← Back
Office with apartments (no commercial)
1791 FULTON STREET
BROOKLYN · Bedford-Stuyvesant (East) · BIN 3047934
💬 Discuss this project
1910Year Built
2Stories
O8Building Class
R7DZoning
—Gross Floor Area
2Units
31 Open Violations 30 unresolved · 1 paperwork only ▸FDNY Report ↗
Office with apartments (no commercial) · Owner of record: BRKLYN 1791 LLC · 1.41 FAR built · Flood zone X
Locations of Work
General
Floor 11p · 1 filing · 11 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
DIMO ENGINEERING507/08/2026
BRKLYN 1791 LLC303/22/2026
INDV403/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
ADL ENGINEERING LLC108/21/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
DIMO DESIGN103/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
RMAC CONSTRUCTION CORPGeneral Contractor207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M. INT'L ENGINEERING PLLC3129108/21/2023
Building Lifecycle
All (47)Filed (1)Permit Issued (2)Signed Off (1)Violation (33)Special Inspection (10)
11/03/2025
Violation issued (ECB, open)
Construction
07/17/2024
Signed off — Alteration
PREMISES RENDERED NON COMPLIANT DUE TO VEHICLE IMPACT. EMERGANCY WORK TO BE DONE AT THE BUILDING ENTRY AND THE DEMISING WALLS IN THE COMMERCIAL SPACE PROVIDE TEMPORARY SHORING AND REBUILD AND RESTORE WALLS AS PER PLANS FILED NO CHANGE IN USE EGRESS OR OCC
B00921948-I1
07/17/2024
Permit issued — General Construction
B00921948-I1-ST
12/14/2023
Violation issued (ECB, open)
Construction
08/23/2023
Permit issued — General Construction
B00921948-I1-GC
08/21/2023
Filed — Alteration
PREMISES RENDERED NON COMPLIANT DUE TO VEHICLE IMPACT. EMERGANCY WORK TO BE DONE AT THE BUILDING ENTRY AND THE DEMISING WALLS IN THE COMMERCIAL SPACE PROVIDE TEMPORARY SHORING AND REBUILD AND RESTORE WALLS AS PER PLANS FILED NO CHANGE IN USE EGRESS OR OCC
B00921948-I1
08/21/2023
Special inspection requirement — Fenestration areas
GEORGE GUTTMANN
08/21/2023
Special inspection requirement — Demolition
NANIK MASSAND
08/21/2023
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
08/21/2023
Special inspection requirement — Fenestration and door U-factor and product ratings
GEORGE GUTTMANN
08/21/2023
Special inspection requirement — Fenestration air leakage
GEORGE GUTTMANN
08/21/2023
Special inspection requirement — Energy Code Compliance Inspections
GEORGE GUTTMANN
08/21/2023
Special inspection requirement — Fire-Resistance Rated Construction
GEORGE GUTTMANN
08/21/2023
Special inspection requirement — Structural Wood Frame
GEORGE GUTTMANN
08/18/2023
Special inspection requirement — Final
GEORGE GUTTMANN
08/18/2023
Special inspection requirement — Structural Stability – Alterations of existing buildings
NANIK MASSAND
08/03/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
07/22/2023
Violation issued (DOB, open)
V-DOB VIOLATION - ACTIVE
07/22/2023
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
12/15/2007
Violation issued (HPD, open)
B
12/15/2007
Violation issued (HPD, open)
C
12/15/2007
Violation issued (HPD, open)
C
04/11/2007
Violation issued (HPD, open)
B
04/11/2007
Violation issued (HPD, open)
B
04/11/2007
Violation issued (HPD, open)
C
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
C
06/18/2004
Violation issued (HPD, open)
C
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
A
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
A
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
A
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
A
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
A
06/18/2004
Violation issued (HPD, open)
B
06/18/2004
Violation issued (HPD, open)
B
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionSigned-offRMAC CONSTRUCTION CORP07/17/2024
DOB NOWGeneral ConstructionSigned-offRMAC CONSTRUCTION CORP08/23/2023
BISPLISSUEDSMART PLBG & HTG CORP08/07/2018
BISMHISSUEDBENEL CONSTRUCTION LLC07/24/2017
BISEQISSUEDBENEL CONSTRUCTION LLC07/24/2017
BISOTISSUEDBENEL CONSTRUCTION LLC07/24/2017
BISPLISSUEDRICHMOND P & H CO., INC03/08/2013
BISOTISSUEDQUEENS CONSTRUCTION KITCH03/06/2013
BISBLISSUEDAVON PLBG & HTG INC06/13/2002
BISPLISSUEDAVON PLBG & HTG INC06/13/2002
Nothing on file for this building.
▾Special Inspection Requirements (DOB NOW) — 10
DateRequirementInspectorRole
08/21/2023Fenestration areasGEORGE GUTTMANNenergy_progress
08/21/2023DemolitionNANIK MASSANDspecial
08/21/2023Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
08/21/2023Fenestration and door U-factor and product ratingsGEORGE GUTTMANNenergy_progress
08/21/2023Fenestration air leakageGEORGE GUTTMANNenergy_progress
08/21/2023Energy Code Compliance InspectionsGEORGE GUTTMANNprogress
08/21/2023Fire-Resistance Rated ConstructionGEORGE GUTTMANNprogress
08/21/2023Structural Wood FrameGEORGE GUTTMANNprogress
08/18/2023FinalGEORGE GUTTMANNprogress
08/18/2023Structural Stability – Alterations of existing buildingsNANIK MASSANDspecial
▾Documents — 74 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/27/2026B00921948-I1Request digital key ↗
▸Applications & Permits13
▸BISPLAN / WORK APPROVAL APPLICATION6
04/29/2025321505563Open ↗
12/12/2018321505563Open ↗
05/10/2017321505563Open ↗
Showing 3 of 6 on file for this type
▸BISWORK PERMIT APPLICATION5
08/09/2018321505563Open ↗
07/25/2017321505563Open ↗
07/25/2017321505563Open ↗
Showing 3 of 5 on file for this type
▸BISPLAN - WORK & PERMITS - SUPPPORTING DOCUMENTATION2
01/16/2019321505563Open ↗
10/11/2018321505563Open ↗
▸Zoning, Tax Lot & Property Records2
▸BISZONING DIAGRAM1
05/19/2017321505563Open ↗
▸BISZONING EXHIBIT III:DESC. & OWNRSHP.STMNT1
05/10/2017321505563Open ↗
▸Seals & Professional Certifications13
▸DOB NOWProgress Inspector Seal & Signature7
08/22/2026B00921948-I1Open ↗
08/22/2026B00921948-I1Open ↗
08/22/2026B00921948-I1Open ↗
Showing 3 of 7 on file for this type
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION2
05/10/2017321505563Open ↗
03/31/2017321505563Open ↗
▸BISPROFESSIONAL CERTIFIED CHECKLIST1
02/01/2013320712733Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM1
02/01/2013320712733Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026B00921948-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/22/2026B00921948-I1Open ↗
▸Trade Schedules & Equipment4
▸BISHVAC & SERVICE WATER HEATING EQUIPMENT1
03/12/2025321505563Open ↗
▸BISHVAC & SERVICE WATER HEATING SYSTEM CONTROLS1
03/12/2025321505563Open ↗
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE1
03/31/2017321505563Open ↗
▸BISSCHEDULE B - PLUMBING1
02/01/2013320712733Open ↗
▸Safety & Tenant Protection2
▸BISEXCAVATION - SHEETING, SHORING, AND BRACING1
03/12/2025321505563Open ↗
▸BISSTREET TREE CHECKLIST1
03/31/2017321505563Open ↗
▸Environmental & Asbestos2
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
05/10/2017321505563Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B00921948-I1Open ↗
▸Energy Compliance14
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
05/10/2017321505563Open ↗
03/31/2017321505563Open ↗
02/01/2013320712733Open ↗
▸BISAIR SEALING AND INSULATION - VISUAL1
03/12/2025321505563Open ↗
▸BISINTERIOR LIGHTING POWER1
03/12/2025321505563Open ↗
▸BIS* DUCT LEAKAGE TESTING1
03/12/2025321505563Open ↗
▸BISFENESTRATION AREAS1
03/12/2025321505563Open ↗
▸BISTECHNICAL REPORT: ENERGY CODE - RESPONSIBILITY1
05/15/2025321505563Open ↗
▸BISINSULATION PLACEMENT & R VALUES1
03/12/2025321505563Open ↗
▸BISENERGY CODE COMPLIANCE INSPECTIONS1
03/12/2025321505563Open ↗
▸BISAS-BUILT ENERGY ANALYSIS (EN2)1
03/12/2025321505563Open ↗
▸BISLIGHTING CONTROLS1
03/12/2025321505563Open ↗
▸BIS* HVAC INSULATION AND SEALING1
03/12/2025321505563Open ↗
▸BISFENESTRATION AIR LEAKAGE1
03/12/2025321505563Open ↗
▸Inspections & Test Reports9
▸BISCONCRETE - CAST-IN-PLACE1
03/12/2025321505563Open ↗
▸BISSTRUCTURAL STABILITY - ALTERATIONS OF EXISTING BUILDINGS1
03/12/2025321505563Open ↗
▸BISFIRE-RESISTANT PENETRATIONS AND JOINTS (FIRESTOP)1
03/12/2025321505563Open ↗
▸BISFIRE-RESISTIVE RATED CONSTRUCTION1
03/12/2025321505563Open ↗
▸BISFOOTING AND FOUNDATION INSPECTION1
03/12/2025321505563Open ↗
▸BISMASONRY1
03/12/2025321505563Open ↗
▸BISTECHNICAL REPORT: RESPONSIBILITY1
03/14/2025321505563Open ↗
▸BISSUBGRADE INSP / SOILS-SITE PREP1
03/12/2025321505563Open ↗
▸BISMECHANICAL SYSTEMS1
03/12/2025321505563Open ↗
▸Approvals, Objections & Sign-offs3
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST1
05/16/2025321505563Open ↗
▸BISFINAL1
03/12/2025321505563Open ↗
▸BISADMINISTRATIVE OBJECTIONS1
02/01/2013320712733Open ↗
▸Cost, Insurance & Ownership4
▸BISCOST AFFIDAVIT2
05/10/2017321505563Open ↗
03/31/2017321505563Open ↗
▸BISCOST AFFIDAVIT (FINAL): PW31
03/12/2025321505563Open ↗
▸BISPROJECT-SPECIFIC GL INSURANCE1
07/25/2017321505563Open ↗
▸Filing & Intake Forms6
▸BISEFILING COVER SHEET3
05/10/2017321505563Open ↗
03/31/2017321505563Open ↗
01/30/2013320712733Open ↗
▸BISBOROUGH INTAKE FORM2
12/12/2018321505563Open ↗
12/10/2018321505563Open ↗
▸BISADDITIONAL INFORMATION1
07/17/2017321505563Open ↗
▸Other Documents1
▸BISUNDERPINNING (2014)1
03/12/2025321505563Open ↗