| Date | Price | Unit | Seller → Buyer | $/sf |
|---|---|---|---|---|
| 12/07/2021 | $2.9M | — | Private party → Private party | $1,080/sf building |
| Firm | Filings | Most Recent |
|---|---|---|
| LEVIN ENGINEERING PLLC | 5 | 08/03/2026 |
| ROBERT SIQECA PE | 7 | 06/18/2025 |
| CORNERSTONE DESIGNS | 6 | 04/10/2025 |
| P GEORGOPOULOS ARCHITECT PC | 1 | 01/03/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| 4444 PPPP CORP | 6 | 03/21/2026 |
| LEVIN ENGINEERING PLLC | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| ADASS INC | General Contractor | 11 | 07/08/2026 |
| JODOM MECHANICAL, INC | Plumbing | 3 | 07/08/2026 |
| M.N.C. GENERAL CONTR CORP | General Contractor | 2 | 03/21/2026 |
| PRESTON NYC LLC | General Contractor | 2 | 03/21/2026 |
| CURRENT MECHS ELEC CONTS | Electrical | 1 | 03/22/2026 |
| SAFETY FIRE SPRINKLER CORP | Fire Protection | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| CITY-WIDE TESTING INC | 416 | 9 | 08/03/2026 |
| P GEORGOPOULOS ARCHITECT | 889 | 1 | 01/03/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | General Construction | Permit Issued | ADASS INC | 06/10/2026 |
| DOB NOW | Mechanical Systems | Permit Issued | ADASS INC | 06/03/2026 |
| DOB NOW | Plumbing | Permit Issued | JODOM MECHANICAL, INC | 06/03/2026 |
| DOB NOW | Construction Fence | Permit Issued | ADASS INC | 05/21/2026 |
| DOB NOW | Plumbing | Permit Issued | JODOM MECHANICAL, INC | 05/07/2026 |
| DOB NOW | Plumbing | Permit Issued | SAFETY FIRE SPRINKLER CORP | 02/26/2026 |
| DOB NOW | Plumbing | Permit Issued | JODOM MECHANICAL, INC | 12/10/2025 |
| DOB NOW | Foundation | Signed-off | ADASS | 07/11/2025 |
| DOB NOW | Foundation | Signed-off | ADASS | 07/11/2025 |
| DOB NOW | Support of Excavation | Signed-off | ADASS | 07/11/2025 |
| DOB NOW | Structural | Signed-off | ADASS | 07/09/2025 |
| DOB NOW | General Construction | Permit Issued | ADASS | 07/07/2025 |
| DOB NOW | Construction Fence | Permit Issued | ADASS | 06/20/2025 |
| DOB NOW | General Construction | Signed-off | MNC GENERAL CONTR CORP | 01/29/2025 |
| DOB NOW | Construction Fence | Permit Issued | PRESTON NYC LLC | 07/03/2024 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 08/03/2026 | Permit Issued | ADASS INC | Generators | Generators Cummins C60n6 60 kW · Generator ×2 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 08/03/2026 | Permit Issued | JODOM MECHANICAL, INC | Gas |
| 04/10/2025 | Permit Issued | JODOM MECHANICAL, INC | Storm, Water/Sanitary |
| 01/24/2025 | — | — | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/11/2025 | Permit Issued | CURRENT MECHS ELEC CONTS | General Wiring |
| Date | Type | Result | Report |
|---|---|---|---|
| 04/23/2026 | Certified Remove/Cap - work done in accordance with code | Certified | View ↗ |
| 03/12/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 02/24/2026 | Pass-Final PL - Up to 9 Requested Floors | Pass | View ↗ |
| 01/08/2026 | Certified Storm Drainage-ST-Piping-Underground | Certified | View ↗ |
| 01/08/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| 12/24/2025 | Certified Water and Sanitary-WS-Sanitary Piping-Underground | Certified | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 08/19/2026 | HVAC-R and service water piping design and insulation | — | energy_progress |
| 08/19/2026 | Private On-Site Storm Water Disposal Systems-, and Detention Facilities, Installation | — | special |
| 08/19/2026 | Fire-Resistant Penetrations and Joints | — | special |
| 08/19/2026 | HVAC-R and service water heating equipment | — | energy_progress |
| 08/19/2026 | Permanent certificate | — | energy_progress |
| 08/19/2026 | Maintenance information | — | energy_progress |
| 08/19/2026 | HVAC-R and service water heating system controls | — | energy_progress |
| 07/01/2026 | Mechanical Systems | ELIAS RASABI | special |
| 07/01/2026 | Final | ELIAS RASABI | progress |
| 07/01/2026 | Emergency and Standby Power Systems (Generator) | ELIAS RASABI | special |
| 04/14/2026 | Emergency and Standby Power Systems (Generator) | ELIAS RASABI | special |
| 03/16/2026 | Mechanical Systems | ELIAS RASABI | special |
| 03/16/2026 | Final | ELIAS RASABI | progress |
| 06/23/2025 | Footing and Foundation | ELIAS RASABI | progress |
| 06/23/2025 | Subsurface Investigations (Borings/Test Pits) | Rajasekhar Sakhamuri | special |
| 06/23/2025 | Underpinning | ELIAS RASABI | special |
| 06/23/2025 | Final | ELIAS RASABI | progress |
| 06/23/2025 | Concrete - Cast-In-Place | ELIAS RASABI | special |
| 06/23/2025 | Subgrade Inspections | ELIAS RASABI | special |
| 06/23/2025 | Structural Stability – Alterations of existing buildings | ELIAS RASABI | special |
| 06/17/2025 | Underpinning | — | special |
| 06/17/2025 | Subsurface Investigations (Borings/Test Pits) | — | special |
| 06/17/2025 | Subgrade Inspections | — | special |
| 06/17/2025 | Concrete - Cast-In-Place | — | special |
| 06/17/2025 | Structural Stability – Alterations of existing buildings | — | special |