| Owner | Filings | Most Recent |
|---|---|---|
| J G CONSTRUCTION SRVCS | 5 | 04/09/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 02/13/2024 | $2.5M | — | Private party → Private party | $1,437/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| MARK WEINBERGER ARCHITECT PLLC | 8 | 07/29/2026 |
| KMA DESIGNS LLC | 1 | 08/01/2025 |
| R & O ENGINEERING | 3 | 03/04/2025 |
| ARYEH SIEGEL ARCHITECT | 1 | 02/23/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| EXPEDITER GROUP | 18 | 03/21/2026 |
| AVALON DESIGNS | 4 | 03/21/2026 |
| KMA DESIGNS LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CLASSIC BUILDERS CORP | General Contractor | 9 | 07/08/2026 |
| HEXAGON INDUSTRIES INC | General Contractor | 3 | 03/21/2026 |
| ORBIT PLBG & HTG INC | Plumbing | 2 | 09/22/2026 |
| WIZ FIRE SPRINKLERS LLC | Fire Protection | 1 | 06/28/2026 |
| RICHARD NEU | Electrical | 1 | 03/22/2026 |
| J & G CONSTRUCTION SVCS | General Contractor | 1 | 04/09/2026 |
| PLUMBING NYC INC | Plumbing | 1 | 09/02/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ENGINEERING CONSULTING SE | 2050 | 11 | 07/29/2026 |
| HRF SERVICES CORP | 5616 | 1 | 03/21/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | ORBIT PLBG & HTG INC | 09/21/2026 |
| DOB NOW | Plumbing | Permit Issued | PLUMBING NYC INC | 09/01/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | CLASSIC BUILDERS CORP | 04/15/2026 |
| DOB NOW | Construction Fence | Permit Issued | CLASSIC BUILDERS CORP | 03/18/2026 |
| DOB NOW | Sprinklers | Permit Issued | WIZ FIRE SPRINKLERS LLC | 11/24/2025 |
| DOB NOW | Plumbing | Permit Issued | ORBIT PLBG & HTG INC | 10/20/2025 |
| DOB NOW | Sidewalk Shed | Permit Issued | J & G CONSTRUCTION SVCS | 08/04/2025 |
| DOB NOW | Support of Excavation | Permit Issued | CLASSIC BUILDERS CORP | 07/31/2025 |
| DOB NOW | Earth Work | Permit Issued | CLASSIC BUILDERS CORP | 07/31/2025 |
| DOB NOW | Structural | Permit Issued | CLASSIC BUILDERS CORP | 07/31/2025 |
| DOB NOW | General Construction | Permit Issued | CLASSIC BUILDERS CORP | 07/30/2025 |
| DOB NOW | Construction Fence | Permit Issued | CLASSIC BUILDERS CORP | 03/24/2025 |
| DOB NOW | Full Demolition | Signed-off | HEXAGON INDUSTRIES INC | 05/03/2024 |
| DOB NOW | Construction Fence | Permit Issued | CLASSIC BUILDERS CORP | 03/04/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/29/2026 | Permit Issued | CLASSIC BUILDERS CORP | Heating and Air Conditioning Systems, Ventilation Systems | Heat / Cool Mitsubishi Electric MXZ-SM36NAMHZ 36,000 BTU · Heat Pump Outdoor ×2 MXZ-SM48NAMHZ 48,000 BTU · Heat Pump Outdoor ×2 Ventilation Greenheck SP-B80 46 CFM · Exhaust Fan ×6 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Permit Issued | WIZ FIRE SPRINKLERS LLC | Sprinkler System |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Permit Issued | ORBIT PLBG & HTG INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/11/2026 | Permit Issued | B.P. ELECTRIC CORP | General Wiring |
| 08/04/2025 | Permit Issued | RICHARD NEU | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Permit Issued | ORBIT PLBG & HTG INC | Steel, Concrete, Masonry |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/01/2025 | Permit Issued | J & G CONSTRUCTION SVCS | Sidewalk Shed |
| 02/23/2024 | Permit Issued | CLASSIC BUILDERS CORP | Fence |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 07/29/2026 | Permit Issued | ORBIT PLBG & HTG INC | Earthwork |
| Date | Type | Result | Report |
|---|---|---|---|
| 08/21/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 08/17/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/09/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/16/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/30/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/28/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 01/08/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/22/2025 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 12/09/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 12/09/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 11/14/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 08/04/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/07/2026 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 04/07/2026 | Maintenance information | PAUL MARINO | energy_progress |
| 04/07/2026 | HVAC-R and service water piping design and insulation | PAUL MARINO | energy_progress |
| 04/07/2026 | HVAC-R and service water heating system controls | PAUL MARINO | energy_progress |
| 04/07/2026 | HVAC-R and service water heating equipment | PAUL MARINO | energy_progress |
| 04/07/2026 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 03/30/2026 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 03/30/2026 | HVAC-R and service water piping design and insulation | PAUL MARINO | energy_progress |
| 03/30/2026 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 03/30/2026 | HVAC-R and service water heating equipment | PAUL MARINO | energy_progress |
| 03/30/2026 | HVAC-R and service water heating system controls | PAUL MARINO | energy_progress |
| 03/30/2026 | Maintenance information | PAUL MARINO | energy_progress |
| 01/23/2026 | Energy Code Compliance Inspections | PAUL MARINO | progress |
| 01/23/2026 | Fire-Resistance Rated Construction | PAUL MARINO | progress |
| 01/23/2026 | Fire-Resistant Penetrations and Joints | PAUL MARINO | special |
| 01/23/2026 | Exterior Insulation and Finish Systems (EIFS) | PAUL MARINO | special |
| 01/23/2026 | Fenestration and door U-factor and product ratings | PAUL MARINO | energy_progress |
| 01/23/2026 | Metering | PAUL MARINO | energy_progress |
| 01/23/2026 | Fenestration areas | PAUL MARINO | energy_progress |
| 01/23/2026 | Permanent certificate | PAUL MARINO | energy_progress |
| 01/23/2026 | Air barrier — testing | PAUL MARINO | energy_progress |
| 01/23/2026 | Fenestration air leakage | PAUL MARINO | energy_progress |
| 01/23/2026 | Electric vehicle service equipment requirements | PAUL MARINO | energy_progress |
| 01/23/2026 | Air barrier - visual inspection | PAUL MARINO | energy_progress |
| 01/23/2026 | Maintenance information | PAUL MARINO | energy_progress |