ECB03/17/20261RCNY 103-09(E). FAILURE TO FILE A RETAINING WALL CONDITION ASSESSMENTREPORT BY THE DEADLINE AS REQUIRED BY 1RCNY 103-09(E)(2) AND (5). TO DATE, THE DEPARTMENT HAS NOT RECEIVED A RETAINING WALL CONDITION ASSESS$6K due
DOB11/14/2025VIOLATION ISSUED-FAILURE TO FILE 2024 EXTERNAL LOW PRESSURE INSPECTION
DOB09/23/2024VIOLATION ISSUED-FAILURE TO FILE 2023 EXTERNAL LOW PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2020 EXTERNAL LOW PRESSURE INSPECTION
DOB06/30/2023VIOLATION ISSUED-FAILURE TO FILE 2021 EXTERNAL LOW PRESSURE INSPECTION
DOB06/20/2023VIOLATION ISSUED-FAILURE TO FILE 2018 EXTERNAL LOW PRESSURE INSPECTION
DOB04/25/2023VIOLATION ISSUED-FAILURE TO FILE 2022 EXTERNAL LOW PRESSURE INSPECTION
DOB05/15/2014VIOLATION ISSUED FOR FAILURE TO FILE ANNUAL BOILER 2012 INSPECTION REPORT
ECB08/16/2019NEED TO INSTALL PIGTAILS ON BOTH CONTROLS, NEED TO SEAL AROUND CHIMNEY. NEED TO FIX BOILER ROOM DOOR.Nothing owed — awaiting certificate of correction
Church, synagogue, chapel · 14,740 sf lot · 0.92 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.