| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 07/03/2025 | Permit Issued | SIERRA MECHANICAL CONTRAC | Others | Other York ×17 |
| 10/22/2024 | Signed-off | HIBUILD LIMITED LIABILITY | Others | Other Aic JAD-XK-6.50.08.72 Heat Exchanger ×2 |
| 10/24/2023 | Permit Issued | HIBUILD LIMITED LIABILITY | Heating and Air Conditioning Systems | Heat / Cool Daikin RXYQ192TATJA 16 tons · Vrf Outdoor ×1 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 01/06/2026 | — | — | 39 heads |
| 12/24/2024 | — | — | — |
| 06/28/2021 | — | — | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/14/2026 | — | — | Water/Sanitary |
| 01/06/2026 | — | — | — |
| 09/03/2024 | Permit Issued | LOUIS L.BUTTERMARK & SONS | Water/Sanitary |
| 08/19/2024 | Signed-off | L.L.G. PLBG & HTG INC | Gas, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/16/2025 | Permit Issued | ZENA ELECTRIC INC | General Wiring |
| 08/08/2024 | Permit Issued | H.J. MARTIN ASSOC. INC. | HVAC Wiring |
| 05/17/2024 | Permit Issued | H.J. MARTIN ASSOC. INC. | HVAC Wiring |
| 03/05/2024 | Complete | CORE ELECTRIC MEP INDS LL | General Wiring, Lighting |
| 10/25/2023 | Permit Issued | REDD ELECTRICAL SVCS INC | General Wiring |
| 05/19/2023 | Complete | H. & L. ELECTRIC INC | General Wiring |
| 02/08/2023 | Permit Issued | AMIN ELECTRICAL CORP | — |
| 10/07/2021 | Permit Issued | J.H. ELEC. OF NEW YORK IN | General Wiring |
| 10/22/2020 | Permit Issued | J.H. ELEC. OF NEW YORK IN | General Wiring |
| 02/11/2020 | Permit Issued | R.C.M. ELECTRIC CORP. | — |
| 10/09/2018 | Permit Issued | AAA'S ELECTL CONTG CORP | General Wiring |
| 10/09/2018 | Permit Issued | AAA'S ELECTL CONTG CORP | General Wiring |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/20/2026 | Permit Issued | AKS INTERNATIONAL INC | Steel |
| 03/04/2026 | — | — | Steel |
| 01/22/2026 | — | — | Concrete |
| 07/09/2025 | — | — | Steel |
| 07/01/2021 | Permit Issued | THE MORGANTI GROUP, INC | 1 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 05/05/2025 | Permit Issued | JAYLEX NYC CORP | Fence, Scaffold, Sidewalk Shed |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/01/2024 | Permit Issued | — | — |
| Owner | Filings | Most Recent |
|---|---|---|
| DASNY | 146 | 09/13/2026 |
| CUNY | 14 | 07/08/2026 |
| DORMITORY AUTHORITY OF NE | 1 | 03/22/2026 |
| CUNY 042 | 1 | 03/22/2026 |
| DEPT RE-CITY OF NEW YORK | 1 | 03/22/2026 |
| WHITESTONE CONSTRUCTION C | 19 | 03/22/2026 |
| CAULDWELL WINGATE | 1 | 03/22/2026 |
| CCNY | 2 | 03/21/2026 |
| VOLMAR CONSTRUCTION | 1 | 03/21/2026 |
| CUNY DEPT OF DESIGN CONST MGMT | 11 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| ROBERT SILMAN ASSOCIATES | 3 | 05/20/2026 |
| DAGHER ENGINEERING PLLC | 4 | 05/14/2026 |
| AHUJA PARTNERSHIP ARCHITECTS | 8 | 04/22/2026 |
| MG ENGINEERING D.P.C. | 5 | 04/22/2026 |
| CONSULTING ENGINEERS COLLABORATIVE, | 2 | 03/04/2026 |
| CAPLES JEFFERSON ARCHITECTS, PC | 3 | 02/18/2026 |
| WILLDAN ENERGY SOLUTIONS | 5 | 07/03/2025 |
| CONAPAC SERVICES, DBA | 5 | 05/05/2025 |
| DAVID KRIEGEL | 1 | 01/07/2025 |
| STEPHEN ELY | 2 | 12/24/2024 |
| KALLEN AND LEMELSON | 4 | 09/03/2024 |
| GRAF & LEWENT ARCHITECTS, LLP | 3 | 08/19/2024 |
| A G CONSULTING ENGINEERING, PC | 6 | 08/13/2024 |
| SBLM ARCHITECTS, PC | 4 | 07/31/2024 |
| SILMAN | 4 | 07/08/2024 |
| GENESYS ENGINEERING | 2 | 10/24/2023 |
| LANGAN ENGINEERING | 2 | 07/01/2021 |
| Representative | Filings | Most Recent |
|---|---|---|
| SKYLINE ACCESS | 1 | 03/21/2026 |
| MUNICIPAL BUILDING CONSULTANTS | 33 | 03/21/2026 |
| CONSTRUCTION PERMIT SERVICES | 22 | 03/21/2026 |
| MUNICIPAL EXPEDITING | 8 | 03/21/2026 |
| CASO ASSOCIATES | 4 | 03/21/2026 |
| JMV ASSOCIATES | 8 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| JAYLEX NYC CORP | General Contractor | 32 | 07/08/2026 |
| THE MORGANTI GROUP, INC | General Contractor | 27 | 07/08/2026 |
| AKS INTERNATIONAL INC | General Contractor | 10 | 07/08/2026 |
| HIBUILD LIMITED LIABILITY | General Contractor | 6 | 07/08/2026 |
| LOUIS L.BUTTERMARK & SONS | Plumbing | 4 | 07/08/2026 |
| CAULDWELL WINGATE CO LLC | General Contractor | 3 | 07/08/2026 |
| L.L.G. PLBG & HTG INC | Plumbing | 3 | 07/08/2026 |
| WILLIAM NIEVES | Electrical | 1 | 03/21/2026 |
| RISHI BUNSEE | Electrical | 1 | 03/21/2026 |
| AMH MECHANICAL INC | General Contractor | 1 | 07/08/2026 |
| BLACKSHEAR, VINCENT | Electrical | 1 | 03/21/2026 |
| NIEVES WILLIAM | Electrical | 1 | 03/21/2026 |
| LIOTINE, VITO | Electrical | 1 | 03/21/2026 |
| P B CONTRACTING CORP | General Contractor | 1 | 07/03/2026 |
| SIERRA MECHANICAL CONTRACTING | General Contractor | 1 | 08/25/2026 |
| CORE ELECTRIC MEP INDS LL | Electrical | 1 | 03/22/2026 |
| VOLMAR CONSTRUCTION INC | General Contractor | 1 | 07/08/2026 |
| EASTERN PLBG & MECH CONTR | Plumbing | 1 | 07/08/2026 |
| BUNAY, CLEVER | Electrical | 1 | 03/21/2026 |
| RUSS FLAUM | Electrical | 1 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| FUTURE TECH CONSULTANTS O | 589 | 22 | 05/20/2026 |
| SOCOTEC ENGINEERING | 4983 | 6 | 10/09/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Permit Issued | SIERRA MECHANICAL CONTRACTING | 08/24/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | AMH MECHANICAL INC | 06/03/2026 |
| DOB NOW | General Construction | Permit Issued | P B CONTRACTING CORP | 06/01/2026 |
| DOB NOW | Plumbing | Signed-off | L.L.G. PLBG & HTG INC | 05/04/2026 |
| DOB NOW | General Construction | Permit Issued | THE MORGANTI GROUP, INC | 03/30/2026 |
| DOB NOW | Construction Fence | Permit Issued | JAYLEX NYC | 02/17/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | JAYLEX NYC | 02/13/2026 |
| DOB NOW | General Construction | Permit Issued | THE MORGANTI GROUP, INC | 01/29/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | JAYLEX NYC | 01/23/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | JAYLEX NYC | 01/23/2026 |
| DOB NOW | Support of Excavation | Permit Issued | THE MORGANTI GROUP, INC | 01/05/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | THE MORGANTI GROUP, INC | 01/05/2026 |
| DOB NOW | General Construction | Permit Issued | THE MORGANTI GROUP, INC | 01/05/2026 |
| DOB NOW | Foundation | Permit Issued | THE MORGANTI GROUP, INC | 01/05/2026 |
| DOB NOW | Structural | Permit Issued | THE MORGANTI GROUP, INC | 01/05/2026 |
| DOB NOW | Plumbing | Permit Issued | LOUIS L.BUTTERMARK & SONS | 12/30/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | AKS INTERNATIONAL INC | 09/17/2025 |
| DOB NOW | General Construction | Permit Issued | VOLMAR CONSTRUCTION INC | 06/16/2025 |
| DOB NOW | Structural | Permit Issued | AKS INTERNATIONAL INC | 03/25/2025 |
| DOB NOW | Plumbing | Signed-off | L.L.G. PLBG & HTG INC | 02/28/2025 |
| DOB NOW | Construction Fence | Permit Issued | JAYLEX NYC | 02/26/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | JAYLEX NYC | 02/25/2025 |
| DOB NOW | Supported Scaffold | Permit Issued | JAYLEX NYC | 01/23/2025 |
| DOB NOW | Mechanical Systems | Permit Issued | THE MORGANTI GROUP, INC | 12/31/2024 |
| DOB NOW | General Construction | Permit Issued | THE MORGANTI GROUP, INC | 12/31/2024 |
| DOB NOW | Foundation | Permit Issued | THE MORGANTI GROUP, INC | 12/31/2024 |
| DOB NOW | Support of Excavation | Permit Issued | THE MORGANTI GROUP, INC | 12/31/2024 |
| DOB NOW | Structural | Permit Issued | THE MORGANTI GROUP, INC | 12/31/2024 |
| DOB NOW | General Construction | Permit Issued | THE MORGANTI GROUP, INC | 12/31/2024 |
| DOB NOW | Plumbing | Permit Issued | LOUIS L.BUTTERMARK & SONS | 12/18/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | HIBUILD LIMITED LIABILITY | 09/10/2024 |
| DOB NOW | Suspended Scaffold | Permit Issued | SKYLINE RESTORATION INC | 09/05/2024 |
| DOB NOW | General Construction | Permit Issued | HIBUILD LIMITED LIABILITY | 08/30/2024 |
| DOB NOW | Structural | Permit Issued | AKS INTERNATIONAL INC | 07/18/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | AKS INTERNATIONAL INC | 07/18/2024 |
| DOB NOW | Mechanical Systems | Signed-off | HIBUILD LIMITED LIABILITY | 05/08/2024 |
| DOB NOW | Structural | Permit Issued | AKS INTERNATIONAL INC | 03/18/2024 |
| DOB NOW | Mechanical Systems | Permit Issued | AKS INTERNATIONAL INC | 03/18/2024 |
| DOB NOW | Plumbing | Signed-off | L.L.G. PLBG & HTG INC | 03/14/2024 |
| DOB NOW | Mechanical Systems | Signed-off | CAULDWELL WINGATE CO LLC | 03/07/2024 |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/26/2026 | Final | Elias Dagher | progress |
| 06/26/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/26/2026 | Mechanical Systems | MARISA HARTE | special |
| 06/18/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 06/12/2026 | Structural Steel - High Strength Bolting | MARISA HARTE | special |
| 06/12/2026 | Final | Joseph Tortorella | progress |
| 06/12/2026 | Structural Steel - Details | MARISA HARTE | special |
| 06/12/2026 | Structural Steel - Welding | MARISA HARTE | special |
| 05/13/2026 | Energy Code Compliance Inspections | MARISA HARTE | progress |
| 05/13/2026 | Final | MARISA HARTE | progress |
| 05/13/2026 | HVAC-R and service water heating system controls | MARISA HARTE | energy_progress |
| 05/13/2026 | Duct leakage testing, insulation and design | MARISA HARTE | energy_progress |
| 05/13/2026 | HVAC-R and service water piping design and insulation | MARISA HARTE | energy_progress |
| 05/13/2026 | Fire-Resistant Penetrations and Joints | MARISA HARTE | special |
| 05/13/2026 | Mechanical Systems | MARISA HARTE | special |
| 05/13/2026 | Post-installed Anchors | MARISA HARTE | special |
| 05/12/2026 | Final | Elias Dagher | progress |
| 05/12/2026 | Mechanical Systems | MARISA HARTE | special |
| 03/17/2026 | Final | Joseph Tortorella | progress |
| 03/17/2026 | Structural Steel - Welding | MARISA HARTE | special |
| 03/17/2026 | Structural Steel - High Strength Bolting | MARISA HARTE | special |
| 03/17/2026 | Structural Steel - Details | MARISA HARTE | special |
| 01/21/2026 | Mechanical Systems | — | special |
| 01/21/2026 | Maintenance information | — | energy_progress |
| 01/21/2026 | Final | — | progress |