← Back
Parks / recreation facility
176 STREET
QUEENS · BIN 4625627
💬 Discuss this project
0Year Built
—Stories
Q1Building Class
PARKZoning
0 sfGross Floor Area
0Units
Parks / recreation facility · Owner of record: NYC DEPARTMENT OF PARKS AND RECREATION · 686,900 sf lot · 0 FAR built · Flood zone X
Locations of Work
StructuralPlumbing
Roof3p · 2 filings · 20 docs
Floor 11p · 1 filing · 20 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
NYC PARKS DEPT403/04/2026
NYC PARKS202/06/2026
LIRO ENGINEERS, INC.110/15/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NYC DEPT OF PARKS & RECREATION1203/21/2026
JMV ASSOCIATES203/21/2026
Building Lifecycle
All (31)Filed (6)Special Inspection (25)
03/04/2026
Filed — New Building
Q01324842-S4
03/02/2026
Filed — New Building
Q01324842-S2
02/26/2026
Special inspection requirement — Energy Code Compliance Inspections
02/26/2026
Special inspection requirement — HVAC-R and service water heating equipment
02/26/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
02/26/2026
Special inspection requirement — HVAC-R and service water heating system controls
02/26/2026
Special inspection requirement — Maintenance information
02/06/2026
Filed — Alteration
Q01352426-I1
01/28/2026
Special inspection requirement — Footing and Foundation
01/28/2026
Special inspection requirement — Concrete - Cast-In-Place
01/28/2026
Special inspection requirement — Subsurface Conditions – Fill Placement & In-Place Density
01/28/2026
Special inspection requirement — Masonry
01/28/2026
Special inspection requirement — Final
12/19/2025
Filed — New Building
Q01324842-S1
12/17/2025
Filed — New Building
Q01324842-I1
12/02/2025
Special inspection requirement — HVAC-R and service water piping design and insulation
12/02/2025
Special inspection requirement — Duct leakage testing, insulation and design
12/02/2025
Special inspection requirement — Maintenance information
12/02/2025
Special inspection requirement — Shutoff dampers
12/02/2025
Special inspection requirement — HVAC-R and service water heating equipment
12/02/2025
Special inspection requirement — Heating Systems
12/02/2025
Special inspection requirement — Energy Code Compliance Inspections
12/02/2025
Special inspection requirement — HVAC-R and service water heating system controls
11/26/2025
Special inspection requirement — Mechanical Systems
11/26/2025
Special inspection requirement — Final
10/15/2025
Filed — Alteration
Proposed work includes the construction of the Gwen Ifill Park. Work includes footing and foundation construction for the installation of new sports lighting poles, shade structure and new concrete retaining walls.
Q01296121-I1
10/01/2025
Special inspection requirement — Subgrade Inspections
10/01/2025
Special inspection requirement — Final
10/01/2025
Special inspection requirement — Subsurface Investigations (Borings/Test Pits)
Michael Mudalel
10/01/2025
Special inspection requirement — Concrete - Cast-In-Place
10/01/2025
Special inspection requirement — Footing and Foundation
Nothing on file for this building.
1 project · most recent 10/15/2025
FiledStatusContractorScope
10/15/2025——1 scope_items
▾Special Inspection Requirements (DOB NOW) — 25
DateRequirementInspectorRole
02/26/2026Energy Code Compliance Inspections—progress
02/26/2026HVAC-R and service water heating equipment—energy_progress
02/26/2026HVAC-R and service water piping design and insulation—energy_progress
02/26/2026HVAC-R and service water heating system controls—energy_progress
02/26/2026Maintenance information—energy_progress
01/28/2026Footing and Foundation—progress
01/28/2026Concrete - Cast-In-Place—special
01/28/2026Subsurface Conditions – Fill Placement & In-Place Density—special
01/28/2026Masonry—special
01/28/2026Final—progress
12/02/2025HVAC-R and service water piping design and insulation—energy_progress
12/02/2025Duct leakage testing, insulation and design—energy_progress
12/02/2025Maintenance information—energy_progress
12/02/2025Shutoff dampers—energy_progress
12/02/2025HVAC-R and service water heating equipment—energy_progress
12/02/2025Heating Systems—special
12/02/2025Energy Code Compliance Inspections—progress
12/02/2025HVAC-R and service water heating system controls—energy_progress
11/26/2025Mechanical Systems—special
11/26/2025Final—progress
10/01/2025Subgrade Inspections—special
10/01/2025Final—progress
10/01/2025Subsurface Investigations (Borings/Test Pits)Michael Mudalelspecial
10/01/2025Concrete - Cast-In-Place—special
10/01/2025Footing and Foundation—progress
▾Documents — 36 on file (BIS + DOB NOW)
▸Plans & Drawings7
▸DOB NOWPlans/Sketch7
08/18/2026Q01296121-I1Request digital key ↗
08/18/2026Q01324842-S1Request digital key ↗
08/18/2026Q01324842-I1Request digital key ↗
Showing 3 of 7 on file for this type
▸Zoning, Tax Lot & Property Records2
▸DOB NOWZD1: DOB Zoning Diagram1
08/13/2026Q01324842-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026Q01324842-I1Open ↗
▸Seals & Professional Certifications7
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/18/2026Q01296121-I1Open ↗
08/18/2026Q01324842-I1Open ↗
08/18/2026Q01324842-S2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature1
08/28/2026Q01296121-I1Open ↗
▸Inspections & Test Reports2
▸DOB NOWTR4 Test Report and Plot Diagram1
08/13/2026Q01296121-I1Open ↗
▸DOB NOWSOIL REPORT1
08/13/2026Q01296121-I1Open ↗
▸Approvals, Objections & Sign-offs14
▸DOB NOWDesign Commission Approval City Owned (Exterior Work)7
08/13/2026Q01352426-I1Open ↗
08/13/2026Q01324842-I1Open ↗
08/13/2026Q01324842-S1Open ↗
Showing 3 of 7 on file for this type
▸DOB NOWFee Exempt Supporting Document - DOF ACRIS report or BIB letter7
08/18/2026Q01324842-I1Open ↗
08/18/2026Q01324842-S1Open ↗
08/18/2026Q01324842-S3Open ↗
Showing 3 of 7 on file for this type
▸Other Documents4
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026Q01324842-S3Open ↗
08/13/2026Q01324842-I1Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026Q01324842-I1Open ↗
08/13/2026Q01324842-S3Open ↗