1910Year Built
2Stories
C0Building Class
R6BZoning
2,673 sfGross Floor Area
3Units
Three families · 1,520 sf lot · 1.76 FAR built · Flood zone X
Locations of Work
ArchitecturePlumbing
Permit Issued — active, not yet Signed-off
Floor 2Under Construction3p · 1 filing · 15 docs
Floor 1
CellarUnder Construction2p · 1 filing · 15 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
PWR ENGINEERING DESIGN DPC305/19/2026
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
KMP DESIGN ENGINEERING403/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
VAIR CONTRACTING INCGeneral Contractor104/09/2026
PRIME PIPING & HEATING INPlumbing108/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
HRF SERVICES CORP5616305/19/2026
Building Lifecycle
All (28)Filed (3)Permit Issued (2)Objection (8)Special Inspection (15)
08/07/2026
Permit issued — Plumbing
B01174739-S1-PL
06/09/2026
Objection resolved — Addressed
06/05/2026
Objection raised — Cost
05/19/2026
Filed — Alteration
PLUMBING WORK TYPE ONLY AS A SUBSEQUENCE FILING OF GC#B01174739 TO CREATE NEW BOILER ROOM AT CELLAR AND RENOVATE EXISTING BATHROOM AT 2ND FLOOR OF AN EXISTING BUILDING.
B01174739-P1
05/19/2026
Special inspection requirement — HVAC-R and service water piping design and insulation
05/19/2026
Special inspection requirement — HVAC-R and service water heating system controls
05/19/2026
Special inspection requirement — Maintenance information
05/19/2026
Special inspection requirement — HVAC-R and service water heating equipment
02/17/2026
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
10/27/2025
Permit issued — General Construction
B01174739-I1-GC
10/09/2025
Filed — Alteration
PLUMBING WORK TYPE ONLY AS A SUBSEQUENCE FILING OF GC#B01174739 TO CREATE NEW BOILER ROOM AT CELLAR AND RENOVATE EXISTING BATHROOM AT 2ND FLOOR OF AN EXISTING BUILDING.
B01174739-S1
06/03/2025
Objection resolved — Addressed
05/30/2025
Objection resolved — Addressed
05/20/2025
Objection raised — Admin
05/09/2025
Objection resolved — Addressed
03/14/2025
Objection raised — Other
03/13/2025
Objection raised — Scope
03/07/2025
Filed — Alteration
PLUMBING WORK TYPE ONLY AS A SUBSEQUENCE FILING OF GC#B01174739 TO CREATE NEW BOILER ROOM AT CELLAR AND RENOVATE EXISTING BATHROOM AT 2ND FLOOR OF AN EXISTING BUILDING.
B01174739-I1
03/07/2025
Special inspection requirement — Insulation placement and R values
SHAHRIAR QUAYYUM
03/07/2025
Special inspection requirement — Interior lighting power
SHAHRIAR QUAYYUM
03/07/2025
Special inspection requirement — Maintenance information
SHAHRIAR QUAYYUM
03/07/2025
Special inspection requirement — Permanent certificate
SHAHRIAR QUAYYUM
03/07/2025
Special inspection requirement — Fenestration areas
SHAHRIAR QUAYYUM
01/31/2025
Special inspection requirement — Fenestration air leakage
SHAHRIAR QUAYYUM
01/31/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
SHAHRIAR QUAYYUM
01/31/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
SHAHRIAR QUAYYUM
01/31/2025
Special inspection requirement — Fire-Resistance Rated Construction
SHAHRIAR QUAYYUM
01/31/2025
Special inspection requirement — Air barrier - visual inspection
SHAHRIAR QUAYYUM
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWPlumbingPermit IssuedPRIME PIPING & HEATING IN08/07/2026
DOB NOWGeneral ConstructionPermit IssuedVAIR CONTRACTING INC10/27/2025
1 project · most recent 05/19/2026
Gas Water/Sanitary
FiledStatusContractorScope
05/19/2026Permit IssuedPRIME PIPING & HEATING INGas, Water/Sanitary
▾Special Inspection Requirements (DOB NOW) — 15
DateRequirementInspectorRole
05/19/2026HVAC-R and service water piping design and insulation—energy_progress
05/19/2026HVAC-R and service water heating system controls—energy_progress
05/19/2026Maintenance information—energy_progress
05/19/2026HVAC-R and service water heating equipment—energy_progress
02/17/2026Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
03/07/2025Insulation placement and R valuesSHAHRIAR QUAYYUMenergy_progress
03/07/2025Interior lighting powerSHAHRIAR QUAYYUMenergy_progress
03/07/2025Maintenance informationSHAHRIAR QUAYYUMenergy_progress
03/07/2025Permanent certificateSHAHRIAR QUAYYUMenergy_progress
03/07/2025Fenestration areasSHAHRIAR QUAYYUMenergy_progress
01/31/2025Fenestration air leakageSHAHRIAR QUAYYUMenergy_progress
01/31/2025Structural Stability – Alterations of existing buildingsSHAHRIAR QUAYYUMspecial
01/31/2025Fire-Resistant Penetrations and JointsSHAHRIAR QUAYYUMspecial
01/31/2025Fire-Resistance Rated ConstructionSHAHRIAR QUAYYUMprogress
01/31/2025Air barrier - visual inspectionSHAHRIAR QUAYYUMenergy_progress
▾Documents — 13 on file (BIS + DOB NOW)
▸Plans & Drawings3
▸DOB NOWPlans/Sketch3
08/17/2026B01174739-S1Request digital key ↗
08/17/2026B01174739-I1Request digital key ↗
08/15/2026B01174739-P1Request digital key ↗
▸Seals & Professional Certifications7
▸DOB NOWDPL-1: Design Professional Seal & Signature3
08/17/2026B01174739-I1Open ↗
08/17/2026B01174739-P1Open ↗
08/17/2026B01174739-S1Open ↗
▸DOB NOWProgress Inspector Seal & Signature2
09/01/2026B01174739-I1Open ↗
09/01/2026B01174739-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
09/01/2026B01174739-I1Open ↗
09/01/2026B01174739-P1Open ↗
▸Environmental & Asbestos3
▸DOB NOWDEP ACP-5: Asbestos Assessment Report3
08/17/2026B01174739-I1Open ↗
08/17/2026B01174739-S1Open ↗
08/15/2026B01174739-P1Open ↗