← Back
Three families
18 CHESTER COURT
BROOKLYN · Prospect Lefferts Gardens-Wingate · BIN 3114615
💬 Discuss this project
1912Year Built
3Stories
C0Building Class
R7-1Zoning
1,970 sfGross Floor Area
3Units
Three families · 1,666 sf lot · 1.18 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
03/09/2021$1.8M—— → —$916/sf building
12/17/2013$1.0M—Private party → Private party$510/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
GREEN RIVER ENVIRONMENTAL ENGINEERI103/05/2025
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
NY State Solar LLC203/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
NYSS LLCGeneral Contractor107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
GREEN RIVER ENVIRONMENTAL7841103/05/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
08/05/2025
Signed off — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS.
B01063564-I1
03/10/2025
Permit issued — Solar
B01063564-I1-SL
03/05/2025
Filed — Alteration
INSTALLATION OF PHOTOVOLTAIC SOLAR ARRAY ON EXISTING ROOF SYSTEM AS PER PLANS.
B01063564-I1
06/07/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
ROBERT MASONE
06/07/2024
Special inspection requirement — Structural Stability – Alterations of existing buildings
ROBERT MASONE
06/07/2024
Special inspection requirement — Energy Code Compliance Inspections
ROBERT MASONE
06/07/2024
Special inspection requirement — Final
ROBERT MASONE
06/07/2024
Special inspection requirement — Air barrier - visual inspection
ROBERT MASONE
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offNYSS LLC03/10/2025
1 project · most recent 07/25/2025
FiledStatusContractorScope
07/25/2025CompleteNY SOLAR ELECTRICAL LLC—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
06/07/2024Fire-Resistant Penetrations and JointsROBERT MASONEspecial
06/07/2024Structural Stability – Alterations of existing buildingsROBERT MASONEspecial
06/07/2024Energy Code Compliance InspectionsROBERT MASONEprogress
06/07/2024FinalROBERT MASONEprogress
06/07/2024Air barrier - visual inspectionROBERT MASONEenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/22/2026B01063564-I1Request digital key ↗
▸Applications & Permits1
▸DOB NOWLPC Approval/Permit1
08/13/2026B01063564-I1Open ↗
▸Seals & Professional Certifications4
▸DOB NOWProgress Inspector Seal & Signature2
08/27/2026B01063564-I1Open ↗
08/27/2026B01063564-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026B01063564-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature1
08/27/2026B01063564-I1Open ↗
▸Environmental & Asbestos1
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/13/2026B01063564-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01063564-I1Open ↗