← Back
Two stories - detached, small or mid-size
176-35 133 ROAD
💬 Discuss this project
1930Year Built
2.5Stories
A1Building Class
R3XZoning
—Gross Floor Area
1Units
Two stories - detached, small or mid-size · 0.31 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
Nothing on file for this building.
Nothing on file for this building.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
BISOTISSUEDCENTURION SOLAR ENERGY09/26/2018
BISOTISSUED1ST LIGHT ENERGY INC01/11/2018
1 project · most recent 10/04/2018
FiledStatusContractorScope
10/04/2018CompleteAMBER ELECTL CONTNG INC—
Nothing on file for this building.
▾Documents — 32 on file (BIS + DOB NOW)
▸Applications & Permits5
▸BISPLAN / WORK APPROVAL APPLICATION3
09/20/2018440510528Open ↗
09/19/2018440456917Open ↗
12/29/2017440456917Open ↗
▸BISWORK PERMIT APPLICATION2
09/20/2018440510528Open ↗
01/11/2018440456917Open ↗
▸Seals & Professional Certifications4
▸BISREQUIRED ITEMS CHECKLIST FOR PROFESSIONAL CERTIFICATION1
09/20/2018440510528Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
09/20/2018440510528Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
12/29/2017440456917Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
09/20/2018440510528Open ↗
▸Safety & Tenant Protection2
▸BISTENANT PROTECTION PLAN AND NOTES2
09/20/2018440510528Open ↗
12/29/2017440456917Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)2
09/20/2018440510528Open ↗
12/29/2017440456917Open ↗
▸Energy Compliance8
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY3
11/30/2018440510528Open ↗
09/20/2018440510528Open ↗
12/29/2017440456917Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (PRELIMINARY)2
09/20/2018440510528Open ↗
12/29/2017440456917Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
11/30/2018440510528Open ↗
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
09/20/2018440510528Open ↗
▸BISPTA4: SOLAR TAX ABATEMENT APPLICATION (FINAL)1
11/30/2018440510528Open ↗
▸Inspections & Test Reports3
▸BISTECHNICAL REPORT: RESPONSIBILITY3
11/30/2018440510528Open ↗
09/20/2018440510528Open ↗
12/29/2017440456917Open ↗
▸Approvals, Objections & Sign-offs2
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
11/30/2018440510528Open ↗
▸BISUtility Company PV System Interconnection Acknowledgement Letter1
11/30/2018440510528Open ↗
▸Cost, Insurance & Ownership3
▸BISCOST AFFIDAVIT3
11/30/2018440510528Open ↗
09/20/2018440510528Open ↗
12/29/2017440456917Open ↗
▸Filing & Intake Forms3
▸BISEFILING JOB APPLICATION COVER SHEET2
09/20/2018440510528Open ↗
12/29/2017440456917Open ↗
▸BISADDITIONAL INFORMATION1
01/10/2018440456917Open ↗