| Owner | Filings | Most Recent |
|---|---|---|
| A+ CHOICE CONSTRUCTION | 10 | 04/09/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| STUDIOSC ARCHITECTURE PLLC | 20 | 10/11/2024 |
| MJE PROFESSIONAL SERVICES | 3 | 12/01/2023 |
| Representative | Filings | Most Recent |
|---|---|---|
| BMB BUILDING CONSULTING | 40 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Y&L INTERIOR LLC | General Contractor | 17 | 07/08/2026 |
| A+ CHOICE CONSTRUCTION IN | General Contractor | 4 | 04/09/2026 |
| HIGHLAND PLUMBING LLC | Plumbing | 2 | 07/08/2026 |
| VILLAGE P & H NY INC | Fire Protection | 1 | 07/08/2026 |
| E&M BUILDERS GROUP CORP | General Contractor | 1 | 04/09/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| REGIONAL TESTING CORP. | 394 | 19 | 10/11/2024 |
| TRIANGLE INSPECTION & TES | 7495 | 2 | 08/10/2023 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | HIGHLAND PLUMBING LLC | 10/03/2024 |
| DOB NOW | Structural | Signed-off | Y&L INTERIOR LLC | 05/10/2024 |
| DOB NOW | General Construction | Permit Issued | Y&L INTERIOR LLC | 05/10/2024 |
| DOB NOW | Foundation | Signed-off | Y&L INTERIOR LLC | 05/09/2024 |
| DOB NOW | Construction Fence | Signed-off | Y&L INTERIOR LLC | 04/08/2024 |
| DOB NOW | General Construction | Permit Issued | Y&L INTERIOR LLC | 04/04/2024 |
| DOB NOW | Mechanical Systems | Signed-off | Y&L INTERIOR LLC | 04/04/2024 |
| DOB NOW | Sprinklers | Signed-off | VILLAGE P & H NY INC | 11/22/2023 |
| DOB NOW | Supported Scaffold | Signed-off | A+ CHOICE CONSTRUCTION IN | 11/08/2023 |
| DOB NOW | Sidewalk Shed | Signed-off | A+ CHOICE CONSTRUCTION IN | 11/08/2023 |
| DOB NOW | Plumbing | Signed-off | HIGHLAND PLUMBING LLC | 09/07/2023 |
| DOB NOW | Foundation | Signed-off | Y&L INTERIOR LLC | 05/15/2023 |
| DOB NOW | Structural | Signed-off | Y&L INTERIOR LLC | 05/15/2023 |
| DOB NOW | General Construction | Permit Issued | Y&L INTERIOR LLC | 04/18/2023 |
| DOB NOW | Foundation | Signed-off | Y&L INTERIOR LLC | 04/17/2023 |
| DOB NOW | Construction Fence | Signed-off | Y&L INTERIOR LLC | 03/20/2023 |
| DOB NOW | Mechanical Systems | Signed-off | Y&L INTERIOR LLC | 03/17/2023 |
| DOB NOW | Support of Excavation | Signed-off | Y&L INTERIOR LLC | 03/17/2023 |
| DOB NOW | Construction Fence | Signed-off | E&M BUILDERS GROUP CORP | 01/23/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 10/11/2024 | Permit Issued | Y&L INTERIOR LLC | Air Conditioning Systems, Heating Systems, Ventilation Systems | Cooling Mitsubishi Electric SUZ-KA36NAHZ / MXZ-SM36NAMHZ 36,000 BTU · Heat Pump Outdoor ×4 SUZ-KA36NAHZ 36,000 BTU · Heat Pump Outdoor ×3 SUZ-KA18NAHZ / RXB09AXVJU 24,000 BTU · Heat Pump Outdoor ×2 SUZ-KA30NAHZ 24,000 BTU · Heat Pump Outdoor ×2 MXZ-SM48NAMHZ 36,000 BTU · Heat Pump Outdoor ×1 Heating Mitsubishi Electric SUZ-KA36NAHZ / MXZ-SM36NAMHZ 38,000 BTU · Heat Pump Outdoor ×4 SUZ-KA36NAHZ 36,000 BTU · Heat Pump Outdoor ×3 SUZ-KA18NAHZ / RXB09AXVJU 25,000 BTU · Heat Pump Outdoor ×2 SUZ-KA30NAHZ 25,000 BTU · Heat Pump Outdoor ×2 MXZ-SM48NAMHZ 42,000 BTU · Heat Pump Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/23/2024 | Complete | KENNETH FISK ELECTRIC COR | General Wiring |
| 04/30/2024 | Complete | TUXEDO ELEC'L CONTR'G INC | — |
| 11/14/2023 | Complete | RICHARD NEU | — |
| 11/08/2023 | Complete | LENS ELECTRIC, INC | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/30/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 11/03/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/07/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/10/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 01/06/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 10/15/2024 | Certified Storm Drainage-ST-Fixtures-Finish | Certified | View ↗ |
| 10/09/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 09/06/2024 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 09/04/2024 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 06/13/2024 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 04/12/2024 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 04/12/2024 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/14/2023 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 09/14/2023 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 10/10/2024 | Air barrier - visual inspection | Paul Raymond | energy_progress |
| 10/10/2024 | Protection of exposed foundation insulation | Paul Raymond | energy_progress |
| 10/10/2024 | Air barrier — testing | Paul Raymond | energy_progress |
| 10/10/2024 | Metering | Paul Raymond | energy_progress |
| 10/10/2024 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |
| 10/10/2024 | Lighting in dwelling units | Paul Raymond | energy_progress |
| 10/10/2024 | Exterior lighting power | Paul Raymond | energy_progress |
| 10/10/2024 | Lighting controls | Paul Raymond | energy_progress |
| 10/10/2024 | Interior lighting power | Paul Raymond | energy_progress |
| 10/10/2024 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 10/10/2024 | Fire-Resistance Rated Construction | Paul Raymond | progress |
| 10/10/2024 | Fenestration and door U-factor and product ratings | Paul Raymond | energy_progress |
| 10/10/2024 | Fenestration air leakage | Paul Raymond | energy_progress |
| 10/10/2024 | Insulation placement and R values | Paul Raymond | energy_progress |
| 10/10/2024 | Maintenance information | Paul Raymond | energy_progress |
| 10/10/2024 | Fenestration areas | Paul Raymond | energy_progress |
| 10/10/2024 | Electrical motors and elevators | Paul Raymond | energy_progress |
| 10/20/2023 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 10/20/2023 | Underpinning | Paul Raymond | special |
| 10/20/2023 | Final | Paul Raymond | progress |
| 10/20/2023 | Footing and Foundation | Paul Raymond | progress |
| 10/20/2023 | Excavations - Sheeting, Shoring, and Bracing | Paul Raymond | special |
| 10/16/2023 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 10/16/2023 | Excavations - Sheeting, Shoring, and Bracing | Paul Raymond | special |
| 10/16/2023 | Underpinning | Paul Raymond | special |