← Back
BuildNYC
Five to six families
18-11 LINDEN STREET
QUEENS · Ridgewood · BIN 4082152
💬 Discuss this project
1930Year Built
3Stories
C2Building Class
R6BZoning
5,250 sfGross Floor Area
6Units
Rent Stabilized3 Active Violations 2 unresolved · 1 paperwork only 4 likely answered ▸
Five to six families · Owner of record: 1811 Linden · 2,500 sf lot · 2.1 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbingGeneral
Names shown beside floors are taken automatically from the text of filed documents and may be incomplete or wrong.
Floor 3Unit 3L, Unit 3R8p · 2 filings · 8 docs
Floor 2
Floor 1
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
18-11 Linden3007/08/2026
1103 Carroll Partners503/21/2026
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
01/31/2018$2.8M—1811 LINDEN PARTNERS LLC → 1811 Linden$540/sf building
05/22/2015$1.6M—RIDGEWOOD ASSETS LLC → 1811 LINDEN PARTNERS LLC$301/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
Rise Architecture NJ202/23/2021
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
Jack Jaffa & Associates403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
AlbetoGeneral Contractor303/21/2026
Drilon Plumbing & HeatingPlumbing207/08/2026
Steel Tone ConstructionGeneral Contractor103/21/2026
So Plumbing & HeatingPlumbing103/21/2026
Dong TangGeneral Contractor103/21/2026
All Over ConstructionGeneral Contractor105/16/2018
Jalco Plumbing & HeatingPlumbing106/11/1999
Reliable WaterproofingGeneral Contractor105/27/1999
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
Biz Designs6312202/23/2021
Building Lifecycle
07/14/2026
Boiler inspection report filed
Initial · no defects · Accepted
06/24/2025
Boiler inspection report filed
Initial · no defects · Accepted
06/25/2024
Boiler inspection report filed
Initial · no defects · Accepted
07/10/2023
Boiler inspection report filed
Initial · no defects · Accepted
06/20/2023
Failure to file 2019 external low pressure inspection
DOB violation · open · Issued 2023; DOB's record still lists it as active
37 history events on file for this building. Sign in free to see the full history. Sign in · Create account
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingSigned-offDrilon Plumbing & Heating07/23/2021
DOB NOWPlumbingSigned-offDrilon Plumbing & Heating04/13/2021
DOB NOWGeneral ConstructionSigned-offAlbeto03/03/2021
BISPLISSUEDSo Plumbing & Heating08/27/2018
BISOTISSUEDAll Over Construction05/16/2018
BISPLISSUEDSo Plumbing & Heating01/11/2018
BISPLISSUEDSo Plumbing & Heating07/17/2017
BISOTISSUEDSteel Tone Construction07/17/2017
BISMHISSUEDSteel Tone Construction01/04/2017
BISPLISSUEDSo Plumbing & Heating12/27/2016
BISOTISSUEDSteel Tone Construction12/27/2016
BISOTISSUEDDong & Tang04/29/2016
BISPLISSUEDSo Plumbing & Heating04/29/2016
BISMHISSUEDDong & Tang04/26/2016
BISPLISSUEDJalco Plumbing & Heating06/11/1999
BISOTISSUEDReliable Waterproofing05/27/1999
1 project · most recent 02/23/2021
Gas Water/Sanitary
FiledStatusContractorScope
02/23/2021Signed-offDrilon Plumbing & HeatingGas, Water/Sanitary
2 projects · most recent 12/27/2021
General Wiring
FiledStatusContractorScope
12/27/2021CompleteMartin DorkinGeneral Wiring
04/30/2021Permit IssuedAmra ElectricalGeneral Wiring
▾Special Inspection Requirements (DOB NOW) — 1
DateRequirementInspectorRole
01/25/2021Fire-Resistant Penetrations and JointsJeff Akermanspecial
158 filed documents on file for this building. Sign in free to see the full history. Sign in · Create account