| Firm | Filings | Most Recent |
|---|---|---|
| DANIEL SAMTON AIA | 3 | 06/12/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| KNA CONSULTING | 6 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| CANAL CONSTRUCTION CORP | General Contractor | 3 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| BFS ARCHITECT PC | 7477 | 3 | 06/12/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | CANAL CONSTRUCTION | 10/11/2024 |
| DOB NOW | General Construction | Permit Issued | CANAL CONSTRUCTION | 10/07/2024 |
| BIS | OT | ISSUED | YUNG WAY CONSTRUCTION INC. | 05/22/2014 |
| BIS | PL | ISSUED | DYCKMAN PLBG AND HTG INC | 08/23/2011 |
| BIS | — | ISSUED | ABDUL CONSTRUCTION INC | 08/11/2011 |
| BIS | EQ | ISSUED | ABDUL CONSTRUCTION INC | 08/11/2011 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/09/2025 | Complete | CITY GRID ELECTRIC CORP | General Wiring |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/16/2025 | Mechanical Systems | Belal Salim | special |
| 04/16/2025 | Final | Daniel Samton | progress |
| 04/16/2025 | HVAC-R and service water piping design and insulation | Daniel Samton | energy_progress |
| 04/16/2025 | Ventilation and air distribution system | Daniel Samton | energy_progress |
| 04/16/2025 | Maintenance information | Daniel Samton | energy_progress |
| 04/16/2025 | HVAC-R and service water heating system controls | Daniel Samton | energy_progress |
| 04/16/2025 | HVAC-R and service water heating equipment | Daniel Samton | energy_progress |