← Back
Three families
1760 56 STREET
BROOKLYN · BIN 3130844
💬 Discuss this project
1910Year Built
2Stories
C0Building Class
R5Zoning
2,320 sfGross Floor Area
3Units
Rent Stabilized13 Open Violations ▸FDNY Report ↗
Three families · 2,454 sf lot · 0.95 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralElectricalPlumbingFire ProtectionCivilGeneral
Roof48p · 1 filing · 20 docs
Floor 348p · 1 filing · 20 docs
Floor 249p · 1 filing · 20 docs
Floor 145p · 1 filing · 20 docs
Cellar51p · 1 filing · 20 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
176 E 108 STREET6007/08/2026
SOLID STATE BUILDERS INC103/22/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/23/2021$1.4M—— → —$582/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
LESTER KATZ, NCARB908/06/2025
JRS CONSULTING806/06/2025
R & O ENGINEERING101/09/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
AVALON DESIGNS3603/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
SOLIDSTATE BUILDERS INCGeneral Contractor2207/08/2026
TARGET PIPING NY LLCFire Protection207/08/2026
B&B MECH PLBG & HTG LLCPlumbing207/08/2026
FIRST QUALITY ELECL LLCElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP56161308/06/2025
Building Lifecycle
All (159)Filed (18)Permit Issued (14)Signed Off (4)Violation (16)Inspection (7)Objection (70)Special Inspection (30)
05/01/2026
Violation issued (HPD, open)
A
11/18/2025
Violation issued (HPD, open)
I
09/25/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORK
B00625029-S6
09/25/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORK
B00625029-S1
09/04/2025
Objection raised — Zoning
09/04/2025
Objection raised — Other
08/21/2025
Objection raised — Zoning
08/06/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORK
B00625029-A3
08/06/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
FAHAD FATEH
08/06/2025
Special inspection requirement — Insulation placement and R values
FAHAD FATEH
08/06/2025
Special inspection requirement — Fenestration areas
FAHAD FATEH
08/06/2025
Special inspection requirement — Fire-Resistance Rated Construction
FAHAD FATEH
08/06/2025
Special inspection requirement — Fenestration air leakage
FAHAD FATEH
08/06/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
08/06/2025
Special inspection requirement — Permanent certificate
FAHAD FATEH
08/06/2025
Special inspection requirement — Interior lighting power
FAHAD FATEH
08/06/2025
Special inspection requirement — Metering
FAHAD FATEH
08/06/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
08/06/2025
Special inspection requirement — Air barrier - visual inspection
FAHAD FATEH
08/06/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
08/06/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
FAHAD FATEH
08/06/2025
Special inspection requirement — Exterior Insulation and Finish Systems (EIFS)
FAHAD FATEH
07/28/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORK
B00625029-S2
07/28/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/02/2025
Inspection — Certified Storm Drainage-ST-Fixtures-Finish
Certified
View inspection ↗
07/02/2025
Inspection — Certified Water and Sanitary-WS-Fixtures-Finish
Certified
View inspection ↗
06/30/2025
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/17/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
06/17/2025
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
06/17/2025
Special inspection requirement — Post-installed Anchors
FAHAD FATEH
06/17/2025
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
06/17/2025
Special inspection requirement — Seismic Isolation Systems
FAHAD FATEH
06/17/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
06/17/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
06/17/2025
Special inspection requirement — Sprinkler Systems
FAHAD FATEH
06/16/2025
Objection resolved — Addressed
06/13/2025
Objection raised — Cost
06/06/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORK
B00625029-A2
06/06/2025
Violation issued (HPD, open)
A
06/04/2025
Special inspection requirement — Maintenance information
FAHAD FATEH
06/04/2025
Special inspection requirement — Seismic Isolation Systems
FAHAD FATEH
06/04/2025
Special inspection requirement — HVAC-R and service water heating equipment
FAHAD FATEH
06/04/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
FAHAD FATEH
06/04/2025
Special inspection requirement — Energy Code Compliance Inspections
FAHAD FATEH
06/04/2025
Special inspection requirement — Sprinkler Systems
FAHAD FATEH
06/04/2025
Special inspection requirement — Post-installed Anchors
FAHAD FATEH
06/04/2025
Special inspection requirement — HVAC-R and service water heating system controls
FAHAD FATEH
05/28/2025
Inspection — Fail-Final PL - Up to 3 Requested Floors
Fail
View inspection ↗
05/19/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORK
B00625029-A1
05/02/2025
Objection resolved — Addressed
05/02/2025
Objection resolved — Addressed
04/29/2025
Objection raised — Energy
04/07/2025
Objection resolved — Addressed
04/03/2025
Objection resolved — Addressed
03/24/2025
Objection resolved — Addressed
03/20/2025
Objection resolved — Addressed
03/18/2025
Objection raised — Zoning
03/18/2025
Objection raised — Energy
03/12/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
SUBSEQUENT FILING FOR PLUMBING AND SPRINKLER WORK
B00625029-P9
03/11/2025
Objection raised — Mechanical
Latest 60 of 159 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedSOLIDSTATE BUILDERS INC12/20/2024
DOB NOWStructuralSigned-offSOLIDSTATE BUILDERS INC12/20/2024
DOB NOWConstruction FenceSigned-offSOLIDSTATE BUILDERS INC12/16/2024
DOB NOWMechanical SystemsSigned-offSOLIDSTATE BUILDERS INC12/05/2024
DOB NOWPlumbingSigned-offTARGET PIPING NY LLC07/24/2024
DOB NOWPlumbingSigned-offTARGET PIPING NY LLC07/24/2024
DOB NOWConstruction FenceSigned-offSOLIDSTATE BUILDERS INC05/31/2024
DOB NOWGeneral ConstructionPermit IssuedSOLIDSTATE BUILDERS INC10/13/2023
DOB NOWStructuralSigned-offSOLIDSTATE BUILDERS INC10/13/2023
DOB NOWSprinklersSigned-offTARGET PIPING NY LLC07/26/2023
DOB NOWSprinklersSigned-offTARGET PIPING NY LLC07/26/2023
DOB NOWStructuralSigned-offSOLIDSTATE BUILDERS INC06/30/2023
DOB NOWGeneral ConstructionPermit IssuedSOLIDSTATE BUILDERS INC06/30/2023
DOB NOWConstruction FenceSigned-offSOLIDSTATE BUILDERS INC06/28/2023
1 project · most recent 08/06/2025
Air Conditioning Systems Heating Systems
FiledStatusContractorScopeMake / Model / Capacity
08/06/2025Signed-offSOLIDSTATE BUILDERS INCAir Conditioning Systems, Heating Systems
Cooling
Mitsubishi Electric Mitsubishi 60,000 BTU · Pump ×8
MXZ-5C42NA3-U1 42,000 BTU · Pump ×1
— MXZ-5C42NA3-U1 42,000 BTU · Pump ×1
Heating
Mitsubishi Electric n/a 41,500 BTU · Heat Pump Outdoor ×5
1 project · most recent 08/06/2025
Sprinkler System
FiledStatusContractorScope
08/06/2025Signed-offTARGET PIPING NY LLCSprinkler System
1 project · most recent 08/06/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
08/06/2025Signed-offB&B MECH PLBG & HTG LLCGas, Storm, Water/Sanitary
1 project · most recent 03/11/2025
General Wiring
FiledStatusContractorScope
03/11/2025CompleteFIRST QUALITY ELECL LLCGeneral Wiring
1 project · most recent 08/06/2025
Steel Concrete
FiledStatusContractorScope
08/06/2025Signed-offSOLIDSTATE BUILDERS INCSteel, Concrete
1 project · most recent 08/06/2025
Fence
FiledStatusContractorScope
08/06/2025Signed-offSOLIDSTATE BUILDERS INCFence
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
07/28/2025Pass-Final CND-Occupancy InspectionPassView ↗
07/02/2025Certified Storm Drainage-ST-Fixtures-FinishCertifiedView ↗
07/02/2025Certified Water and Sanitary-WS-Fixtures-FinishCertifiedView ↗
06/30/2025Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/28/2025Fail-Final PL - Up to 3 Requested FloorsFailView ↗
08/27/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
05/15/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
▾Special Inspection Requirements (DOB NOW) — 130
DateRequirementInspectorRole
08/06/2025Air barrier - visual inspectionFAHAD FATEHenergy_progress
08/06/2025Exterior Insulation and Finish Systems (EIFS)FAHAD FATEHspecial
08/06/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
08/06/2025Structural Stability – Alterations of existing buildingsFAHAD FATEHspecial
08/06/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
08/06/2025Fire-Resistance Rated ConstructionFAHAD FATEHprogress
08/06/2025Insulation placement and R valuesFAHAD FATEHenergy_progress
08/06/2025Interior lighting powerFAHAD FATEHenergy_progress
08/06/2025Fenestration and door U-factor and product ratingsFAHAD FATEHenergy_progress
08/06/2025Fenestration air leakageFAHAD FATEHenergy_progress
08/06/2025Maintenance informationFAHAD FATEHenergy_progress
08/06/2025Fenestration areasFAHAD FATEHenergy_progress
08/06/2025Permanent certificateFAHAD FATEHenergy_progress
08/06/2025MeteringFAHAD FATEHenergy_progress
06/17/2025Maintenance informationFAHAD FATEHenergy_progress
06/17/2025Seismic Isolation SystemsFAHAD FATEHspecial
06/17/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
06/17/2025Sprinkler SystemsFAHAD FATEHspecial
06/17/2025Post-installed AnchorsFAHAD FATEHspecial
06/17/2025Energy Code Compliance InspectionsFAHAD FATEHprogress
06/17/2025HVAC-R and service water heating equipmentFAHAD FATEHenergy_progress
06/17/2025HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
06/04/2025Post-installed AnchorsFAHAD FATEHspecial
06/04/2025Fire-Resistant Penetrations and JointsFAHAD FATEHspecial
06/04/2025HVAC-R and service water heating system controlsFAHAD FATEHenergy_progress
Latest 25 of 130.
▾Documents — 128 on file (BIS + DOB NOW)
▸Plans & Drawings18
▸DOB NOWPlans/Sketch18
08/21/2026B00625029-A1Request digital key ↗
08/21/2026B00625029-P7Request digital key ↗
08/21/2026B00625029-S7Request digital key ↗
Showing 3 of 18 on file for this type
▸Zoning, Tax Lot & Property Records11
▸DOB NOWZoning Exhibit form (1-5)5
08/13/2026B00625029-P5Open ↗
08/13/2026B00625029-P2Open ↗
08/13/2026B00625029-I1Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWZD1: DOB Zoning Diagram5
08/13/2026B00625029-I1Open ↗
08/13/2026B00625029-P5Open ↗
08/13/2026B00625029-P6Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00625029-I1Open ↗
▸Seals & Professional Certifications55
▸DOB NOWProgress Inspector Seal & Signature22
09/29/2026B00625029-P2Open ↗
09/29/2026B00625029-P2Open ↗
09/01/2026B00625029-P7Open ↗
Showing 3 of 22 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature18
08/21/2026B00625029-S4Open ↗
08/21/2026B00625029-A3Open ↗
08/21/2026B00625029-A2Open ↗
Showing 3 of 18 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature15
09/29/2026B00625029-P2Open ↗
09/29/2026B00625029-P2Open ↗
09/01/2026B00625029-P7Open ↗
Showing 3 of 15 on file for this type
▸Trade Schedules & Equipment6
▸DOB NOWDEP: Sewer Certification (Sanitary/Storm)6
08/13/2026B00625029-P6Open ↗
08/13/2026B00625029-P2Open ↗
08/13/2026B00625029-P5Open ↗
Showing 3 of 6 on file for this type
▸Environmental & Asbestos17
▸DOB NOWDEP ACP-5: Asbestos Assessment Report17
08/21/2026B00625029-A1Open ↗
08/21/2026B00625029-P7Open ↗
08/21/2026B00625029-P3Open ↗
Showing 3 of 17 on file for this type
▸Energy Compliance1
▸DOB NOWEN2: As Built Energy Analysis.1
08/13/2026B00625029-I1Open ↗
▸Other Documents20
▸DOB NOWSite Survey: Initial6
08/13/2026B00625029-I1Open ↗
08/13/2026B00625029-P5Open ↗
08/13/2026B00625029-S6Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone6
08/13/2026B00625029-P6Open ↗
08/13/2026B00625029-P5Open ↗
08/13/2026B00625029-P2Open ↗
Showing 3 of 6 on file for this type
▸DOB NOWProperty Ownership Certification5
08/21/2026B00625029-P2Open ↗
08/14/2026B00625029-P5Open ↗
08/14/2026B00625029-A3Open ↗
Showing 3 of 5 on file for this type
▸DOB NOWFinal Survey1
08/13/2026B00625029-I1Open ↗
▸DOB NOWProject Specific General Liability (PGL1)1
08/13/2026B00625029-I1Open ↗
▸DOB NOWSurvey1
08/13/2026B00625029-S4Open ↗