← Back
Two family converted from one family
174-41 126 AVENUE
💬 Discuss this project
1960Year Built
2Stories
B3Building Class
R3AZoning
1,770 sfGross Floor Area
2Units
Two family converted from one family · 3,080 sf lot · 0.57 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbing
Floor 26p · 2 filings · 20 docs
Floor 16p · 2 filings · 20 docs
Cellar11p · 2 filings · 20 docs
Site & exterior1p · 1 filing · 2 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
KOJO SIMPSON ARCHITECT607/25/2022
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
J&J DESIGNS INCGeneral Contractor807/08/2026
POWER SURGE ELECTRIC, INCElectrical103/22/2026
ROCK E SMALL PLBG&HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
KOJO SIMPSON ARCHITECT1664507/25/2022
Building Lifecycle
All (55)Filed (6)Permit Issued (5)Inspection (10)Objection (4)Special Inspection (30)
02/14/2023
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/11/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
08/03/2022
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
08/01/2022
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
07/30/2022
Special inspection requirement — Fenestration areas
KOJO SIMPSON
07/30/2022
Special inspection requirement — Fenestration and door U-factor and product ratings
KOJO SIMPSON
07/30/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
KOJO SIMPSON
07/30/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
KOJO SIMPSON
07/30/2022
Special inspection requirement — HVAC-R and service water heating system controls
KOJO SIMPSON
07/30/2022
Special inspection requirement — Air barrier - visual inspection
KOJO SIMPSON
07/30/2022
Special inspection requirement — Fire-Resistance Rated Construction
KOJO SIMPSON
07/30/2022
Special inspection requirement — Permanent certificate
KOJO SIMPSON
07/30/2022
Special inspection requirement — Metering
KOJO SIMPSON
07/30/2022
Special inspection requirement — Maintenance information
KOJO SIMPSON
07/30/2022
Special inspection requirement — HVAC-R and service water piping design and insulation
KOJO SIMPSON
07/30/2022
Special inspection requirement — Insulation placement and R values
KOJO SIMPSON
07/30/2022
Special inspection requirement — Fenestration air leakage
KOJO SIMPSON
07/30/2022
Special inspection requirement — HVAC-R and service water heating equipment
KOJO SIMPSON
07/30/2022
Special inspection requirement — Masonry
KOJO SIMPSON
07/30/2022
Special inspection requirement — Heating Systems
KOJO SIMPSON
07/30/2022
Special inspection requirement — Concrete - Cast-In-Place
KOJO SIMPSON
07/30/2022
Special inspection requirement — Mechanical Systems
KOJO SIMPSON
07/30/2022
Special inspection requirement — Energy Code Compliance Inspections
KOJO SIMPSON
07/30/2022
Special inspection requirement — Final
KOJO SIMPSON
07/30/2022
Special inspection requirement — Footing and Foundation
KOJO SIMPSON
07/30/2022
Special inspection requirement — Interior lighting power
KOJO SIMPSON
07/25/2022
Filed — Alteration CO
APPLICATION FILED FOR VERTICAL AND HORIZONTAL EXTENSION WITH MINOR INTERIOR RENOVATION, INSTALLATION OF HVAC AND CONVERSION FROM 1 TO 2 FAMILY DWELLING.
Q00509930-P4
07/15/2022
Special inspection requirement — Structural Stability – Alterations of existing buildings
KOJO SIMPSON
07/15/2022
Special inspection requirement — Concrete - Cast-In-Place
KOJO SIMPSON
07/15/2022
Special inspection requirement — Mechanical Systems
KOJO SIMPSON
07/15/2022
Special inspection requirement — Energy Code Compliance Inspections
KOJO SIMPSON
07/15/2022
Special inspection requirement — Heating Systems
KOJO SIMPSON
07/15/2022
Special inspection requirement — Fire-Resistant Penetrations and Joints
KOJO SIMPSON
07/15/2022
Special inspection requirement — Masonry
KOJO SIMPSON
07/15/2022
Special inspection requirement — Final
KOJO SIMPSON
07/11/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
05/27/2022
Filed — Alteration
Installation of plumbing fixtures & equipment in conjunction with application number Q00509930.
Q00510039-P1
05/24/2022
Filed — Alteration CO
APPLICATION FILED FOR VERTICAL AND HORIZONTAL EXTENSION WITH MINOR INTERIOR RENOVATION, INSTALLATION OF HVAC AND CONVERSION FROM 1 TO 2 FAMILY DWELLING.
Q00509930-P1
04/29/2022
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
04/29/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Roughing
Certified
View inspection ↗
04/29/2022
Inspection — Certified Water and Sanitary-WS-Sanitary Piping-Underground
Certified
View inspection ↗
04/18/2022
Permit issued — Plumbing
Q00510039-I1-PL
04/04/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
02/28/2022
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
09/24/2021
Permit issued — Mechanical Systems
Q00509930-I1-GC-CX
09/24/2021
Permit issued — Construction Fence
Q00510033-I1-FN
09/10/2021
Permit issued — Foundation
Q00509930-I1-GC-CX
08/11/2021
Permit issued — Construction Fence
Q00510033-I1-FN
05/28/2021
Filed — Alteration CO
APPLICATION FILED FOR VERTICAL AND HORIZONTAL EXTENSION WITH MINOR INTERIOR RENOVATION, INSTALLATION OF HVAC AND CONVERSION FROM 1 TO 2 FAMILY DWELLING.
Q00509930-I1
05/27/2021
Objection raised — Scope
05/27/2021
Objection resolved — Addressed
05/27/2021
Objection raised — Zoning
05/27/2021
Objection resolved — Addressed
05/14/2021
Filed — Alteration
Installation of plumbing fixtures & equipment in conjunction with application number Q00509930.
Q00510039-I1
05/14/2021
Filed — Alteration
Installation of temporary construction fence as per plan.
Q00510033-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedROCK E SMALL PLBG&HTG INC04/18/2022
DOB NOWMechanical SystemsPermit IssuedJ&J DESIGNS INC09/24/2021
DOB NOWConstruction FencePermit IssuedJ&J DESIGNS INC09/24/2021
DOB NOWFoundationPermit IssuedJ&J DESIGNS INC09/10/2021
DOB NOWConstruction FencePermit IssuedJ&J DESIGNS INC08/11/2021
BISOTISSUEDVOLTAIC SOLAIRE LLC01/31/2014
1 project · most recent 07/25/2022
Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
07/25/2022Permit IssuedJ&J DESIGNS INCAir Conditioning Systems, Heating Systems
Cooling
Midea DLCMRAH27CAK 27,000 BTU · Heat Pump Outdoor ×4
DLCMRAH36DAK 36,000 BTU · Heat Pump Outdoor ×2
Heating
Midea DLCMRAH27CAK 27,000 BTU · Heat Pump Outdoor ×4
DLCMRAH36DAK 36,000 BTU · Heat Pump Outdoor ×2
1 project · most recent 05/27/2022
Gas Water/Sanitary
FiledStatusContractorScope
05/27/2022Permit IssuedROCK E SMALL PLBG&HTG INCGas, Water/Sanitary
1 project · most recent 01/10/2023
General Wiring
FiledStatusContractorScope
01/10/2023CompletePOWER SURGE ELECTRIC, INCGeneral Wiring
1 project · most recent 07/25/2022
FiledStatusContractorScope
07/25/2022Permit IssuedJ&J DESIGNS INC2 scope_items
1 project · most recent 05/14/2021
Fence
FiledStatusContractorScope
05/14/2021Permit IssuedJ&J DESIGNS INCFence
▾Field Inspections (DOB CAP) — 10
DateTypeResultReport
02/14/2023Pass-Final CND-Occupancy InspectionPassView ↗
08/11/2022Pass-Final CND-Occupancy InspectionPassView ↗
08/03/2022Fail-Final PL - Up to 3 Requested FloorsFailView ↗
08/01/2022Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
07/11/2022Pass-Final CND-Occupancy InspectionPassView ↗
04/29/2022Certified Gas-Gas-Piping-RoughingCertifiedView ↗
04/29/2022Certified Water and Sanitary-WS-Sanitary Piping-RoughingCertifiedView ↗
04/29/2022Certified Water and Sanitary-WS-Sanitary Piping-UndergroundCertifiedView ↗
04/04/2022Pass-Final CND-Occupancy InspectionPassView ↗
02/28/2022Pass-Final CND-Occupancy InspectionPassView ↗
▾Special Inspection Requirements (DOB NOW) — 72
DateRequirementInspectorRole
07/30/2022Fire-Resistant Penetrations and JointsKOJO SIMPSONspecial
07/30/2022Fenestration air leakageKOJO SIMPSONenergy_progress
07/30/2022HVAC-R and service water heating equipmentKOJO SIMPSONenergy_progress
07/30/2022Fenestration areasKOJO SIMPSONenergy_progress
07/30/2022HVAC-R and service water piping design and insulationKOJO SIMPSONenergy_progress
07/30/2022HVAC-R and service water heating system controlsKOJO SIMPSONenergy_progress
07/30/2022Insulation placement and R valuesKOJO SIMPSONenergy_progress
07/30/2022Fenestration and door U-factor and product ratingsKOJO SIMPSONenergy_progress
07/30/2022Air barrier - visual inspectionKOJO SIMPSONenergy_progress
07/30/2022Permanent certificateKOJO SIMPSONenergy_progress
07/30/2022MeteringKOJO SIMPSONenergy_progress
07/30/2022Maintenance informationKOJO SIMPSONenergy_progress
07/30/2022Interior lighting powerKOJO SIMPSONenergy_progress
07/30/2022Footing and FoundationKOJO SIMPSONprogress
07/30/2022Energy Code Compliance InspectionsKOJO SIMPSONprogress
07/30/2022FinalKOJO SIMPSONprogress
07/30/2022Fire-Resistance Rated ConstructionKOJO SIMPSONprogress
07/30/2022Concrete - Cast-In-PlaceKOJO SIMPSONspecial
07/30/2022Mechanical SystemsKOJO SIMPSONspecial
07/30/2022MasonryKOJO SIMPSONspecial
07/30/2022Heating SystemsKOJO SIMPSONspecial
07/30/2022Structural Stability – Alterations of existing buildingsKOJO SIMPSONspecial
07/15/2022HVAC-R and service water piping design and insulationKOJO SIMPSONenergy_progress
07/15/2022Concrete - Cast-In-PlaceKOJO SIMPSONspecial
07/15/2022Fire-Resistant Penetrations and JointsKOJO SIMPSONspecial
Latest 25 of 72.
▾Documents — 67 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch6
08/27/2026Q00510033-I1Request digital key ↗
08/26/2026Q00510039-P1Request digital key ↗
08/26/2026Q00509930-P4Request digital key ↗
Showing 3 of 6 on file for this type
▸Applications & Permits2
▸BISPLAN / WORK APPROVAL APPLICATION1
01/29/2014440121823Open ↗
▸BISWORK PERMIT APPLICATION1
01/31/2014440121823Open ↗
▸Zoning, Tax Lot & Property Records4
▸DOB NOWZD1: DOB Zoning Diagram3
08/26/2026Q00509930-P1Open ↗
08/26/2026Q00509930-I1Open ↗
08/13/2026Q00509930-P4Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q00509930-I1Open ↗
▸Seals & Professional Certifications24
▸DOB NOWProgress Inspector Seal & Signature11
09/02/2026Q00509930-P4Open ↗
09/02/2026Q00509930-P4Open ↗
09/02/2026Q00509930-P4Open ↗
Showing 3 of 11 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/27/2026Q00510033-I1Open ↗
08/26/2026Q00510039-P1Open ↗
08/26/2026Q00510039-I1Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature4
09/02/2026Q00509930-P4Open ↗
08/31/2026Q00509930-I1Open ↗
08/28/2026Q00510039-I1Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY-CERTIFICATION2
06/17/2014440121823Open ↗
01/29/2014440121823Open ↗
▸BISApplicant / Owner Signature1
01/29/2014440121823Open ↗
▸Safety & Tenant Protection5
▸DOB NOWStreet Tree Checklist3
08/26/2026Q00509930-P1Open ↗
08/26/2026Q00509930-I1Open ↗
08/13/2026Q00509930-P4Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026Q00509930-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026Q00509930-I1Open ↗
▸Environmental & Asbestos6
▸DOB NOWDEP ACP-5: Asbestos Assessment Report5
08/26/2026Q00510039-P1Open ↗
08/26/2026Q00509930-P1Open ↗
08/26/2026Q00509930-I1Open ↗
Showing 3 of 5 on file for this type
▸BISACP5 ASBESTOS: CERTIFICATION (DEP ACP5)1
01/29/2014440121823Open ↗
▸Energy Compliance6
▸BISTR8: Energy Code Progress Inspections2
06/17/2014440121823Open ↗
01/29/2014440121823Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
10/28/2014440121823Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION1
10/28/2014440121823Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)1
01/29/2014440121823Open ↗
▸BISSOLAR TAX ABATEMENT APPLICATION (PTA4)1
06/06/2014440121823Open ↗
▸Approvals, Objections & Sign-offs3
▸BISLETTERS - SUPPORTING DOCUMENTATION1
06/17/2014440121823Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
06/06/2014440121823Open ↗
▸BISCERTIFICATE OF OCCUPANCY - LOC: REQUEST1
06/06/2014440121823Open ↗
▸Cost, Insurance & Ownership2
▸BISCOST AFFIDAVIT2
06/06/2014440121823Open ↗
01/29/2014440121823Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
01/29/2014440121823Open ↗
▸Other Documents8
▸DOB NOWPlot Diagram3
08/26/2026Q00509930-P1Open ↗
08/26/2026Q00509930-I1Open ↗
08/13/2026Q00509930-P4Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone3
08/26/2026Q00509930-P1Open ↗
08/26/2026Q00509930-I1Open ↗
08/13/2026Q00509930-P4Open ↗
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
06/17/2014440121823Open ↗
▸DOB NOWSite Survey: Initial1
08/13/2026Q00509930-P4Open ↗