| Firm | Filings | Most Recent |
|---|---|---|
| AG ENGINEERING PLLC | 2 | 06/01/2026 |
| Representative | Filings | Most Recent |
|---|---|---|
| XPDITE GROUP LLC (104) | 1 | 03/21/2026 |
| XPDITE GROUP LLC 105 | 1 | 03/21/2026 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 02/02/2026 | — | — | 2 scope_items |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/01/2026 | — | — | Fence |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/22/2026 | Exterior Insulation and Finish Systems (EIFS) | — | special |
| 01/22/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 01/22/2026 | Energy Code Compliance Inspections | — | progress |
| 01/22/2026 | Fire-Resistance Rated Construction | — | progress |
| 01/22/2026 | Air barrier — testing | — | energy_progress |
| 01/22/2026 | Insulation placement and R values | — | energy_progress |
| 01/22/2026 | Fenestration air leakage | — | energy_progress |
| 01/22/2026 | Lighting in dwelling units | — | energy_progress |
| 01/22/2026 | Air barrier - visual inspection | — | energy_progress |
| 01/22/2026 | Fenestration and door U-factor and product ratings | — | energy_progress |
| 01/22/2026 | Interior lighting power | — | energy_progress |
| 01/22/2026 | Maintenance information | — | energy_progress |
| 01/22/2026 | Exterior lighting power | — | energy_progress |
| 01/22/2026 | Fenestration areas | — | energy_progress |
| 01/22/2026 | Lighting controls | — | energy_progress |
| 01/22/2026 | Metering | — | energy_progress |
| 01/22/2026 | Protection of exposed foundation insulation | — | energy_progress |