| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 10/23/2025 | $1.4M | — | Private party → Private party | $731/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| HALO ARCHITECTURE PLLC | 3 | 08/11/2026 |
| CLIP ARCHITECTS | 7 | 06/24/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| MODERN BUILDING CONSULTANT | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JZ CONSTRUCTION GROUP INC | General Contractor | 2 | 06/28/2026 |
| AMC PLBG, HTG & CLNG, INC | Plumbing | 1 | 06/27/2026 |
| PREMIER FLOW PLBG AND HTG | Plumbing | 1 | 06/27/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| GREAT WALL CONSULTANT P.E | 5633 | 10 | 08/11/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | JZ CONSTRUCTION GROUP INC | 06/25/2026 |
| DOB NOW | Plumbing | Permit Issued | AMC PLBG, HTG & CLNG, INC | 03/27/2026 |
| DOB NOW | Plumbing | Permit Issued | GALICJA PLBG AND HTG.CORP | 11/14/2025 |
| DOB NOW | General Construction | Signed-off | JZ CONSTRUCTION GROUP INC | 11/13/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/24/2026 | Permit Issued | AMC PLBG, HTG & CLNG, INC | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/18/2025 | Permit Issued | FIRST STAR ELECTRIC INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 07/14/2026 | Pass-Final SP - Up to 3 Requested Floors | Pass | View ↗ |
| 06/25/2026 | Fail-Final SP - Up to 3 Requested Floors | Fail | View ↗ |
| 04/27/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/23/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 04/02/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 09/11/2023 | No Access-Final SP - Up to 3 Requested Floors | No Access | View ↗ |
| 06/30/2023 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 07/28/2026 | Metering | Xiong Wei Wu | energy_progress |
| 07/28/2026 | Interior lighting power | Xiong Wei Wu | energy_progress |
| 07/28/2026 | Permanent certificate | Xiong Wei Wu | energy_progress |
| 07/28/2026 | Fenestration and door U-factor and product ratings | Xiong Wei Wu | energy_progress |
| 07/28/2026 | Fenestration areas | Xiong Wei Wu | energy_progress |
| 07/28/2026 | Maintenance information | Xiong Wei Wu | energy_progress |
| 07/28/2026 | Fenestration air leakage | Xiong Wei Wu | energy_progress |
| 07/28/2026 | Electric vehicle service equipment requirements | Xiong Wei Wu | energy_progress |
| 07/28/2026 | Fire-Resistance Rated Construction | Xiong Wei Wu | progress |
| 07/28/2026 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 07/28/2026 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 07/06/2026 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 07/06/2026 | Fire-Resistance Rated Construction | Xiong Wei Wu | progress |
| 07/06/2026 | Energy Code Compliance Inspections | Xiong Wei Wu | progress |
| 07/06/2026 | Fenestration and door U-factor and product ratings | Xiong Wei Wu | energy_progress |
| 07/06/2026 | Fenestration areas | Xiong Wei Wu | energy_progress |
| 07/06/2026 | Electric vehicle service equipment requirements | Xiong Wei Wu | energy_progress |
| 07/06/2026 | Permanent certificate | Xiong Wei Wu | energy_progress |
| 07/06/2026 | Metering | Xiong Wei Wu | energy_progress |
| 07/06/2026 | Fenestration air leakage | Xiong Wei Wu | energy_progress |
| 07/06/2026 | Maintenance information | Xiong Wei Wu | energy_progress |
| 07/06/2026 | Interior lighting power | Xiong Wei Wu | energy_progress |
| 06/26/2026 | Fire-Resistant Penetrations and Joints | Xiong Wei Wu | special |
| 06/26/2026 | Interior lighting power | Jaeyoung Jang | energy_progress |
| 06/26/2026 | Fire-Resistance Rated Construction | Jaeyoung Jang | progress |