| Owner | Filings | Most Recent |
|---|---|---|
| MAXIMUM CONTRACTING | 3 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| VALENZIANO ARCHITECTURE LLC | 3 | 02/27/2024 |
| C&P DESIGN CONSULTANTS | 1 | 06/29/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| MAXIMUM CONTRACTING INC | General Contractor | 3 | 04/09/2026 |
| BETHEL BUILDING CORP | General Contractor | 2 | 09/23/2026 |
| FLIP CITY ELECT & FIRE LL | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| C&P DESIGN CONSULTANT | 8472 | 2 | 02/27/2024 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Construction Fence | Permit Issued | BETHEL BUILDING CORP | 09/22/2026 |
| DOB NOW | Construction Fence | Permit Issued | BETHEL BUILDING CORP | 08/02/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | MAXIMUM CONTRACTING INC | 12/04/2023 |
| DOB NOW | Construction Fence | Permit Issued | MAXIMUM CONTRACTING INC | 09/15/2023 |
| DOB NOW | Construction Fence | Permit Issued | MAXIMUM CONTRACTING INC | 07/12/2023 |
| BIS | — | ISSUED | J. SMITH CONSTRUCTION INC. | 07/31/2023 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 02/27/2024 | Permit Issued | MAXIMUM CONTRACTING INC | Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/27/2024 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 12/18/2025 | Permit Issued | FLIP CITY ELECT & FIRE LL | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/27/2024 | Permit Issued | MAXIMUM CONTRACTING INC | Wood |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/29/2023 | Permit Issued | BETHEL BUILDING CORP | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/19/2024 | Ventilation and air distribution system | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | Concrete - Cast-In-Place | Stanislav Pilipenko | special |
| 04/19/2024 | Mechanical Systems | Stanislav Pilipenko | special |
| 04/19/2024 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | Stanislav Pilipenko | special |
| 04/19/2024 | Subgrade Inspections | Stanislav Pilipenko | special |
| 04/19/2024 | Flood Zone Compliance (attach FEMA elevation/dry floodproofing certificate where applicable) | Stanislav Pilipenko | special |
| 04/19/2024 | Wood – Prefabricated I-Joists | Stanislav Pilipenko | special |
| 04/19/2024 | Subsurface Investigations (Borings/Test Pits) | WILLIAM MONTAGUE | special |
| 04/19/2024 | Fire-Resistant Penetrations and Joints | Stanislav Pilipenko | special |
| 04/19/2024 | Lowest Floor Elevation | Stanislav Pilipenko | progress |
| 04/19/2024 | Energy Code Compliance Inspections | Stanislav Pilipenko | progress |
| 04/19/2024 | Footing and Foundation | Stanislav Pilipenko | progress |
| 04/19/2024 | Structural Wood Frame | Stanislav Pilipenko | progress |
| 04/19/2024 | Fire-Resistance Rated Construction | Stanislav Pilipenko | progress |
| 04/19/2024 | Final | Stanislav Pilipenko | progress |
| 04/19/2024 | HVAC-R and service water heating system controls | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | Maintenance information | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | Fenestration areas | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | Fenestration air leakage | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | HVAC-R and service water heating equipment | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | Air barrier - visual inspection | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | Insulation placement and R values | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | Electric vehicle service equipment requirements | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | Permanent certificate | Stanislav Pilipenko | energy_progress |
| 04/19/2024 | Air barrier — testing | Stanislav Pilipenko | energy_progress |