| Firm | Filings | Most Recent |
|---|---|---|
| C&P DESIGN CONSULTANTS | 2 | 02/05/2026 |
| PARKER AND WEST ENGINEERING, PLLC | 2 | 11/18/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| SUNRUN | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SUNRUN INSTALLATION SVC | General Contractor | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| PARKER AND WEST ENGINEERI | 5272 | 2 | 11/18/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Signed-off | SUNRUN INSTALLATION SVC | 10/25/2024 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 10/22/2024 | Complete | SUNRUN SOLAR ELECTL CORP | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/05/2026 | — | — | Wood |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 02/19/2026 | Footing and Foundation | — | progress |
| 02/19/2026 | Concrete - Cast-In-Place | — | special |
| 02/19/2026 | Subgrade Inspections | — | special |
| 02/19/2026 | Final | — | progress |
| 02/03/2026 | Concrete - Cast-In-Place | — | special |
| 02/03/2026 | Subgrade Inspections | — | special |
| 02/03/2026 | Final | — | progress |
| 02/03/2026 | Footing and Foundation | — | progress |