| Owner | Filings | Most Recent |
|---|---|---|
| Yitzchok Trust | 6 | 03/21/2026 |
| Smart Consulting NY | 4 | 04/09/2026 |
| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 01/21/2025 | $2.2M | — | — → — | — not available |
| Firm | Filings | Most Recent |
|---|---|---|
| Nikolai Katz Architect | 4 | 09/03/2026 |
| Structural Engineering Technologies | 8 | 08/20/2026 |
| Associates | 4 | 05/13/2026 |
| McHenery Testing Lab | 2 | 01/30/2026 |
| Mje Professional Services | 1 | 01/16/2026 |
| Grid Drafting and Consulting | 1 | 12/22/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| Sierra Safety | 2 | 03/21/2026 |
| YG Expediting | 13 | 03/21/2026 |
| New American Construction | 2 | 03/21/2026 |
| SNR Expediting Design | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Success Developers | General Contractor | 13 | 07/08/2026 |
| Success Developers | Scaffold | 6 | 04/09/2026 |
| New American Construction | Scaffold | 3 | 04/09/2026 |
| B&B Mechanical Plumbing & Heating | Plumbing | 1 | 07/08/2026 |
| Fast Repair | Plumbing | 1 | 07/08/2026 |
| Target Piping NY | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Regional Testing | 394 | 13 | 09/03/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Plumbing | Permit Issued | Fast Repair | 04/16/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | Success Developers | 03/10/2026 |
| DOB NOW | General Construction | Permit Issued | Success Developers | 03/10/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | Success Developers | 02/19/2026 |
| DOB NOW | Protection and Mechanical Methods | Permit Issued | New American Construction | 02/04/2026 |
| DOB NOW | Supported Scaffold | Permit Issued | New American Construction | 01/16/2026 |
| DOB NOW | Plumbing | Permit Issued | Target Piping NY | 01/06/2026 |
| DOB NOW | Sprinklers | Permit Issued | Target Piping NY | 01/06/2026 |
| DOB NOW | Sidewalk Shed | Permit Issued | New American Construction | 01/06/2026 |
| DOB NOW | Foundation | Permit Issued | Success Developers | 12/29/2025 |
| DOB NOW | Support of Excavation | Permit Issued | Success Developers | 12/29/2025 |
| DOB NOW | Structural | Permit Issued | Success Developers | 12/29/2025 |
| DOB NOW | Foundation | Permit Issued | Success Developers | 12/09/2025 |
| DOB NOW | Support of Excavation | Permit Issued | Success Developers | 12/08/2025 |
| DOB NOW | Construction Fence | Permit Issued | Success Developers | 12/08/2025 |
| DOB NOW | Construction Fence | Permit Issued | Success Developers | 11/28/2025 |
| DOB NOW | Foundation | Permit Issued | Success Developers | 07/15/2025 |
| DOB NOW | Support of Excavation | Permit Issued | Success Developers | 07/07/2025 |
| DOB NOW | Support of Excavation | Permit Issued | Success Developers | 05/23/2025 |
| DOB NOW | Foundation | Permit Issued | Success Developers | 05/22/2025 |
| DOB NOW | Construction Fence | Permit Issued | Success Developers | 12/03/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 09/03/2026 | Permit Issued | Success Developers | Air Conditioning Systems, Heating and Air Conditioning Systems, Heating Systems, Ventilation Systems | Cooling Daikin RK12NMVJU 10,900 BTU · Heat Pump Outdoor ×1 Heat / Cool Daikin RXTQ60TBVJUA 5 tons · Vrf Outdoor ×5 RXTQ36TBVJUA 3 tons · Vrf Outdoor ×3 RXTQ48TBVJUA 4 tons · Vrf Outdoor ×1 RXTA36AAUJU 3 tons · Heat Pump Outdoor ×12 RXTA48AAVJU 4 tons · Vrf Outdoor ×3 RXTA24AAUJU 2 tons · Vrf Outdoor ×1 Heating — CSH-07A 7,680 BTU ×4 Ventilation — RENEWAIRE HE07RT 400 CFM ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2026 | Permit Issued | Target Piping NY | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 06/08/2026 | Permit Issued | M.R. Electrical Service | General Wiring |
| 03/12/2026 | Permit Issued | Power Direct Electric | — |
| 01/06/2026 | Complete | Richard Neu | — |
| 11/27/2025 | Permit Issued | Power Direct Electric | General Wiring |
| 07/03/2025 | Permit Issued | Power Direct Electric | — |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/03/2026 | Permit Issued | Success Developers | 1 scope_items |
| 11/03/2025 | Permit Issued | Success Developers | 3 scope_items |
| 08/04/2025 | Permit Issued | Success Developers | 3 scope_items |
| Date | Type | Result | Report |
|---|---|---|---|
| 05/15/2026 | Certified Water and Sanitary-WS-Fixtures-Finish | Certified | View ↗ |
| 04/29/2026 | Pass-Final PL - Underground | Pass | View ↗ |
| 04/16/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 02/26/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/12/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 09/01/2026 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |
| 09/01/2026 | Air barrier — testing | Paul Raymond | energy_progress |
| 09/01/2026 | Fire-Resistance Rated Construction | Paul Raymond | progress |
| 09/01/2026 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 09/01/2026 | Post-installed Anchors | Paul Raymond | special |
| 09/01/2026 | Alternative Materials - OTCR Buildings Bulletin Number | Paul Raymond | special |
| 09/01/2026 | Protection of exposed foundation insulation | Paul Raymond | energy_progress |
| 09/01/2026 | Fenestration and door U-factor and product ratings | Paul Raymond | energy_progress |
| 09/01/2026 | Interior lighting power | Paul Raymond | energy_progress |
| 09/01/2026 | Fenestration air leakage | Paul Raymond | energy_progress |
| 09/01/2026 | Metering | Paul Raymond | energy_progress |
| 09/01/2026 | Insulation placement and R values | Paul Raymond | energy_progress |
| 09/01/2026 | Exterior lighting power | Paul Raymond | energy_progress |
| 09/01/2026 | Lighting in dwelling units | Paul Raymond | energy_progress |
| 09/01/2026 | Electrical motors and elevators | Paul Raymond | energy_progress |
| 09/01/2026 | Lighting controls | Paul Raymond | energy_progress |
| 09/01/2026 | Air barrier - visual inspection | Paul Raymond | energy_progress |
| 09/01/2026 | Fenestration areas | Paul Raymond | energy_progress |
| 08/19/2026 | Footing and Foundation | — | progress |
| 08/19/2026 | Final | — | progress |
| 08/19/2026 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 08/19/2026 | Subgrade Inspections | — | special |
| 08/19/2026 | Concrete - Cast-In-Place | — | special |
| 03/11/2026 | Energy Code Compliance Inspections | Paul Raymond | progress |
| 03/11/2026 | Fire-Resistant Penetrations and Joints | Paul Raymond | special |