| Owner | Filings | Most Recent |
|---|---|---|
| ZMIROT | 16 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 07/19/2024 | $1.3M | — | — → — | $450/sf building |
| 12/21/2023 | $520K | — | — → — | $178/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| GREEN RIVER ENVIRONMENTAL ENGINEERI | 1 | 12/17/2025 |
| J.K.DESIGN | 4 | 05/09/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| NY State Solar LLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| 26 BONIM LLC | General Contractor | 4 | 03/21/2026 |
| POWER SURGE ELECTRIC, INC | Electrical | 1 | 03/22/2026 |
| NYSS LLC | General Contractor | 1 | 07/08/2026 |
| PLBG P & H INC | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GREEN RIVER ENVIRONMENTAL | 7841 | 1 | 12/17/2025 |
| TRIANGLE INSPECTION & TES | 7495 | 1 | 05/09/2024 |
| AA BUILDING & INSPECTION | 1519 | 2 | 03/05/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | NYSS LLC | 12/18/2025 |
| DOB NOW | Plumbing | Signed-off | PLBG P & H INC | 03/07/2024 |
| DOB NOW | Foundation | Permit Issued | 26 BONIM | 03/04/2024 |
| DOB NOW | Construction Fence | Signed-off | 26 BONIM | 02/08/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/16/2025 | Complete | NY SOLAR ELECTRICAL LLC | — |
| 03/14/2024 | Complete | POWER SURGE ELECTRIC, INC | General Wiring |
| 03/20/2019 | Complete | HI-TECH WIRING ELECL SVCS | 1 meters, 1 new_meters |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/09/2024 | Permit Issued | 26 BONIM LLC | Concrete, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 09/03/2024 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 07/22/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 07/15/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 06/26/2024 | Fail-Final PL - Up to 9 Requested Floors | Fail | View ↗ |
| 06/14/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 05/10/2024 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/03/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 04/03/2024 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/03/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 03/25/2024 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 03/25/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 05/03/2024 | Chimneys and vents | Rajasekhar Sakhamuri | special |
| 05/03/2024 | Concrete - Cast-In-Place | Rajasekhar Sakhamuri | special |
| 05/03/2024 | Fire-Resistant Penetrations and Joints | Rajasekhar Sakhamuri | special |
| 05/03/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Rajasekhar Sakhamuri | special |
| 05/03/2024 | Structural Stability – Alterations of existing buildings | Rajasekhar Sakhamuri | special |
| 05/03/2024 | Subgrade Inspections | Rajasekhar Sakhamuri | special |
| 05/03/2024 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 05/03/2024 | Energy Code Compliance Inspections | Rajasekhar Sakhamuri | progress |
| 05/03/2024 | Final | Rajasekhar Sakhamuri | progress |
| 05/03/2024 | Fire-Resistance Rated Construction | Rajasekhar Sakhamuri | progress |
| 05/03/2024 | Footing and Foundation | Rajasekhar Sakhamuri | progress |
| 05/03/2024 | Structural Wood Frame | Rajasekhar Sakhamuri | progress |
| 05/03/2024 | Interior lighting power | Rajasekhar Sakhamuri | energy_progress |
| 05/03/2024 | Permanent certificate | Rajasekhar Sakhamuri | energy_progress |
| 05/03/2024 | Electric vehicle service equipment requirements | Rajasekhar Sakhamuri | energy_progress |
| 05/03/2024 | Fenestration areas | Rajasekhar Sakhamuri | energy_progress |
| 05/03/2024 | Fenestration air leakage | Rajasekhar Sakhamuri | energy_progress |
| 05/03/2024 | Insulation placement and R values | Rajasekhar Sakhamuri | energy_progress |
| 05/03/2024 | Fenestration and door U-factor and product ratings | Rajasekhar Sakhamuri | energy_progress |
| 05/03/2024 | Metering | Rajasekhar Sakhamuri | energy_progress |
| 05/03/2024 | Air barrier - visual inspection | Rajasekhar Sakhamuri | energy_progress |
| 02/01/2024 | Fire-Resistant Penetrations and Joints | Younes Abouyaala | special |
| 02/01/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Younes Abouyaala | special |
| 02/01/2024 | Soil Percolation Test - Private On-Site Storm Water Drainage Disposal Systems, and Detention Facilities | Younes Abouyaala | special |
| 02/01/2024 | Energy Code Compliance Inspections | Younes Abouyaala | progress |