1 Active Violation 0 unresolved · 1 paperwork only ▸FDNY Report ↗
Church, synagogue, chapel · 4,000 sf lot · 2.61 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalMechanicalPlumbingFire ProtectionEquipmentLandscapeCivilGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
RoofTemporary pipe scaffold and sidewalk shed1p · 1 filing · 5 docs
Floor 3Quentin Road Synagogue13p · 3 filings · 11 docs
Floor 2Quentin Road Synagogue24p · 3 filings · 12 docs
Floor 1Quentin Road Synagogue23p · 3 filings · 12 docs
CellarQuentin Road Synagogue5p · 1 filing · 1 doc
Site & exterior6p · 1 filing · 2 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
Expert Groupenterprises503/22/2026
▾Design Consultants (Architect / Engineer of Record)
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
2020 Group Service403/21/2026
Expedia Building Solution103/21/2026
ASAP Associates203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
Expert GroupenterpriseScaffold507/08/2026
John Evan ContractingGeneral Contractor203/22/2026
Expert Plumbing & HeatingPlumbing203/22/2026
Safety Fire SprinklerFire Protection207/08/2026
Expert Plumbing & HeatingGeneral Contractor103/22/2026
M.N.C. General ContractorsGeneral Contractor103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
O'Rourke Engineering5873108/05/2019
Building Lifecycle
All (50)Filed (10)Permit Issued (5)Signed Off (3)Violation (19)Objection (8)Special Inspection (5)
03/07/2026
Special inspection requirement — Public Assembly Emergency Lighting
NAVEEN KUMAR
02/24/2026
Objection resolved — Addressed
02/20/2026
Objection raised — Admin
02/09/2026
Special inspection requirement — Public Assembly Emergency Lighting
NAVEEN KUMAR
01/29/2026
Filed — No Work
B00528200-P2
01/29/2026
Filed — No Work
B00528207-P1
01/29/2026
Filed — No Work
B00492985-P1
01/29/2026
Special inspection requirement — Public Assembly Emergency Lighting
NAVEEN KUMAR
07/16/2025
Special inspection requirement — Public Assembly Emergency Lighting
NAVEEN KUMAR
07/16/2025
Special inspection requirement — Public Assembly Emergency Lighting
NAVEEN KUMAR
04/16/2025
Violation issued (FDNY_ORDER, closed)
06/14/2022
Signed off — Alteration
B00189626-I1
06/25/2021
Objection raised — Structural
06/25/2021
Objection resolved — Addressed
06/25/2021
Objection raised — Structural
06/25/2021
Objection resolved — Addressed
06/25/2021
Objection raised — Inspections
06/25/2021
Objection resolved — Addressed
06/17/2021
Filed — No Work
B00528200-I1
06/17/2021
Filed — No Work
B00492985-I1
06/17/2021
Filed — No Work
B00528207-I1
04/23/2021
Permit issued — Sprinklers
B00189626-I1-EW-SP
02/03/2021
Violation issued (FDNY_ORDER, closed)
01/27/2020
Signed off — Alteration
B00177151-I1
10/25/2019
Permit issued — Sprinklers
B00189626-I1-EW-SP
10/08/2019
Signed off — Alteration
INSTALLATION OF TEMPORARY (12'-42') HIGH PIPE SCAFFOLD AT VARIOUS LEVELS FOR NEW BUILDING CONSTRUCTION WORK AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY,PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE.HEAVY DUTY SIDEWALK SHED FILED UNDER SEPARATE APPLICATION#440304804.
B00063214-I1
08/05/2019
Filed — Alteration
B00189626-I1
06/07/2019
Permit issued — Sidewalk Shed
B00177151-I1-SH
06/06/2019
Filed — Alteration
B00177151-I1
05/22/2019
Violation issued (ECB, closed)
Construction
05/22/2019
Violation issued (ECB, closed)
Construction
05/22/2019
Violation issued (ECB, closed)
Construction
05/22/2019
Violation issued (ECB, closed)
Construction
05/22/2019
Violation issued (ECB, closed)
Construction
05/16/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
05/16/2019
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
04/06/2019
Filed — Alteration
INSTALLATION OF TEMPORARY (12'-42') HIGH PIPE SCAFFOLD AT VARIOUS LEVELS FOR NEW BUILDING CONSTRUCTION WORK AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY,PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE.HEAVY DUTY SIDEWALK SHED FILED UNDER SEPARATE APPLICATION#440304804.
B00063214-P1
02/20/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
02/20/2019
Violation issued (ECB, closed)
Construction
10/05/2018
Permit issued — Supported Scaffold
B00063214-I1-SF
07/20/2018
Permit issued — Supported Scaffold
B00063214-I1-SF
07/19/2018
Filed — Alteration
INSTALLATION OF TEMPORARY (12'-42') HIGH PIPE SCAFFOLD AT VARIOUS LEVELS FOR NEW BUILDING CONSTRUCTION WORK AS PER PLAN. NO CHANGE IN USE EGRESS OR OCCUPANCY,PIPE SCAFFOLD SHALL COMPLY WITH CHAPTER#33 OF 2014 THE NY BUILDING CODE.HEAVY DUTY SIDEWALK SHED FILED UNDER SEPARATE APPLICATION#440304804.
B00063214-I1
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSprinklersSigned-offSafety Fire Sprinkler04/23/2021
DOB NOWSprinklersSigned-offSafety Fire Sprinkler10/25/2019
DOB NOWSidewalk ShedSigned-offExpert Groupenterprise06/07/2019
DOB NOWSupported ScaffoldSigned-offExpert Groupenterprise10/05/2018
DOB NOWSupported ScaffoldSigned-offExpert Groupenterprise07/20/2018
BISPLISSUEDExpert Plumbing & Heating02/26/2025
BIS—ISSUEDJohn Evan Contracting01/30/2025
BIS—ISSUEDM.N.C. General Contractors11/24/2021
BIS—ISSUEDM.N.C. General Contractors10/29/2020
BIS—ISSUEDM.N.C. General Contractors10/25/2020
BIS—ISSUEDM.N.C. General Contractors05/19/2020
BIS—RE-ISSUEDM.N.C. General Contractors10/15/2019
BISEQISSUEDM.N.C. General Contractors07/18/2019
BISPLISSUEDS & J Industrial05/22/2019
BIS—ISSUEDM.N.C. General Contractors10/15/2018
BIS—ISSUEDM.N.C. General Contractors07/25/2018
BISMHISSUEDM.N.C. General Contractors07/20/2018
BISEQISSUEDM.N.C. General Contractors07/20/2018
BISEQISSUEDM.N.C. General Contractors04/24/2018
BISEQISSUEDM.N.C. General Contractors04/24/2018
BIS—ISSUEDM.N.C. General Contractors04/24/2018
BISMHISSUEDM.N.C. General Contractors08/07/2017
BISMHISSUEDMetro Mechanical07/28/2017
BISEQISSUEDM.N.C. General Contractors07/25/2017
BISOTISSUEDM.N.C. General Contractors07/21/2017
BISEQISSUEDMRM Development02/29/2012
BISEQISSUEDMRM Development01/03/2012
3 projects · most recent 10/16/2019
General Wiring
FiledStatusContractorScope
10/16/2019CompleteTuxedo Electrical Contracting—
07/07/2019Permit IssuedAlef Electrical ContractingGeneral Wiring
06/06/2019CompleteMeo Electric—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/07/2026Public Assembly Emergency LightingNAVEEN KUMARprogress
02/09/2026Public Assembly Emergency LightingNAVEEN KUMARprogress
01/29/2026Public Assembly Emergency LightingNAVEEN KUMARprogress
07/16/2025Public Assembly Emergency LightingNAVEEN KUMARprogress
07/16/2025Public Assembly Emergency LightingNAVEEN KUMARprogress
▾Tenants in the building
TenantSpaceFloorsRenovation projects
Quentin Road SynagogueReligiousCellar, Floors 1–3
Project B00492985 No Work · PA Certificate of Operation Issued · 06/17/2021
Project B00528200 No Work · PA Certificate of Operation Issued · 06/17/2021
Project B00528207 No Work · PAA Approved · 06/17/2021
Project B00189626 Alteration · LOC Issued · 08/05/2019
Names are taken automatically from the text of each project’s filed documents (title blocks and cover sheets) and screened to exclude owners, landlords and designers. They may be incomplete or wrong; check the filing.
▾Documents — 190 on file (BIS + DOB NOW)
▸Plans & Drawings11
▸DOB NOWPlans/Sketch - Place of Assembly6
09/01/2026B00528200-I1Request digital key ↗
09/01/2026B00528200-P2Request digital key ↗
09/01/2026B00528207-P1Request digital key ↗
Showing 3 of 6 on file for this type
▸DOB NOWPlans/Sketch - Supported Scaffold2
09/03/2026B00063214-I1Request digital key ↗
08/15/2026B00063214-P1Request digital key ↗
▸DOB NOWPlans/Sketch1
09/03/2026B00063214-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sprinkler1
09/02/2026B00189626-I1Request digital key ↗
▸DOB NOWPlans/Sketch - Sidewalk Shed1
09/02/2026B00177151-I1Request digital key ↗
▸Applications & Permits60
▸BISPLAN / WORK APPROVAL APPLICATION35
05/16/2025321313538Open ↗
05/14/2025321313538Open ↗
04/09/2025321313538Open ↗
Showing 3 of 35 on file for this type
▸BISWORK PERMIT APPLICATION20
02/26/2025321313538Open ↗
02/06/2025321313538Open ↗
01/31/2025320197381Open ↗
Showing 3 of 20 on file for this type
▸BISBPP-5 - Authorization to the Department of Transportation4
01/25/2019321829811Open ↗
09/13/2018321829811Open ↗
09/13/2018321829811Open ↗
Showing 3 of 4 on file for this type
▸BISCERTIFICATE OF OCCUPANCY: APPLICATION1
09/14/2022320197381Open ↗
▸Zoning, Tax Lot & Property Records5
▸BISADDRESS - NEW HOUSE NUMBER APPROVED1
08/12/2010320197381Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
12/06/2016320197381Open ↗
▸BISCO OBJ: VERIFY ADDRESS-TOPO STAMP1
01/14/2025320197381Open ↗
▸BISZONING DIAGRAM1
12/14/2016320197381Open ↗
▸BISZONING EXHIBIT I: CERTIFICATION1
12/06/2016320197381Open ↗
▸Seals & Professional Certifications25
▸DOB NOWDPL-1: Design Professional Seal & Signature10
09/03/2026B00063214-P1Open ↗
09/03/2026B00063214-I1Open ↗
09/02/2026B00177151-I1Open ↗
Showing 3 of 10 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION6
10/04/2017320197381Open ↗
10/03/2017320197381Open ↗
07/31/2017321313538Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProgress Inspector Seal & Signature5
09/21/2026B00528200-P2Open ↗
08/29/2026B00528207-P1Open ↗
08/26/2026B00528200-I1Open ↗
Showing 3 of 5 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST2
02/20/2016321313538Open ↗
01/05/2012320415984Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
02/20/2016321313538Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
01/05/2012320415984Open ↗
▸Trade Schedules & Equipment3
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
02/20/2016321313538Open ↗
▸BISSCHEDULE B - PLUMBING1
08/12/2010320197381Open ↗
▸BISDEP SANITARY SEWER CERTIFICATION (HCP/SCP)1
07/18/2017320197381Open ↗
▸Safety & Tenant Protection7
▸BISSTREET TREE CHECKLIST4
03/12/2020321829811Open ↗
12/12/2018321829811Open ↗
12/06/2016320197381Open ↗
Showing 3 of 4 on file for this type
▸BISSTREET TREES: RECEIPT OF STREET TREES SITE PLAN1
04/25/2018320197381Open ↗
▸BISSTREET TREE SIGNOFF1
01/26/2022320197381Open ↗
▸BISEXCAVATION - SHEETING, SHORING, AND BRACING1
05/21/2025321315821Open ↗
▸Environmental & Asbestos1
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER1
08/12/2010320197381Open ↗
▸Energy Compliance3
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS2
10/03/2017320197381Open ↗
02/24/2016321313538Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
05/15/2025321313538Open ↗
▸Inspections & Test Reports10
▸BISTECHNICAL REPORT: RESPONSIBILITY4
05/21/2025321315821Open ↗
05/21/2025321315821Open ↗
05/15/2025321313538Open ↗
Showing 3 of 4 on file for this type
▸BISTECHNICAL REPORT: CONCRETE DESIGN MIX2
04/25/2018320197381Open ↗
04/25/2018320197381Open ↗
▸BISMECHANICAL SYSTEMS1
05/15/2025321313538Open ↗
▸BISD-14 FINAL INSPECTION1
05/16/2025321313538Open ↗
▸BISTECHNICAL REPORT: SOIL INSPECTION1
12/14/2016320197381Open ↗
▸BISTECHNICAL REPORT: CONCRETE/TEST CYLINDER1
04/25/2018320197381Open ↗
▸Approvals, Objections & Sign-offs29
▸BISSCHEDULE A - OCCUPANCY / USE9
04/03/2025320197381Open ↗
04/01/2025320197381Open ↗
03/08/2022320197381Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter6
09/01/2026B00528200-I1Open ↗
09/01/2026B00528200-P2Open ↗
09/01/2026B00528207-I1Open ↗
Showing 3 of 6 on file for this type
▸BISLETTERS - SUPPORTING DOCUMENTATION5
01/31/2025320197381Open ↗
08/08/2017321313538Open ↗
08/08/2017321313538Open ↗
Showing 3 of 5 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
05/22/2025321315821Open ↗
05/16/2025321313538Open ↗
01/30/2025320415984Open ↗
▸BISADMINISTRATIVE OBJECTIONS3
04/11/2013320741257Open ↗
01/05/2012320415984Open ↗
08/12/2010320197381Open ↗
▸BISFINAL1
05/21/2025321315821Open ↗
▸BISBSA/CPC APPROVAL1
10/19/2016320197381Open ↗
▸BISSUPERSEDING LETTER1
02/26/2025321313538Open ↗
▸Cost, Insurance & Ownership13
▸BISAcord 25 (Acord Certificate of Liability Insurance)3
11/26/2021320197381Open ↗
10/15/2019320197381Open ↗
07/30/2019320197381Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE3
01/31/2025320197381Open ↗
11/26/2021320197381Open ↗
07/30/2019320197381Open ↗
▸BISPROJECT SPECIFIC GENERAL LIABILITY INSURANCE3
10/15/2019320197381Open ↗
07/25/2018320197381Open ↗
04/25/2018320197381Open ↗
▸BISCOST AFFIDAVIT2
02/20/2016321313538Open ↗
08/12/2010320197381Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW32
05/21/2025321315821Open ↗
05/15/2025321313538Open ↗
▸Filing & Intake Forms18
▸BISEFILING COVER SHEET9
09/13/2018321829811Open ↗
03/03/2016321322118Open ↗
02/24/2016321315821Open ↗
Showing 3 of 9 on file for this type
▸BISADDITIONAL INFORMATION4
05/12/2025320197381Open ↗
04/09/2025321313538Open ↗
03/12/2025321313538Open ↗
Showing 3 of 4 on file for this type
▸BISBOROUGH INTAKE FORM3
11/26/2021320197381Open ↗
10/13/2021320197381Open ↗
05/28/2019321313538Open ↗
▸BISBPP: CHECKLIST IN LIEU OF PLANS-ALT32
01/25/2019321829811Open ↗
04/11/2013320741257Open ↗
▸Other Documents5
▸BISCONSTRUCTION - SUPPORTING DOCUMENTATION1
05/03/2022320197381Open ↗
▸BISPLOT DIAGRAM1
08/12/2010320197381Open ↗
▸BISBSA VARIANCE1
10/19/2016320197381Open ↗
▸BISEXTERNAL FORMS - SUPPORTING DOCUMENTATION1
07/25/2017320415984Open ↗
▸DOB NOWBSA Meeting Minutes/BSA Resolution1
08/13/2026B00177151-I1Open ↗