| Owner | Filings | Most Recent |
|---|---|---|
| SAPOL CONSTRUCTION | 38 | 07/08/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BRICOLAGE DESIGNS | 10 | 08/29/2025 |
| YAKER ENGINEERING, P.C. | 1 | 07/15/2024 |
| Representative | Filings | Most Recent |
|---|---|---|
| D S CREATIVE INOVATIONS | 10 | 03/21/2026 |
| BRICOLAGE DESIGNS | 5 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| SAPOL CONSTRUCTION LLC | General Contractor | 9 | 07/08/2026 |
| M&D FIRE SPRINKLER INC | Fire Protection | 2 | 07/08/2026 |
| BROOKLYN MECH WORKS CORP | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| ENGINEERING PROFESSIONAL | 6393 | 8 | 08/29/2025 |
| STEEL CORE ENGINEERING PL | 1098 | 2 | 03/14/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sprinklers | Signed-off | M&D FIRE SPRINKLER INC | 08/11/2025 |
| DOB NOW | Mechanical Systems | Signed-off | LEON D. DEMATTEIS CONSTR | 08/01/2025 |
| DOB NOW | Curb Cut | Signed-off | LEON D. DEMATTEIS CONSTR | 07/30/2025 |
| DOB NOW | General Construction | Permit Issued | LEON D. DEMATTEIS CONSTR | 05/06/2025 |
| DOB NOW | Sprinklers | Signed-off | M&D FIRE SPRINKLER INC | 02/11/2025 |
| DOB NOW | Plumbing | Signed-off | BROOKLYN MECH WORKS CORP | 01/22/2025 |
| DOB NOW | Support of Excavation | Signed-off | LEON D. DEMATTEIS CONSTR | 10/15/2024 |
| DOB NOW | Foundation | Permit Issued | LEON D. DEMATTEIS CONSTR | 10/02/2024 |
| DOB NOW | Construction Fence | Signed-off | LEON D. DEMATTEIS CONSTR | 09/30/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/29/2025 | Signed-off | SAPOL CONSTRUCTION LLC | Heating and Air Conditioning Systems | Heat / Cool Daikin RXTQ36TBVJUB; RXTQ36TBVJUB; RXTQ60TBVJUB 22,000 BTU · Vrf Outdoor ×3 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/29/2025 | Signed-off | BROOKLYN MECH WORKS CORP | Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/08/2025 | Complete | SHELBY ELECTRICAL CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/29/2025 | Signed-off | M&D FIRE SPRINKLER INC | Steel, Masonry, Wood |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/08/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 02/18/2026 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/26/2025 | Pass-Final CND-Occupancy Inspection | Pass | View ↗ |
| 08/14/2025 | Pass-Final Curb Cut Non-Directive 14 | Pass | View ↗ |
| 08/12/2025 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 08/07/2025 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 04/04/2025 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 04/04/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 02/26/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/08/2025 | Wood – Seismic Resistance | OLEG RUDITSER | special |
| 09/08/2025 | Fenestration and door U-factor and product ratings | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Permanent certificate | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Interior lighting power | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Air barrier — testing | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Maintenance information | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Fenestration air leakage | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Air barrier - visual inspection | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Metering | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Fenestration areas | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Insulation placement and R values | OLEG RUDITSER | energy_progress |
| 09/08/2025 | Footing and Foundation | OLEG RUDITSER | progress |
| 09/08/2025 | Fire-Resistance Rated Construction | OLEG RUDITSER | progress |
| 09/08/2025 | Final | OLEG RUDITSER | progress |
| 09/08/2025 | Energy Code Compliance Inspections | OLEG RUDITSER | progress |
| 09/08/2025 | Subgrade Inspections | OLEG RUDITSER | special |
| 09/08/2025 | Structural Cold-Formed Steel | OLEG RUDITSER | special |
| 09/08/2025 | Fire-Resistant Penetrations and Joints | OLEG RUDITSER | special |
| 09/08/2025 | Concrete - Cast-In-Place | OLEG RUDITSER | special |
| 09/08/2025 | Structural Steel - Details | OLEG RUDITSER | special |
| 09/08/2025 | Masonry | OLEG RUDITSER | special |
| 08/29/2025 | Fenestration air leakage | OLEG RUDITSER | energy_progress |
| 08/29/2025 | Air barrier - visual inspection | OLEG RUDITSER | energy_progress |
| 08/29/2025 | Interior lighting power | OLEG RUDITSER | energy_progress |
| 08/29/2025 | Fenestration and door U-factor and product ratings | OLEG RUDITSER | energy_progress |