← Back
Walk-up cooperative
172 WEST 82 STREET
MANHATTAN · Upper West Side (Central) · BIN 1032050
💬 Discuss this project
1891Year Built
3Stories
C6Building Class
R8BZoning
4,326 sfGross Floor Area
5Units
Rent Stabilized8 Open Violations 7 unresolved · 1 paperwork only ▸
Walk-up cooperative · Owner of record: WEST 82 TENANTS REALTY CORP · 1,703 sf lot · 2.54 FAR built · Flood zone X
Locations of Work
ArchitectureOther
Roof5p · 2 filings · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
SANDBERG MANAGEMENT407/08/2026
WEST 82 TENANTS REALTY403/22/2026
WEST 82 STREET TENANTS REALTY403/21/2026
WEST 82ND TENANT REALTY403/21/2026
TENANTS REALTY203/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MOORE ASSOCIATES, LLC105/07/2025
RAND ENGINEERING & ARCHITECTURE DPC210/31/2023
PS ENGINEERS, INC.104/18/2022
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
JULIAN A. GOMEZ403/21/2026
PS ENGINEERS203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TWO-TONE CONTRACTING CORP.General Contractor507/08/2026
BILLY SERVULUSElectrical103/21/2026
RU HUANGElectrical103/21/2026
SERVULUS BILLYElectrical103/21/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
MOORE ENG. OF NY, DPC9134105/07/2025
RAND ENGINEERING & ARCHIT266210/31/2023
AR CONSULTING ENGINEER P.4054104/18/2022
Building Lifecycle
All (48)Filed (4)Permit Issued (4)Signed Off (3)Violation (17)Objection (2)Special Inspection (18)
04/29/2026
Violation issued (HPD, closed)
A
01/15/2026
Signed off — Alteration
INSTALLATION OF SUPPORTED PIPE SCAFFOLD AS SHOWN ON THE PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M00715828-I1
11/26/2025
Signed off — Alteration
EXTERIOR FACADE REPAIRS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. WORK SHALL INCLUDE MORTAR JOINT REPOINTING, CRACKED BRICK REPLACEMENT AND STUCCO REPAIRS.
M01177352-I1
05/19/2025
Permit issued — General Construction
M01177352-I1-GC
05/07/2025
Filed — Alteration
EXTERIOR FACADE REPAIRS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY. WORK SHALL INCLUDE MORTAR JOINT REPOINTING, CRACKED BRICK REPLACEMENT AND STUCCO REPAIRS.
M01177352-I1
05/07/2025
Special inspection requirement — Masonry
Christine Hobson
05/07/2025
Special inspection requirement — Final
Christine Hobson
05/07/2025
Special inspection requirement — Tenant Protection Plan Compliance
Christine Hobson
04/01/2024
Violation issued (HPD, closed)
A
11/01/2023
Signed off — Alteration
Roof Replacement & Limited Roof Level Repairs. No change to use, egress or occupancy.
M00556213-I1
11/01/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
John Monroe
11/01/2023
Special inspection requirement — Post-installed Anchors
John Monroe
11/01/2023
Special inspection requirement — Masonry
John Monroe
11/01/2023
Special inspection requirement — Final
John Monroe
11/01/2023
Special inspection requirement — Energy Code Compliance Inspections
John Monroe
11/01/2023
Special inspection requirement — Insulation placement and R values
John Monroe
11/01/2023
Special inspection requirement — Air barrier - visual inspection
John Monroe
10/31/2023
Filed — Alteration
Roof Replacement & Limited Roof Level Repairs. No change to use, egress or occupancy.
M00556213-P1
09/26/2023
Special inspection requirement — Masonry
John Monroe
09/26/2023
Special inspection requirement — Energy Code Compliance Inspections
John Monroe
09/26/2023
Special inspection requirement — Final
John Monroe
09/26/2023
Special inspection requirement — Air barrier - visual inspection
John Monroe
09/26/2023
Special inspection requirement — Insulation placement and R values
John Monroe
09/26/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
John Monroe
09/26/2023
Special inspection requirement — Post-installed Anchors
John Monroe
03/24/2023
Permit issued — General Construction
M00556213-I1-GC
03/16/2023
Violation issued (HPD, closed)
A
11/10/2022
Violation issued (HPD, closed)
C
04/19/2022
Permit issued — Supported Scaffold
M00715828-I1-SF
04/18/2022
Filed — Alteration
INSTALLATION OF SUPPORTED PIPE SCAFFOLD AS SHOWN ON THE PLANS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
M00715828-I1
04/08/2022
Special inspection requirement — Post-installed Anchors
QAZI RAZZAK
04/06/2022
Permit issued — General Construction
M00556213-I1-GC
02/16/2022
Violation issued (HPD, closed)
A
01/06/2022
Objection resolved — Addressed
12/07/2021
Objection raised — Admin
12/01/2021
Filed — Alteration
Roof Replacement & Limited Roof Level Repairs. No change to use, egress or occupancy.
M00556213-I1
04/01/2021
Violation issued (HPD, closed)
A
04/01/2021
Violation issued (HPD, closed)
I
04/06/2018
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
01/01/2009
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/02/2002
Violation issued (ECB, open)
Boilers
03/26/2002
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
08/18/1986
Violation issued (HPD, open)
B
06/11/1981
Violation issued (HPD, open)
B
05/20/1981
Violation issued (HPD, open)
A
05/20/1981
Violation issued (HPD, open)
A
05/20/1981
Violation issued (HPD, open)
B
05/20/1981
Violation issued (HPD, open)
A
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offTWO-TONE CONTRACTING CORP05/19/2025
DOB NOWGeneral ConstructionSigned-offTWO-TONE CONTRACTING CORP03/24/2023
DOB NOWSupported ScaffoldSigned-offTWO-TONE CONTRACTING CORP04/19/2022
DOB NOWGeneral ConstructionSigned-offTWO-TONE CONTRACTING CORP04/06/2022
BISEQISSUEDEVEREST SCAFFOLDING INC07/06/2016
BISEQISSUEDEVEREST SCAFFOLDING INC07/05/2016
BISOTISSUEDQUALITY BUILDING CONSTRUTION05/24/2016
BISOTISSUEDQUALITY BUILDING CONSTRUTION08/31/2015
BISEQISSUEDEVEREST SCAFFOLDING INC07/20/2015
BISEQISSUEDEVEREST SCAFFOLDING INC07/17/2015
BISOTISSUEDTIMOTHY SCHROCK ARCHITECT03/22/2013
BISPLISSUEDS.T.P. P & H INC11/21/2011
BISOTISSUEDBULLFROG DEVELOPMENT INC10/25/2011
BISOTISSUEDFAUCHER CONSTRUCTION LLC04/30/2009
BISPLISSUEDTIME MECHANICALS INC.05/11/2001
BISPLISSUEDJOHN TRANI PLBG AND HTG06/25/1997
BISOTISSUEDPHILP FAUCHER04/15/1997
1 project · most recent 11/16/2022
General Wiring
FiledStatusContractorScope
11/16/2022CompleteATMOS ELECTRIC SVCE CORPGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 18
DateRequirementInspectorRole
05/07/2025MasonryChristine Hobsonspecial
05/07/2025FinalChristine Hobsonprogress
05/07/2025Tenant Protection Plan ComplianceChristine Hobsonspecial
11/01/2023Structural Stability – Alterations of existing buildingsJohn Monroespecial
11/01/2023Post-installed AnchorsJohn Monroespecial
11/01/2023MasonryJohn Monroespecial
11/01/2023FinalJohn Monroeprogress
11/01/2023Energy Code Compliance InspectionsJohn Monroeprogress
11/01/2023Insulation placement and R valuesJohn Monroeenergy_progress
11/01/2023Air barrier - visual inspectionJohn Monroeenergy_progress
09/26/2023MasonryJohn Monroespecial
09/26/2023Energy Code Compliance InspectionsJohn Monroeprogress
09/26/2023FinalJohn Monroeprogress
09/26/2023Air barrier - visual inspectionJohn Monroeenergy_progress
09/26/2023Insulation placement and R valuesJohn Monroeenergy_progress
09/26/2023Structural Stability – Alterations of existing buildingsJohn Monroespecial
09/26/2023Post-installed AnchorsJohn Monroespecial
04/08/2022Post-installed AnchorsQAZI RAZZAKspecial
▾Documents — 152 on file (BIS + DOB NOW)
▸Plans & Drawings4
▸DOB NOWPlans/Sketch4
09/02/2026M00715828-I1Request digital key ↗
08/28/2026M00556213-P1Request digital key ↗
08/23/2026M01177352-I1Request digital key ↗
Showing 3 of 4 on file for this type
▸Applications & Permits25
▸BISWORK PERMIT APPLICATION12
08/02/2016140376545Open ↗
07/08/2016140377161Open ↗
06/03/2016140329151Open ↗
Showing 3 of 12 on file for this type
▸BISPLAN / WORK APPROVAL APPLICATION10
11/24/2025121402026Open ↗
09/29/2015140329151Open ↗
07/17/2015140377161Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWLPC Approval/Permit3
08/13/2026M00556213-P1Open ↗
08/13/2026M00556213-I1Open ↗
08/13/2026M01177352-I1Open ↗
▸Seals & Professional Certifications42
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION19
12/20/2016140329151Open ↗
12/20/2016140329151Open ↗
12/07/2016140376545Open ↗
Showing 3 of 19 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature5
09/25/2026M00556213-I1Open ↗
08/30/2026M00715828-I1Open ↗
08/25/2026M00556213-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
09/25/2026M00556213-I1Open ↗
09/25/2026M00556213-I1Open ↗
08/25/2026M00556213-P1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature4
09/02/2026M00715828-I1Open ↗
08/28/2026M00556213-I1Open ↗
08/28/2026M00556213-P1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY2
07/17/2015140377161Open ↗
07/16/2015140376545Open ↗
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION2
07/17/2015140377161Open ↗
07/16/2015140376545Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT2
07/17/2015140377161Open ↗
07/16/2015140376545Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
04/07/2015140329151Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
12/06/2012121402026Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
12/06/2012121402026Open ↗
▸Trade Schedules & Equipment8
▸BISSELF-CERT PLUMBING NOTICE5
02/15/2012120858205Open ↗
12/18/2009110367344Open ↗
11/04/2009110367344Open ↗
Showing 3 of 5 on file for this type
▸BISSCHEDULE B - PLUMBING3
10/25/2011120858205Open ↗
12/22/2008110367344Open ↗
10/20/2008110367344Open ↗
▸Environmental & Asbestos10
▸BISTHIS IS 'NOT AN ASBESTOS PROJECT'3
10/25/2011120858205Open ↗
10/20/2008110367344Open ↗
10/20/2008110367344Open ↗
▸BISASBESTOS-CERTIFICATION (DEP ACP5)3
03/04/2013121402026Open ↗
03/04/2013121402026Open ↗
07/17/2015140377161Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/28/2026M00556213-P1Open ↗
08/15/2026M00556213-I1Open ↗
08/13/2026M01177352-I1Open ↗
▸BISDEP ASBESTOS PROJECT COMPLETION FORM1
08/31/2015140329151Open ↗
▸Energy Compliance10
▸BISTECHNICAL REPORT: ENERGY2
10/26/2011120858205Open ↗
10/25/2011120858205Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
12/20/2016140329151Open ↗
07/20/2012120858205Open ↗
▸BISAS-BUILT ENERGY ANALYSIS2
12/20/2016140329151Open ↗
07/20/2012120858205Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY2
04/07/2015140329151Open ↗
04/07/2015140329151Open ↗
▸BISELECTRICAL APPLICATION FOR SIDEWALK SHED LIGHTING1
07/16/2015140376545Open ↗
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026M00556213-I1Open ↗
▸Inspections & Test Reports11
▸BISTECHNICAL REPORT: RESPONSIBILITY11
12/02/2025121402026Open ↗
12/02/2025121402026Open ↗
11/25/2025121402026Open ↗
Showing 3 of 11 on file for this type
▸Approvals, Objections & Sign-offs22
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST8
12/02/2025121402026Open ↗
12/20/2016140329151Open ↗
12/07/2016140376545Open ↗
Showing 3 of 8 on file for this type
▸BISLANDMARKS APPROVAL6
07/17/2015140377161Open ↗
07/16/2015140376545Open ↗
07/08/2015140329151Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION3
12/20/2016140329151Open ↗
08/02/2016140376545Open ↗
07/20/2012120858205Open ↗
▸BISADMINISTRATIVE OBJECTIONS2
10/25/2011120858205Open ↗
10/20/2008110367344Open ↗
▸BISLANDMARKS SIGNOFF1
12/02/2025121402026Open ↗
▸BISFINAL1
12/02/2025121402026Open ↗
▸BISSHED LETTER1
08/31/2015140329151Open ↗
▸Cost, Insurance & Ownership11
▸BISCOST AFFIDAVIT9
04/07/2015140329151Open ↗
12/06/2012121402026Open ↗
07/20/2012120858205Open ↗
Showing 3 of 9 on file for this type
▸BISAcord 25 (Acord Certificate of Liability Insurance)1
03/04/2013121402026Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
12/02/2025121402026Open ↗
▸Filing & Intake Forms9
▸BISEFILING COVER SHEET4
12/06/2012121402026Open ↗
10/25/2011120858205Open ↗
10/20/2008110367344Open ↗
Showing 3 of 4 on file for this type
▸BISEFILING JOB APPLICATION COVER SHEET3
07/17/2015140377161Open ↗
07/16/2015140376545Open ↗
04/07/2015140329151Open ↗
▸BISADDITIONAL INFORMATION2
01/05/2016140329151Open ↗
07/08/2015140329151Open ↗