| Firm | Filings | Most Recent |
|---|---|---|
| NY BUILDING ASSOCIATES INC | 1 | 04/22/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| S R SOLAR DESIGN | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| J SYNERGY GREEN INC | General Contractor | 2 | 03/21/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| NKM ENGINEERING PLLC | 6244 | 1 | 04/22/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Solar | Permit Issued | J SYNERGY GREEN | 06/24/2025 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/25/2025 | Complete | GREEN LIGHT ELECL & MECH | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/22/2025 | Permit Issued | J SYNERGY GREEN INC | 12 panels, 5.16 kw, 892.39 roof_area_sqft |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 04/14/2025 | Fire-Resistant Penetrations and Joints | NARESH MAHANGU | special |
| 04/14/2025 | Structural Stability – Alterations of existing buildings | NARESH MAHANGU | special |
| 04/14/2025 | Energy Code Compliance Inspections | NARESH MAHANGU | progress |
| 04/14/2025 | Final | NARESH MAHANGU | progress |
| 04/14/2025 | Air barrier - visual inspection | NARESH MAHANGU | energy_progress |