergy_progress
Latest 25 of 47.
▾Documents — 90 on file (BIS + DOB NOW)
▸Plans & Drawings8
▸DOB NOWPlans/Sketch8
08/21/2026B00995908-S2Request digital key ↗
08/21/2026B00995908-P3Request digital key ↗
08/15/2026B00995908-P1Request digital key ↗
Showing 3 of 8 on file for this type
▸Zoning, Tax Lot & Property Records7
▸DOB NOWZD1: DOB Zoning Diagram3
08/13/2026B00995908-P1Open ↗
08/13/2026B00995908-I1Open ↗
08/13/2026B00995908-P5Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/14/2026B00995908-I1Open ↗
08/13/2026B00995908-P5Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp2
08/14/2026B00995908-I1Open ↗
08/13/2026B00995908-I1Open ↗
▸Seals & Professional Certifications53
▸DOB NOWProgress Inspector Seal & Signature38
09/01/2026B00995908-P1Open ↗
09/01/2026B00995908-P1Open ↗
09/01/2026B00995908-P1Open ↗
Showing 3 of 38 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature8
08/21/2026B00995908-P1Open ↗
08/21/2026B00995908-S3Open ↗
08/21/2026B00995908-S1Open ↗
Showing 3 of 8 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature7
09/01/2026B00995908-P1Open ↗
09/01/2026B00995908-P1Open ↗
08/31/2026B00995908-S2Open ↗
Showing 3 of 7 on file for this type
▸Safety & Tenant Protection6
▸DOB NOWStreet Tree Checklist3
08/15/2026B00995908-P1Open ↗
08/14/2026B00995908-I1Open ↗
08/14/2026B00995908-P5Open ↗
▸DOB NOWStreet Tree Sign Off1
08/14/2026B00995908-I1Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00995908-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00995908-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/21/2026B00995908-S2Open ↗
08/21/2026B00995908-P3Open ↗
08/15/2026B00995908-P4Open ↗
▸Other Documents13
▸DOB NOWSite Survey: Initial3
08/13/2026B00995908-P1Open ↗
08/13/2026B00995908-P5Open ↗
08/13/2026B00995908-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/13/2026B00995908-P5Open ↗
08/13/2026B00995908-P1Open ↗
08/13/2026B00995908-I1Open ↗
▸DOB NOWPlot Diagram3
08/13/2026B00995908-P5Open ↗
08/13/2026B00995908-P1Open ↗
08/13/2026B00995908-I1Open ↗
▸DOB NOWProperty Ownership Certification3
08/15/2026B00995908-P1Open ↗
08/14/2026B00995908-I1Open ↗
08/14/2026B00995908-P5Open ↗
▸DOB NOWFinal Survey1
08/13/2026B00995908-I1Open ↗