| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 09/23/2020 | $770K | — | Private party → Private party | $433/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| INFINITY DESIGN CONSULTANT INC | 4 | 01/03/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| GREEN STUDIO | 4 | 03/21/2026 |
| W J PROFESSIONAL EXPEDITING COMPANY | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BAY RIDGE STAR CONSTRUCT | General Contractor | 4 | 03/21/2026 |
| EH PLUMBING & HEATING COR | Plumbing | 2 | 07/08/2026 |
| ALL HOUR SEWER SERVICE CO. | Plumbing | 1 | 07/08/2026 |
| PIPESTYLISTS, INC | Plumbing | 1 | 07/08/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | BAY RIDGE STAR CONSTRUCT | 08/30/2023 |
| DOB NOW | Plumbing | Permit Issued | T & T PLUMBING INC | 02/17/2023 |
| DOB NOW | Plumbing | Permit Issued | EH PLUMBING & HEATING COR | 01/18/2023 |
| DOB NOW | General Construction | Permit Issued | BAY RIDGE STAR CONSTRUCT | 02/18/2022 |
| DOB NOW | Plumbing | Permit Issued | EH PLUMBING & HEATING COR | 06/10/2021 |
| DOB NOW | Plumbing | Permit Issued | ALL HOUR SEWER SERVICE CO. | 12/23/2020 |
| BIS | — | ISSUED | BAY RIDGE STAR CONSTRUCTION | 06/09/2023 |
| BIS | OT | ISSUED | BAY RIDGE STAR CONSTRUCT | 05/16/2022 |
| BIS | OT | ISSUED | BAY RIDGE STAR CONSTRUCT | 01/10/2022 |
| BIS | OT | ISSUED | BAY RIDGE STAR CONSTRUCT | 12/08/2020 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/03/2023 | Permit Issued | A&H EXPRESS PLBG & HTG CO | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/10/2022 | Permit Issued | INARA ELECTRIC CORP | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/23/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/30/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 08/16/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 06/29/2022 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 12/03/2021 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 12/02/2022 | Lighting in dwelling units | Samy Abouzid | energy_progress |
| 09/09/2022 | Lighting in dwelling units | Samy Abouzid | energy_progress |