← Back
Two family converted from one family
1720 EAST 4 STREET
BROOKLYN · Gravesend (East)-Homecrest · BIN 3176011
💬 Discuss this project
1930Year Built
2Stories
B3Building Class
R5Zoning
1,280 sfGross Floor Area
2Units
Two family converted from one family · 2,400 sf lot · 0.53 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalGeneral
Filed — no permit issued32p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
JUST CONSULTING ENGINEERING209/12/2025
MAQE ARCHITECTURE106/16/2025
Building Lifecycle
All (91)Filed (3)Objection (72)Special Inspection (16)
06/04/2026
Objection raised — Scope
04/29/2026
Objection resolved — Addressed
04/29/2026
Objection resolved — Open
04/15/2026
Objection resolved — Addressed
04/15/2026
Objection resolved — Addressed
03/18/2026
Objection raised — Zoning
02/16/2026
Objection resolved — Addressed
02/09/2026
Objection raised — Cost
02/09/2026
Objection raised — Energy
01/30/2026
Objection resolved — Addressed
12/23/2025
Objection raised — Zoning
12/05/2025
Objection resolved — Addressed
12/03/2025
Objection raised — Structural
11/24/2025
Objection resolved — Open
11/18/2025
Objection resolved — Addressed
11/18/2025
Objection resolved — Addressed
11/18/2025
Objection resolved — Addressed
11/18/2025
Objection resolved — Addressed
11/18/2025
Objection resolved — Addressed
11/18/2025
Objection resolved — Addressed
11/18/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
11/07/2025
Objection resolved — Addressed
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Zoning
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Other
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Fire_Protection
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Inspections
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Admin
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/25/2025
Objection raised — Structural
09/12/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
FILING FOUNDATION WORK IN CONJUNCTION WITH ALT JOB #B01223458I1
B01223458-S1
09/12/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
FILING FOUNDATION WORK IN CONJUNCTION WITH ALT JOB #B01223458I1
B01223458-S2
09/12/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
09/12/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
09/11/2025
Objection resolved — Addressed
08/24/2025
Special inspection requirement — Final
08/24/2025
Special inspection requirement — Concrete - Cast-In-Place
08/24/2025
Special inspection requirement — Subgrade Inspections
08/24/2025
Special inspection requirement — Final
Latest 60 of 91 events.
Nothing on file for this building.
1 project · most recent 09/12/2025
Wood
FiledStatusContractorScope
09/12/2025——Wood
▾Special Inspection Requirements (DOB NOW) — 16
DateRequirementInspectorRole
09/12/2025Structural Stability – Alterations of existing buildings—special
09/12/2025Structural Stability – Alterations of existing buildings—special
08/24/2025Final—progress
08/24/2025Concrete - Cast-In-Place—special
08/24/2025Subgrade Inspections—special
08/24/2025Final—progress
08/24/2025Footing and Foundation—progress
08/24/2025Structural Wood Frame—progress
08/12/2025Maintenance information—energy_progress
08/12/2025Interior lighting power—energy_progress
06/07/2025Structural Stability – Alterations of existing buildings—special
06/07/2025Fire-Resistant Penetrations and Joints—special
06/07/2025Masonry—special
06/07/2025Fire-Resistance Rated Construction—progress
06/07/2025Energy Code Compliance Inspections—progress
06/07/2025Exterior Insulation and Finish Systems (EIFS)—special
▾Documents — 19 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/21/2026B01223458-I1Request digital key ↗
08/14/2026B01223458-S1Request digital key ↗
08/14/2026B01223458-S2Request digital key ↗
▸Zoning, Tax Lot & Property Records3
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026B01223458-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B01223458-I1Open ↗
▸DOB NOWZoning Exhibit form (1-5)1
08/13/2026B01223458-I1Open ↗
▸Seals & Professional Certifications3
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/21/2026B01223458-S1Open ↗
08/21/2026B01223458-I1Open ↗
08/21/2026B01223458-S2Open ↗
▸Trade Schedules & Equipment1
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)1
08/13/2026B01223458-I1Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/13/2026B01223458-I1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/21/2026B01223458-I1Open ↗
08/14/2026B01223458-S1Open ↗
08/14/2026B01223458-S2Open ↗
▸Inspections & Test Reports1
▸DOB NOWGeotechnical Report (BC 1803.6)1
08/13/2026B01223458-S1Open ↗
▸Other Documents4
▸DOB NOWPlot Diagram1
08/13/2026B01223458-I1Open ↗
▸DOB NOWProperty Ownership Certification1
08/21/2026B01223458-I1Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026B01223458-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone1
08/13/2026B01223458-I1Open ↗