| Owner | Filings | Most Recent |
|---|---|---|
| 181 ARLINGTON AVE | 3 | 03/22/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 05/26/2021 | $1.2M | — | — → — | $572/sf building |
| 01/25/2018 | $420K | — | Private party → 181 ARLINGTON AVE CORP. | $195/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LI ARCHITECT ASSOCIATE, PLLC | 5 | 02/15/2023 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JUST PLBG & HTG INC | Plumbing | 7 | 07/08/2026 |
| TARIFA CONSTRUCTION INC | General Contractor | 3 | 03/22/2026 |
| RM ELECTRIC CO., INC. | Electrical | 1 | 03/22/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| LI ARCHITECT ASSOCIATE, P | 1104 | 3 | 11/15/2022 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Signed-off | MOHAMED ABDELRAZEK | 02/07/2023 |
| DOB NOW | Plumbing | Signed-off | MOHAMED ABDELRAZEK | 07/18/2022 |
| DOB NOW | General Construction | Signed-off | TARIFA CONSTRUCTION INC | 07/07/2022 |
| BIS | OT | ISSUED | AXONAL DESIGN INC | 12/05/2018 |
| BIS | OT | ISSUED | AXONAL DESIGN INC | 09/14/2018 |
| BIS | PL | ISSUED | PLUMBING PLBG & PLBG CORP | 09/14/2018 |
| BIS | OT | ISSUED | JCT DEVELOPMENT NY INC | 10/11/2016 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 03/22/2024 | Permit Issued | GREEN POWER ELECTRIC CORP | 3 meters, 1 new_meters |
| 07/28/2022 | Complete | Y.S ELECTRIC | General Wiring |
| 04/04/2019 | Permit Issued | RM ELECTRIC CO., INC. | 2 meters, 2 new_meters |
| Date | Type | Result | Report |
|---|---|---|---|
| 02/07/2023 | Fail-Final PL - Up to 3 Requested Floors | Fail | View ↗ |
| 01/11/2023 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 12/28/2022 | Fail-Final General Construction Non-Directive 14 | Fail | View ↗ |
| 09/01/2022 | Certified Gas-Gas-Piping-Roughing | Certified | View ↗ |
| 09/01/2022 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 09/01/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 09/01/2022 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 03/21/2023 | Fire-Resistant Penetrations and Joints | Ling Li | special |
| 03/06/2023 | Fire-Resistant Penetrations and Joints | — | special |
| 12/22/2022 | Fire-Resistance Rated Construction | Ling Li | progress |
| 12/22/2022 | Energy Code Compliance Inspections | Ling Li | progress |
| 12/22/2022 | Interior lighting power | Ling Li | energy_progress |
| 12/22/2022 | Fenestration and door U-factor and product ratings | Ling Li | energy_progress |
| 12/22/2022 | Fenestration air leakage | Ling Li | energy_progress |
| 12/22/2022 | Fenestration areas | Ling Li | energy_progress |
| 12/22/2022 | Maintenance information | Ling Li | energy_progress |
| 12/22/2022 | Insulation placement and R values | Ling Li | energy_progress |
| 12/22/2022 | Fire-Resistant Penetrations and Joints | Ling Li | special |
| 11/15/2022 | Energy Code Compliance Inspections | Ling Li | progress |
| 11/15/2022 | Fire-Resistance Rated Construction | Ling Li | progress |
| 11/15/2022 | Insulation placement and R values | Ling Li | energy_progress |
| 11/15/2022 | Fenestration areas | Ling Li | energy_progress |
| 11/15/2022 | Fenestration and door U-factor and product ratings | Ling Li | energy_progress |
| 11/15/2022 | Maintenance information | Ling Li | energy_progress |
| 11/15/2022 | Interior lighting power | Ling Li | energy_progress |
| 11/15/2022 | Fenestration air leakage | Ling Li | energy_progress |
| 11/15/2022 | Fire-Resistant Penetrations and Joints | Ling Li | special |