| Owner | Filings | Most Recent |
|---|---|---|
| METRO CONTRACTING NY | 5 | 03/22/2026 |
| BLUE ELM BUILDERS | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| KAO HWA LEE ARCHITECTS PC | 13 | 09/17/2024 |
| ENTHINK ENGINEERS LLC | 1 | 04/04/2023 |
| YORK TOWER CONSULTING ENGINEERING | 3 | 07/21/2022 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPRESS FILING INC | 32 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BLUE ELM INC | General Contractor | 21 | 07/08/2026 |
| METRO CONTRACTING NY, INC. | General Contractor | 2 | 03/21/2026 |
| PRIME PIPING & HEATING IN | Fire Protection | 1 | 07/08/2026 |
| PRIME PIPING & HEATING IN | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| HRF SERVICES CORP | 5616 | 14 | 09/17/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Curb Cut | Signed-off | BLUE ELM INC | 09/22/2023 |
| DOB NOW | Curb Cut | Signed-off | BLUE ELM INC | 09/22/2023 |
| DOB NOW | Mechanical Systems | Signed-off | BLUE ELM INC | 09/22/2023 |
| DOB NOW | General Construction | Permit Issued | BLUE ELM INC | 07/06/2023 |
| DOB NOW | General Construction | Permit Issued | BLUE ELM INC | 04/04/2023 |
| DOB NOW | Supported Scaffold | Signed-off | METRO CONTRACTING NY, INC. | 04/04/2023 |
| DOB NOW | Earth Work | Signed-off | BLUE ELM INC | 04/04/2023 |
| DOB NOW | Sprinklers | Signed-off | PRIME PIPING & HEATING IN | 02/21/2023 |
| DOB NOW | Sprinklers | Signed-off | A M B MECHANICAL INC | 02/21/2023 |
| DOB NOW | General Construction | Permit Issued | BLUE ELM INC | 12/06/2022 |
| DOB NOW | Structural | Signed-off | BLUE ELM INC | 12/02/2022 |
| DOB NOW | General Construction | Permit Issued | BLUE ELM INC | 10/21/2022 |
| DOB NOW | Earth Work | Signed-off | BLUE ELM INC | 06/03/2022 |
| DOB NOW | Foundation | Signed-off | BLUE ELM INC | 05/19/2022 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/17/2024 | Signed-off | BLUE ELM INC | Associated Ducts and Piping, Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-4C36NA3 35,400 BTU · Heat Pump Outdoor ×20 MXZ-5C42NA3 45,000 BTU · Heat Pump Outdoor ×16 MXZ-3C30NA3 28,600 BTU · Heat Pump Outdoor ×12 MUZ-GS12NA 14,400 BTU · Heat Pump Outdoor ×4 Ventilation Ducts & Piping N/A N/A 5 kW · Electric Heater ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/10/2023 | Complete | RICHARD NEU | — |
| 01/09/2023 | Complete | SAFEWAY CONSTRUCTION, INC | General Wiring, Lighting |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/06/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/04/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/30/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/08/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/30/2023 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 10/24/2023 | Certified Sprinkler-Dry Pipe Valve (SP)-Dry Pipe Valve Test | Certified | View ↗ |
| 10/24/2023 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 10/21/2023 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 10/20/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 10/18/2023 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/04/2023 | Fail-Final Curb Cut Non-Directive 14 | Fail | View ↗ |
| 06/09/2023 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 06/09/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 06/09/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 06/09/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/25/2024 | Fire-Resistant Penetrations and Joints | FAHAD FATEH | special |
| 09/25/2024 | Post-installed Anchors | FAHAD FATEH | special |
| 09/25/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 09/25/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 09/25/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 09/25/2024 | Lighting in dwelling units | FAHAD FATEH | energy_progress |
| 09/25/2024 | Metering | FAHAD FATEH | energy_progress |
| 09/25/2024 | Maintenance information | FAHAD FATEH | energy_progress |
| 09/25/2024 | Fenestration areas | FAHAD FATEH | energy_progress |
| 09/25/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |
| 09/25/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 09/25/2024 | Air barrier - visual inspection | FAHAD FATEH | energy_progress |
| 09/25/2024 | Interior lighting power | FAHAD FATEH | energy_progress |
| 09/25/2024 | Protection of exposed foundation insulation | FAHAD FATEH | energy_progress |
| 09/25/2024 | Lighting controls | FAHAD FATEH | energy_progress |
| 09/25/2024 | Fenestration and door U-factor and product ratings | FAHAD FATEH | energy_progress |
| 09/25/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 09/16/2024 | Exterior Insulation and Finish Systems (EIFS) | FAHAD FATEH | special |
| 09/16/2024 | Post-installed Anchors | FAHAD FATEH | special |
| 09/16/2024 | Energy Code Compliance Inspections | FAHAD FATEH | progress |
| 09/16/2024 | Fire-Resistance Rated Construction | FAHAD FATEH | progress |
| 09/16/2024 | Metering | FAHAD FATEH | energy_progress |
| 09/16/2024 | Insulation placement and R values | FAHAD FATEH | energy_progress |
| 09/16/2024 | Fenestration air leakage | FAHAD FATEH | energy_progress |
| 09/16/2024 | Exterior lighting power | FAHAD FATEH | energy_progress |