← Back
Mansion type or town house
1816 EAST 3 STREET
BROOKLYN · Gravesend (East)-Homecrest · BIN 3177220
💬 Discuss this project
1925Year Built
2Stories
A7Building Class
R5Zoning
6,394 sfGross Floor Area
1Units
Mansion type or town house · 4,624 sf lot · 1.38 FAR built · Flood zone X
Locations of Work
ArchitectureStructuralMechanicalPlumbingCivilGeneralOther
Roof2p · 1 filing · 20 docs
Floor 344p · 1 filing · 20 docs
Floor 245p · 1 filing · 20 docs
Floor 155p · 1 filing · 20 docs
Cellar45p · 2 filings · 20 docs
Site & exterior51p · 1 filing · 20 docs
▾Sales History (ACRIS)
DatePriceUnitSeller → Buyer$/sf
07/21/2014$810K—Private party → Private party$127/sf building
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
MSM ENGINEERING SERVICES, PLLC603/11/2025
HAYYAN DESIGN306/23/2023
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
MISTER EXPEDITER903/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
TFJ CONTRACTING LLCGeneral Contractor1707/08/2026
B&B MECH PLBG & HTG LLCPlumbing207/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
M. INT'L ENGINEERING PLLC3129603/11/2025
Building Lifecycle
All (98)Filed (9)Permit Issued (11)Signed Off (5)Inspection (7)Objection (36)Special Inspection (30)
06/16/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
Foundation work filed in conjunction to alt1 application
B00804772-S3
06/04/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
Foundation work filed in conjunction to alt1 application
B00804772-S1
05/29/2025
Inspection — Pass-Final Curb Cut Non-Directive 14
Pass
View inspection ↗
05/21/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
04/22/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
NANIK MASSAND
04/22/2025
Special inspection requirement — Construction Operations Influencing Adjacent Structures
NANIK MASSAND
04/22/2025
Special inspection requirement — Concrete - Cast-In-Place
NANIK MASSAND
04/22/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
04/22/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
NANIK MASSAND
04/22/2025
Special inspection requirement — Fire-Resistance Rated Construction
NANIK MASSAND
04/22/2025
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
03/11/2025
Filed — ALT-CO - New Building with Existing Elements to Remain
Foundation work filed in conjunction to alt1 application
B00804772-P2
03/11/2025
Special inspection requirement — Air barrier — testing
NANIK MASSAND
03/11/2025
Special inspection requirement — Concrete - Cast-In-Place
NANIK MASSAND
03/11/2025
Special inspection requirement — Construction Operations Influencing Adjacent Structures
NANIK MASSAND
03/11/2025
Special inspection requirement — Excavations - Sheeting, Shoring, and Bracing
NANIK MASSAND
03/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
03/11/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
NANIK MASSAND
03/11/2025
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
03/11/2025
Special inspection requirement — Fire-Resistance Rated Construction
NANIK MASSAND
03/11/2025
Special inspection requirement — Air barrier - visual inspection
NANIK MASSAND
03/11/2025
Special inspection requirement — Insulation placement and R values
NANIK MASSAND
03/11/2025
Special inspection requirement — Fenestration air leakage
NANIK MASSAND
03/11/2025
Special inspection requirement — Interior lighting power
NANIK MASSAND
03/11/2025
Special inspection requirement — Fenestration and door U-factor and product ratings
NANIK MASSAND
03/11/2025
Special inspection requirement — Electric vehicle service equipment requirements
NANIK MASSAND
03/11/2025
Special inspection requirement — Fenestration areas
NANIK MASSAND
03/11/2025
Special inspection requirement — Permanent certificate
NANIK MASSAND
03/11/2025
Special inspection requirement — Maintenance information
NANIK MASSAND
03/11/2025
Special inspection requirement — Metering
NANIK MASSAND
02/26/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
Foundation work filed in conjunction to alt1 application
B00804772-S5
02/26/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
Foundation work filed in conjunction to alt1 application
B00804772-S4
02/25/2025
Signed off — ALT-CO - New Building with Existing Elements to Remain
Foundation work filed in conjunction to alt1 application
B00804772-S2
12/09/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
11/27/2024
Inspection — Certified Remove/Cap - work done in accordance with code
Certified
View inspection ↗
11/19/2024
Permit issued — Structural
B00804772-S4-ST
11/18/2024
Permit issued — Foundation
B00804772-S5-FO
10/11/2024
Permit issued — Plumbing
B00804772-S3-PL
05/30/2024
Permit issued — Construction Fence
B00804772-S2-FN
05/30/2024
Permit issued — General Construction
B00804772-I1-GC
02/22/2024
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
02/20/2024
Inspection — Pass-Final PL - Up to 9 Requested Floors
Pass
View inspection ↗
02/12/2024
Special inspection requirement — HVAC-R and service water heating system controls
MOHAMED MAHMOUD
02/12/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
NANIK MASSAND
02/12/2024
Special inspection requirement — Energy Code Compliance Inspections
NANIK MASSAND
02/12/2024
Special inspection requirement — HVAC-R and service water piping design and insulation
MOHAMED MAHMOUD
02/12/2024
Special inspection requirement — HVAC-R and service water heating equipment
MOHAMED MAHMOUD
02/06/2024
Objection resolved — Addressed
01/25/2024
Objection raised — Other
01/17/2024
Filed — ALT-CO - New Building with Existing Elements to Remain
Foundation work filed in conjunction to alt1 application
B00804772-P1
11/06/2023
Inspection — Pass-Final PL - Underground
Pass
View inspection ↗
10/18/2023
Permit issued — Plumbing
B00804772-S3-PL
08/22/2023
Permit issued — Foundation
B00804772-S5-FO
08/22/2023
Permit issued — Structural
B00804772-S4-ST
06/23/2023
Filed — ALT-CO - New Building with Existing Elements to Remain
Foundation work filed in conjunction to alt1 application
B00804772-S6
06/23/2023
Objection resolved — Addressed
06/23/2023
Objection resolved — Addressed
06/15/2023
Permit issued — General Construction
B00804772-I1-GC
05/22/2023
Permit issued — Curb Cut
B00804772-S1-CC
04/28/2023
Permit issued — Construction Fence
B00804772-S2-FN
Latest 60 of 98 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWStructuralSigned-offTFJ CONTRACTING LLC11/19/2024
DOB NOWFoundationSigned-offTFJ CONTRACTING LLC11/18/2024
DOB NOWPlumbingSigned-offTARGET PIPING NY LLC10/11/2024
DOB NOWConstruction FenceSigned-offTFJ CONTRACTING LLC05/30/2024
DOB NOWGeneral ConstructionPermit IssuedTFJ CONTRACTING LLC05/30/2024
DOB NOWPlumbingSigned-offTARGET PIPING NY LLC10/18/2023
DOB NOWFoundationSigned-offTFJ CONTRACTING LLC08/22/2023
DOB NOWStructuralSigned-offTFJ CONTRACTING LLC08/22/2023
DOB NOWGeneral ConstructionPermit IssuedTFJ CONTRACTING LLC06/15/2023
DOB NOWCurb CutSigned-offTFJ CONTRACTING LLC05/22/2023
DOB NOWConstruction FenceSigned-offTFJ CONTRACTING LLC04/28/2023
1 project · most recent 03/11/2025
Gas Storm Water/Sanitary
FiledStatusContractorScope
03/11/2025Signed-offB&B MECH PLBG & HTG LLCGas, Storm, Water/Sanitary
1 project · most recent 01/22/2024
General Wiring
FiledStatusContractorScope
01/22/2024CompleteJ & F ELECL CONTNG INCGeneral Wiring
1 project · most recent 03/11/2025
Steel Wood
FiledStatusContractorScope
03/11/2025Signed-offTFJ CONTRACTING LLCSteel, Wood
1 project · most recent 03/11/2025
Fence
FiledStatusContractorScope
03/11/2025Signed-offTFJ CONTRACTING LLCFence
▾Field Inspections (DOB CAP) — 7
DateTypeResultReport
05/29/2025Pass-Final Curb Cut Non-Directive 14PassView ↗
05/21/2025Pass-Final CND-Occupancy InspectionPassView ↗
12/09/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
11/27/2024Certified Remove/Cap - work done in accordance with codeCertifiedView ↗
02/22/2024Pass-Final PL - UndergroundPassView ↗
02/20/2024Pass-Final PL - Up to 9 Requested FloorsPassView ↗
11/06/2023Pass-Final PL - UndergroundPassView ↗
▾Special Inspection Requirements (DOB NOW) — 46
DateRequirementInspectorRole
04/22/2025Structural Stability – Alterations of existing buildingsNANIK MASSANDspecial
04/22/2025Construction Operations Influencing Adjacent StructuresNANIK MASSANDspecial
04/22/2025Concrete - Cast-In-PlaceNANIK MASSANDspecial
04/22/2025Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
04/22/2025Excavations - Sheeting, Shoring, and BracingNANIK MASSANDspecial
04/22/2025Fire-Resistance Rated ConstructionNANIK MASSANDprogress
04/22/2025Energy Code Compliance InspectionsNANIK MASSANDprogress
03/11/2025Air barrier — testing NANIK MASSANDenergy_progress
03/11/2025Concrete - Cast-In-PlaceNANIK MASSANDspecial
03/11/2025Construction Operations Influencing Adjacent StructuresNANIK MASSANDspecial
03/11/2025Excavations - Sheeting, Shoring, and BracingNANIK MASSANDspecial
03/11/2025Fire-Resistant Penetrations and JointsNANIK MASSANDspecial
03/11/2025Structural Stability – Alterations of existing buildingsNANIK MASSANDspecial
03/11/2025Energy Code Compliance InspectionsNANIK MASSANDprogress
03/11/2025Fire-Resistance Rated ConstructionNANIK MASSANDprogress
03/11/2025Air barrier - visual inspectionNANIK MASSANDenergy_progress
03/11/2025Insulation placement and R valuesNANIK MASSANDenergy_progress
03/11/2025Fenestration air leakageNANIK MASSANDenergy_progress
03/11/2025Interior lighting powerNANIK MASSANDenergy_progress
03/11/2025Fenestration and door U-factor and product ratingsNANIK MASSANDenergy_progress
03/11/2025Electric vehicle service equipment requirementsNANIK MASSANDenergy_progress
03/11/2025Fenestration areasNANIK MASSANDenergy_progress
03/11/2025Permanent certificateNANIK MASSANDenergy_progress
03/11/2025Maintenance informationNANIK MASSANDenergy_progress
03/11/2025MeteringNANIK MASSANDenergy_progress
Latest 25 of 46.
▾Documents — 73 on file (BIS + DOB NOW)
▸Plans & Drawings9
▸DOB NOWPlans/Sketch9
08/26/2026B00804772-S2Request digital key ↗
08/26/2026B00804772-P2Request digital key ↗
08/26/2026B00804772-S6Request digital key ↗
Showing 3 of 9 on file for this type
▸Applications & Permits1
▸BISPLAN / WORK APPROVAL APPLICATION1
02/06/2023340878633Open ↗
▸Zoning, Tax Lot & Property Records5
▸DOB NOWZD1: DOB Zoning Diagram2
08/13/2026B00804772-I1Open ↗
08/13/2026B00804772-P2Open ↗
▸DOB NOWZoning Exhibit form (1-5)2
08/13/2026B00804772-P2Open ↗
08/13/2026B00804772-I1Open ↗
▸DOB NOWHouse Number Verification: TOPO Stamp1
08/13/2026B00804772-I1Open ↗
▸Seals & Professional Certifications27
▸DOB NOWProgress Inspector Seal & Signature10
09/12/2026B00804772-P2Open ↗
09/12/2026B00804772-P2Open ↗
08/31/2026B00804772-S5Open ↗
Showing 3 of 10 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature9
08/26/2026B00804772-P2Open ↗
08/26/2026B00804772-P1Open ↗
08/26/2026B00804772-S6Open ↗
Showing 3 of 9 on file for this type
▸DOB NOWSpecial Inspector Seal & Signature6
09/12/2026B00804772-P2Open ↗
08/31/2026B00804772-S5Open ↗
08/27/2026B00804772-I1Open ↗
Showing 3 of 6 on file for this type
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY1
02/06/2023340878633Open ↗
▸BISAPPLICANT OWNER SIGNATURE1
02/06/2023340878633Open ↗
▸Safety & Tenant Protection6
▸BISSTREET TREE CHECKLIST2
06/12/2023340878633Open ↗
02/08/2023340878633Open ↗
▸BISSTREET TREES SITE PLAN1
06/12/2023340878633Open ↗
▸DOB NOWStreet Trees Site Plan1
08/13/2026B00804772-I1Open ↗
▸DOB NOWParks Department Acknowledgment Letter for Street Trees Plan1
08/13/2026B00804772-I1Open ↗
▸DOB NOWStreet Tree Sign Off1
08/13/2026B00804772-I1Open ↗
▸Environmental & Asbestos10
▸DOB NOWDEP ACP-5: Asbestos Assessment Report9
08/26/2026B00804772-P2Open ↗
08/26/2026B00804772-S6Open ↗
08/26/2026B00804772-S5Open ↗
Showing 3 of 9 on file for this type
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
02/06/2023340878633Open ↗
▸Energy Compliance1
▸BISTECHNICAL REPORT STATEMENT OF RESPONSIBILITY FOR ENERGY CODE PROGRESS INSPECTIONS1
02/06/2023340878633Open ↗
▸Inspections & Test Reports2
▸DOB NOWGeotechnical Report (BC 1803.6)2
08/13/2026B00804772-S5Open ↗
08/13/2026B00804772-S6Open ↗
▸Filing & Intake Forms1
▸BISEFILING JOB APPLICATION COVER SHEET1
02/06/2023340878633Open ↗
▸Other Documents11
▸BISBPP - SUPPORTING DOCUMENTATION2
02/08/2023340878633Open ↗
02/08/2023340878633Open ↗
▸DOB NOWSite Survey: Initial2
08/13/2026B00804772-I1Open ↗
08/13/2026B00804772-P2Open ↗
▸DOB NOWFinal Survey2
08/26/2026B00804772-I1Open ↗
08/13/2026B00804772-I1Open ↗
▸DOB NOWLocal Law 92/94 of 2019 Sustainable Roof Zone2
08/13/2026B00804772-P2Open ↗
08/13/2026B00804772-I1Open ↗
▸DOB NOWProperty Ownership Certification2
08/26/2026B00804772-P2Open ↗
08/26/2026B00804772-I1Open ↗
▸BISRECORDS MGMT FEE PAYMENT RECEIPT1
06/12/2023340878633Open ↗