| Owner | Filings | Most Recent |
|---|---|---|
| GELFACTORY | 9 | 07/08/2026 |
| 1731 UNIONPORT ROAD REALT | 2 | 03/22/2026 |
| CARLITOS CONTRACTING | 1 | 03/22/2026 |
| OK UNIONPORT LLC | 1 | 03/21/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 08/17/2023 | $675K | — | 1731 UNIONPORT ROAD REALTY CORP. → OK UNIONPORT LLC | $220/sf building |
| 09/25/2018 | $570K | — | — → — | $186/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| TL ENGINEERING, PC | 5 | 08/08/2025 |
| H2H GROUP | 1 | 05/24/2021 |
| A & T ENGINEERING, P.C. | 1 | 08/17/2020 |
| URBAN INTEGRATIONS | 1 | 06/30/2020 |
| ALBERT MONTOYA ARCHITECT | 1 | 02/07/2020 |
| Representative | Filings | Most Recent |
|---|---|---|
| ARISTAR GROUP | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CARLITOS CONTRACTING CORP | General Contractor | 6 | 03/21/2026 |
| LEBANON CONSTRUCTION INC | General Contractor | 4 | 07/08/2026 |
| TREDENT CONTRACTING SERVI | General Contractor | 4 | 07/08/2026 |
| DOVAL PLBG & HTG CORP | Plumbing | 4 | 07/08/2026 |
| RAFALEX CONTRACTING CORP | General Contractor | 1 | 07/08/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| JOANN PRICE | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| TL ENGINEERING, PC | 1222 | 3 | 08/08/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | LEBANON CONSTRUCTION INC | 08/30/2024 |
| DOB NOW | Plumbing | Permit Issued | DOVAL PLBG & HTG CORP | 08/12/2024 |
| DOB NOW | General Construction | Permit Issued | LEBANON CONSTRUCTION INC | 02/07/2024 |
| DOB NOW | Sidewalk Shed | Signed-off | CARLITOS CONTRACTING CORP | 09/29/2021 |
| DOB NOW | Construction Fence | Signed-off | TREDENT CONTRACTING SERVI | 05/27/2021 |
| DOB NOW | Supported Scaffold | Signed-off | TREDENT CONTRACTING SERVI | 05/25/2021 |
| DOB NOW | Construction Fence | Signed-off | RAFALEX CONTRACTING CORP | 08/20/2020 |
| DOB NOW | Sidewalk Shed | Signed-off | CARLITOS CONTRACTING CORP | 07/01/2020 |
| BIS | OT | ISSUED | TREDENT CONTRACTING SERVI | 07/30/2021 |
| BIS | OT | ISSUED | RAFALEX CONTRACTING CORP | 01/04/2021 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/07/2020 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/08/2025 | Permit Issued | DOVAL PLBG & HTG CORP | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/23/2025 | Permit Issued | MARTINEZ ELECTRICAL CONT | General Wiring |
| 06/25/2020 | Complete | RICHARD NEU | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 10/20/2025 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 10/10/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 12/19/2024 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 10/28/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/06/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/12/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 08/12/2025 | Energy Code Compliance Inspections | — | progress |
| 08/12/2025 | Fire-Resistance Rated Construction | — | progress |
| 08/12/2025 | Metering | — | energy_progress |
| 08/12/2025 | Fenestration areas | — | energy_progress |
| 08/12/2025 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 08/12/2025 | Exterior lighting power | — | energy_progress |
| 08/12/2025 | Interior lighting power | — | energy_progress |
| 08/12/2025 | Maintenance information | — | energy_progress |
| 08/12/2025 | Insulation placement and R values | — | energy_progress |
| 08/12/2025 | Fenestration air leakage | — | energy_progress |
| 08/12/2025 | Lighting controls | — | energy_progress |
| 08/12/2025 | Air barrier - visual inspection | — | energy_progress |
| 08/12/2025 | Lighting in dwelling units | — | energy_progress |
| 08/12/2025 | Air barrier — testing | — | energy_progress |
| 04/15/2024 | Fire-Resistant Penetrations and Joints | — | special |
| 04/15/2024 | Energy Code Compliance Inspections | — | progress |
| 04/15/2024 | Fire-Resistance Rated Construction | — | progress |
| 04/15/2024 | Insulation placement and R values | — | energy_progress |
| 04/15/2024 | Air barrier — testing | — | energy_progress |
| 04/15/2024 | Fenestration air leakage | — | energy_progress |
| 04/15/2024 | Interior lighting power | — | energy_progress |
| 04/15/2024 | Air barrier - visual inspection | — | energy_progress |
| 04/15/2024 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 04/15/2024 | Lighting controls | — | energy_progress |