← Back
BROOKLYN
1823 LINDEN BOULEVARD
BROOKLYN · East New York-New Lots · BIN 3348150
💬 Discuss this project
—Year Built
—Stories
—Building Class
—Zoning
—Gross Floor Area
—Units
Flood zone X500
Locations of Work
Architecture
Roof1p · 1 filing · 8 docs
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
TOM PETERSEN ARCHITECT, LLC103/13/2025
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
VOLTAIC SOLAIRE LLCGeneral Contractor303/21/2026
BERGER QUALITY ELEC'L CONElectrical103/22/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
THOMAS PETERSEN ARCHITECT7854103/13/2025
Building Lifecycle
All (8)Filed (1)Permit Issued (1)Signed Off (1)Special Inspection (5)
06/26/2025
Signed off — Alteration
Installation of PV system on existing roof no change to egress or use of occupancy
B01193516-I1
03/21/2025
Permit issued — Solar
B01193516-I1-SL
03/13/2025
Filed — Alteration
Installation of PV system on existing roof no change to egress or use of occupancy
B01193516-I1
03/11/2025
Special inspection requirement — Fire-Resistant Penetrations and Joints
TOM PETERSEN
03/11/2025
Special inspection requirement — Structural Stability – Alterations of existing buildings
TOM PETERSEN
03/11/2025
Special inspection requirement — Energy Code Compliance Inspections
TOM PETERSEN
03/11/2025
Special inspection requirement — Final
TOM PETERSEN
03/11/2025
Special inspection requirement — Air barrier - visual inspection
TOM PETERSEN
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWSolarSigned-offVOLTAIC SOLAIRE LLC03/21/2025
BISPLISSUEDJ.E.S. PLBG & HTG CORP12/27/2001
1 project · most recent 10/21/2024
FiledStatusContractorScope
10/21/2024CompleteBERGER QUALITY ELEC'L CON—
▾Special Inspection Requirements (DOB NOW) — 5
DateRequirementInspectorRole
03/11/2025Fire-Resistant Penetrations and JointsTOM PETERSENspecial
03/11/2025Structural Stability – Alterations of existing buildingsTOM PETERSENspecial
03/11/2025Energy Code Compliance InspectionsTOM PETERSENprogress
03/11/2025FinalTOM PETERSENprogress
03/11/2025Air barrier - visual inspectionTOM PETERSENenergy_progress
▾Documents — 8 on file (BIS + DOB NOW)
▸Plans & Drawings1
▸DOB NOWPlans/Sketch1
08/22/2026B01193516-I1Request digital key ↗
▸Seals & Professional Certifications6
▸DOB NOWProgress Inspector Seal & Signature3
08/27/2026B01193516-I1Open ↗
08/27/2026B01193516-I1Open ↗
08/27/2026B01193516-I1Open ↗
▸DOB NOWSpecial Inspector Seal & Signature2
08/27/2026B01193516-I1Open ↗
08/27/2026B01193516-I1Open ↗
▸DOB NOWDPL-1: Design Professional Seal & Signature1
08/13/2026B01193516-I1Open ↗
▸Approvals, Objections & Sign-offs1
▸DOB NOWUtility Company Final Acceptance Letter1
08/13/2026B01193516-I1Open ↗