← Back
Cape Cod
172-10 EFFINGTON AVENUE
QUEENS · Auburndale · BIN 4125986
💬 Discuss this project
1955Year Built
1.5Stories
A0Building Class
R2AZoning
1,154 sfGross Floor Area
1Units
Cape Cod · 4,000 sf lot · 0.29 FAR built · Flood zone X
Locations of Work
Electrical
Roof1 filing · 7 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
12/05/2013$592K—Private party → Private party$513/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOMENTUM SOLAR103/18/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
ISLAND ELECTRIC CORPElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MXV SIA LLC9281103/18/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
09/26/2025
Signed off — Alteration
Installation of solar panels, rooftop, railed, grid-tied, 27 modules, 11.07 KW
Q01195992-I1
03/20/2025
Permit issued — Solar
Q01195992-I1-SL
03/18/2025
Filed — Alteration
Installation of solar panels, rooftop, railed, grid-tied, 27 modules, 11.07 KW
Q01195992-I1
03/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
Mina Makar
03/17/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
Mina Makar
03/17/2025
Special inspection requirement — Energy Code Compliance Inspections
Mina Makar
03/17/2025
Special inspection requirement — Final
Mina Makar
03/17/2025
Special inspection requirement — Air barrier - visual inspection
Mina Makar
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offMOMENTUM SOLAR03/20/2025
1 project · most recent 03/17/2025
FiledStatusContractorScope
03/17/2025CompleteISLAND ELECTRIC CORP—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/17/2025Fire-Resistant Penetrations and JointsMina Makarspecial
03/17/2025Structural Stability – Alterations of existing buildingsMina Makarspecial
03/17/2025Energy Code Compliance InspectionsMina Makarprogress
03/17/2025FinalMina Makarprogress
03/17/2025Air barrier - visual inspectionMina Makarenergy_progress
▾Documents — 7 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/20/2026Q01195992-I1Request digital key ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/26/2026Q01195992-I1Open ↗
08/26/2026Q01195992-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026Q01195992-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/26/2026Q01195992-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026Q01195992-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026Q01195992-I1Open ↗