← Back
One story retail building
183-02 HORACE HARDING EXPWY
QUEENS · BIN 4152787
💬 Discuss this project
1950Year Built
1Stories
K1Building Class
R3-2Zoning
8,640 sfGross Floor Area
5Units
2 Open Violations 0 unresolved · 2 paperwork only ▸FDNY Report ↗
One story retail building · Owner of record: HORACE 183 REALTY LLC · 12,000 sf lot · 0.72 FAR built · Flood zone X
Locations of Work
ArchitectureStructural
Floor 13p · 1 filing · 5 docs
Cellar5p · 1 filing · 5 docs
▾Owner History (Filing Record)
Companies and organizations named on filings. Individual owners are not shown.
OwnerFilingsMost Recent
HORACE 183 REALTY1203/22/2026
ALI BABA ENTERPRISES603/21/2026
BEN-KAN ENTERPRISES103/21/2026
▾Design Consultants (Architect / Engineer of Record)
FirmFilingsMost Recent
CARUSONE & CHERRES ARCHITECTS, LLC306/04/2024
GERALD CALIENDO ARCHITECTS305/21/2024
▾Filing Representatives (Expediters)
RepresentativeFilingsMost Recent
GERALD J CALIENDO ARCHITECT P C603/21/2026
AB WORKS PROCESSING303/21/2026
▾Contractors (License-Anchored)
FirmTradeRolesMost Recent
DONOHUE, MICHAELElectrical103/21/2026
HI-RITE ELECTRIC CORPElectrical103/22/2026
MCCLARIN, LEROYElectrical103/21/2026
RODNEY SCOTTElectrical103/21/2026
ROOPCHAND SINGHElectrical103/21/2026
IMPACT BUILDERS CORPGeneral Contractor107/08/2026
STIVAN PLBG & HTG INCPlumbing107/08/2026
▾Special Inspection Agencies
AgencyLicense #FilingsMost Recent
CARUSONE & CHERRES ARCHIT6166306/04/2024
WORLD DESIGN ARCHITECTURE9323102/05/2024
Building Lifecycle
All (65)Filed (6)Permit Issued (2)Violation (20)Inspection (8)Objection (26)Special Inspection (3)
06/29/2026
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
03/10/2025
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
01/16/2025
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
12/16/2024
Inspection — Fail-Final CND-Occupancy Inspection
Fail
View inspection ↗
11/20/2024
Permit issued — General Construction
Q00989105-I1-GC-CX
11/15/2024
Inspection — Pass-Final CND-Occupancy Inspection
Pass
View inspection ↗
07/08/2024
Objection resolved — Addressed
07/08/2024
Objection resolved — Addressed
07/01/2024
Objection resolved — Addressed
07/01/2024
Objection resolved — Addressed
07/01/2024
Objection resolved — Addressed
06/18/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
06/17/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JORGE CHERRES
06/07/2024
Objection resolved — Addressed
06/07/2024
Objection resolved — Addressed
06/06/2024
Objection resolved — Addressed
06/06/2024
Objection resolved — Addressed
06/04/2024
Filed — Alteration
NEW GAS PIPING FOR GAS EQUIPMENT IN AN EXISTING BAGEL SHOP DUE TO FIRE DAMAGE AS PER PLANS AND OBTAIN A LETTER OF COMPLETION AS PER ZONING AND BUILDING CODES STANDARDS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
Q01017969-P2
06/03/2024
Objection raised — Fire_Protection
06/03/2024
Objection raised — Other
06/03/2024
Objection raised — Other
06/03/2024
Objection raised — Structural
06/03/2024
Objection raised — Scope
06/03/2024
Objection resolved — Addressed
06/03/2024
Objection raised — Other
06/03/2024
Objection raised — Fire_Protection
06/03/2024
Objection raised — Admin
05/30/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JORGE CHERRES
05/29/2024
Inspection — Pass-Final PL - Up to 3 Requested Floors
Pass
View inspection ↗
05/22/2024
Inspection — Certified Gas-Gas-Piping-Roughing
Certified
View inspection ↗
05/21/2024
Filed — No Work
Q01054081-I1
05/02/2024
Filed — Alteration
NEW GAS PIPING FOR GAS EQUIPMENT IN AN EXISTING BAGEL SHOP DUE TO FIRE DAMAGE AS PER PLANS AND OBTAIN A LETTER OF COMPLETION AS PER ZONING AND BUILDING CODES STANDARDS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
Q01017969-P1
05/01/2024
Special inspection requirement — Fire-Resistant Penetrations and Joints
JORGE CHERRES
04/19/2024
Objection resolved — Addressed
04/18/2024
Objection resolved — Addressed
04/11/2024
Objection resolved — Addressed
03/29/2024
Permit issued — Plumbing
Q01017969-I1-PL
03/12/2024
Filed — Alteration
NEW GAS PIPING FOR GAS EQUIPMENT IN AN EXISTING BAGEL SHOP DUE TO FIRE DAMAGE AS PER PLANS AND OBTAIN A LETTER OF COMPLETION AS PER ZONING AND BUILDING CODES STANDARDS. NO CHANGE IN USE, EGRESS, OR OCCUPANCY UNDER THIS APPLICATION.
Q01017969-I1
02/26/2024
Objection raised — Fire_Protection
02/26/2024
Objection raised — Structural
02/26/2024
Objection raised — Inspections
02/26/2024
Objection raised — Inspections
02/26/2024
Objection raised — Inspections
02/09/2024
Filed — No Work
Q00997904-I1
02/05/2024
Filed — Alteration CO
Q00989105-I1
09/29/2022
Violation issued (FDNY_NOV, closed)
09/29/2022
Violation issued (FDNY_NOV, closed)
02/26/2022
Violation issued (FDNY_NOV, closed)
02/26/2022
Violation issued (FDNY_NOV, closed)
04/11/2019
Violation issued (ECB, open)
Construction
08/14/2018
Violation issued (ECB, closed)
Construction
07/25/2018
Violation issued (DOB, closed)
V*-DOB VIOLATION - DISMISSED
06/13/2018
Violation issued (FDNY_ORDER, closed)
04/26/2018
Violation issued (ECB, closed)
Construction
08/28/2017
Violation issued (ECB, open)
Construction
06/04/2014
Violation issued (FDNY_NOV, closed)
05/23/2012
Violation issued (ECB, closed)
Construction
05/18/2012
Violation issued (ECB, closed)
Construction
05/18/2012
Violation issued (ECB, closed)
Construction
05/04/2005
Violation issued (ECB, closed)
Construction
Latest 60 of 65 events.
Permit / Filing Register
SourceWork TypeStatusApplicantIssued
DOB NOWGeneral ConstructionPermit IssuedIMPACT BUILDERS CORP11/20/2024
DOB NOWPlumbingSigned-offSTIVAN PLBG & HTG INC03/29/2024
BISOTISSUEDHENRYSMITH PROPERTY MGMT03/15/2019
BISOTISSUEDHENRYSMITH PROPERTY MGMT01/23/2019
BISEQISSUEDHENRYSMITH PROPERTY MGMT01/23/2019
BISPLISSUEDSO PLUMBING & HEATING INC09/18/2018
BISOTISSUEDLAILE INC06/25/2012
BISPLISSUEDFLEET PLBG AND HTG INC03/12/2012
BISOTISSUEDLAILE INC01/31/2012
BISOTISSUEDN.Y.C ROCK INC01/30/2012
BISFPISSUEDFIRE COMMAND CO. INC.05/16/2007
BIS—ISSUEDNY SIGN CITY INC12/15/2005
BISOTISSUEDH & Z DESIGN CORP12/15/2005
BISOTISSUEDRUSSELL CONSTRUCTION06/06/2005
BISEQISSUEDRUSSELL CONSTRUCTION06/06/2005
BISFPISSUEDMASTER FIRE SYSTEMS, INC01/18/2001
BISMHISSUEDEASTERN 2000 INC.01/17/2001
BISOTISSUEDEASTERN 2000 INC.01/16/2001
BISEQISSUEDSMILEY'S MARKET INC11/02/2000
BISFPISSUEDIDEAL FIRE CONTROL02/21/1995
BISPLISSUEDSTARLITE P & H06/17/1993
BISMHISSUEDINTERSCAPE DESIGN GROUP INC05/20/1993
1 project · most recent 06/04/2024
Gas
FiledStatusContractorScope
06/04/2024Signed-offSTIVAN PLBG & HTG INCGas
3 projects · most recent 08/16/2019
General Wiring
FiledStatusContractorScope
08/16/2019CompleteHI-RITE ELECTRIC CORP—
09/17/2018CompletePAPPAS & FODERA ELECT'LGeneral Wiring
01/17/2018CompleteHI-RITE ELECTRIC CORPGeneral Wiring
▾Field Inspections (DOB CAP) — 8
DateTypeResultReport
06/29/2026Fail-Final CND-Occupancy InspectionFailView ↗
03/10/2025Fail-Final CND-Occupancy InspectionFailView ↗
01/16/2025Pass-Final CND-Occupancy InspectionPassView ↗
12/16/2024Fail-Final CND-Occupancy InspectionFailView ↗
11/15/2024Pass-Final CND-Occupancy InspectionPassView ↗
06/18/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/29/2024Pass-Final PL - Up to 3 Requested FloorsPassView ↗
05/22/2024Certified Gas-Gas-Piping-RoughingCertifiedView ↗
▾Special Inspection Requirements (DOB NOW) — 3
DateRequirementInspectorRole
06/17/2024Fire-Resistant Penetrations and JointsJORGE CHERRESspecial
05/30/2024Fire-Resistant Penetrations and JointsJORGE CHERRESspecial
05/01/2024Fire-Resistant Penetrations and JointsJORGE CHERRESspecial
▾Documents — 118 on file (BIS + DOB NOW)
▸Plans & Drawings6
▸DOB NOWPlans/Sketch4
08/23/2026Q00989105-I1Request digital key ↗
08/22/2026Q01017969-I1Request digital key ↗
08/22/2026Q01017969-P1Request digital key ↗
Showing 3 of 4 on file for this type
▸DOB NOWPlans/Sketch - Place of Assembly2
08/23/2026Q00997904-I1Request digital key ↗
08/22/2026Q01054081-I1Request digital key ↗
▸Applications & Permits30
▸BISPLAN / WORK APPROVAL APPLICATION16
06/25/2019421228102Open ↗
06/17/2019421228111Open ↗
05/02/2019421228111Open ↗
Showing 3 of 16 on file for this type
▸BISWORK PERMIT APPLICATION8
03/20/2019421228111Open ↗
01/25/2019421228111Open ↗
10/15/2018421679865Open ↗
Showing 3 of 8 on file for this type
▸BISPLACE OF ASSEMBLY4
09/03/2019421228102Open ↗
08/05/2019421228102Open ↗
06/10/2019421228102Open ↗
Showing 3 of 4 on file for this type
▸BISIntent to Revoke Approval/Permit2
11/15/2013420527200Open ↗
03/28/2013420527200Open ↗
▸Seals & Professional Certifications30
▸BISTECHNICAL REPORT: RESPONSIBILITY/CERTIFICATION13
09/03/2019421228102Open ↗
09/03/2019421228102Open ↗
12/22/2018421228111Open ↗
Showing 3 of 13 on file for this type
▸DOB NOWDPL-1: Design Professional Seal & Signature6
08/23/2026Q00989105-I1Open ↗
08/22/2026Q01054081-I1Open ↗
08/22/2026Q01017969-I1Open ↗
Showing 3 of 6 on file for this type
▸BISPROFESSIONAL CERTIFICATION STATEMENT FORM4
06/15/2012420580348Open ↗
06/15/2012420580348Open ↗
06/15/2012420580348Open ↗
Showing 3 of 4 on file for this type
▸BISPROFESSIONAL CERTIFIED CHECKLIST3
10/15/2018421679865Open ↗
06/15/2012420580348Open ↗
01/27/2012420527200Open ↗
▸DOB NOWSpecial Inspector Seal & Signature3
08/26/2026Q01017969-P1Open ↗
08/22/2026Q01017969-P2Open ↗
08/22/2026Q01017969-I1Open ↗
▸BISPROFESSIONAL CERTIFICATION STATEMENT1
10/15/2018421679865Open ↗
▸Trade Schedules & Equipment6
▸BISSCHEDULE B - PLUMBING/SPRINKLER/STANDPIPE3
05/02/2019421228111Open ↗
10/15/2018421679865Open ↗
04/25/2016421228111Open ↗
▸BISSELF-CERT PLUMBING NOTICE2
11/03/2012420527200Open ↗
04/12/2012420527200Open ↗
▸BISSCHEDULE B - PLUMBING1
01/27/2012420527200Open ↗
▸Safety & Tenant Protection1
▸DOB NOWStreet Tree Checklist1
08/23/2026Q00989105-I1Open ↗
▸Environmental & Asbestos4
▸BISASBESTOS EXEMPTION CERTIFICATION LETTER2
06/15/2012420580348Open ↗
06/23/2010420204923Open ↗
▸BISASBESTOS: CERTIFICATION (DEP ACP5)1
10/15/2018421679865Open ↗
▸DOB NOWDEP ACP-5: Asbestos Assessment Report1
08/23/2026Q00989105-I1Open ↗
▸Energy Compliance5
▸BISTECHNICAL REPORT: ENERGY CODE PROGRESS INSPS3
12/22/2018421228111Open ↗
11/06/2015421228111Open ↗
12/17/2012420527200Open ↗
▸BISAS-BUILT ENERGY ANALYSIS1
12/17/2012420527200Open ↗
▸BISTECHNICAL REPORT: ENERGY1
01/27/2012420527200Open ↗
▸Inspections & Test Reports1
▸BISINSPECTION REPORT - SUPPORTING DOCUMENTATION1
09/03/2019421228102Open ↗
▸Approvals, Objections & Sign-offs17
▸BISLETTERS - SUPPORTING DOCUMENTATION11
09/03/2019421228102Open ↗
09/03/2019421228102Open ↗
09/03/2019421228102Open ↗
Showing 3 of 11 on file for this type
▸BISCERTIFICATE OF OCCUPANCY/LOC: REQUEST3
10/26/2018421679865Open ↗
12/17/2012420527200Open ↗
09/17/2012420580348Open ↗
▸BISADMINISTRATIVE OBJECTIONS3
06/15/2012420580348Open ↗
01/27/2012420527200Open ↗
06/23/2010420204923Open ↗
▸Cost, Insurance & Ownership8
▸BISCOST AFFIDAVIT8
10/26/2018421679865Open ↗
10/15/2018421679865Open ↗
11/06/2015421228111Open ↗
Showing 3 of 8 on file for this type
▸Filing & Intake Forms9
▸BISEFILING COVER SHEET6
10/15/2018421679865Open ↗
04/25/2016421228111Open ↗
11/06/2015421228111Open ↗
Showing 3 of 6 on file for this type
▸BISADDITIONAL INFORMATION3
04/26/2016421228111Open ↗
06/30/2012420580348Open ↗
06/29/2012420580348Open ↗
▸Other Documents1
▸DOB NOWProperty Ownership Certification1
08/23/2026Q00989105-I1Open ↗