| Owner | Filings | Most Recent |
|---|---|---|
| OWNER OF 1836 NOSTRAND | 1 | 03/22/2026 |
| URBAN-SCAPE LLC MLM PARTNERS | 1 | 03/22/2026 |
| ARMCRES REALTY | 2 | 03/21/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| BAILEYS ENGINEERING PC | 2 | 10/15/2018 |
| Representative | Filings | Most Recent |
|---|---|---|
| AE DESIGN SOLUTION | 4 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| BBM CONSTRUCTION CORP | General Contractor | 5 | 03/22/2026 |
| POWERS BRIDGING & SCAFFOLDING | General Contractor | 5 | 07/08/2026 |
| CARLO LIBURDI | Electrical | 2 | 03/21/2026 |
| R.C.M. ELECTRIC CORP. | Electrical | 1 | 03/22/2026 |
| STUDIO BD | General Contractor | 1 | 03/22/2026 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Sidewalk Shed | Signed-off | POWERS BRIDGING & SCAFFOL | 12/19/2018 |
| DOB NOW | Supported Scaffold | Signed-off | POWERS BRIDGING & SCAFFOL | 10/16/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | POWERS BRIDGING & SCAFFOL | 03/28/2018 |
| DOB NOW | Sidewalk Shed | Signed-off | POWERS BRIDGING & SCAFFOL | 01/18/2018 |
| BIS | PL | ISSUED | CREATIVE PLUMBING IN | 06/12/2019 |
| BIS | EQ | ISSUED | BBM CONSTRUCTION CORP | 01/31/2019 |
| BIS | OT | ISSUED | BEN'S GEN'L CONTRACT CORP | 12/13/2018 |
| BIS | OT | ISSUED | BBM CONSTRUCTION CORP | 11/20/2018 |
| BIS | — | ISSUED | BBM CONSTRUCTION CORP | 11/20/2018 |
| BIS | — | ISSUED | BBM CONSTRUCTION CORP | 11/20/2018 |
| BIS | OT | ISSUED | BBM CONSTRUCTION CORP | 09/17/2018 |
| BIS | OT | ISSUED | BBM CONSTRUCTION CORP | 09/17/2018 |
| BIS | — | ISSUED | BBM CONSTRUCTION CORP | 09/13/2018 |
| BIS | — | ISSUED | BBM CONSTRUCTION CORP | 09/13/2018 |
| BIS | OT | ISSUED | BBM CONSTRUCTION CORP | 08/08/2018 |
| BIS | PL | ISSUED | CREATIVE PLUMBING IN | 06/13/2018 |
| BIS | — | ISSUED | BBM CONSTRUCTION CORP | 03/16/2018 |
| BIS | — | ISSUED | BBM CONSTRUCTION CORP | 02/13/2018 |
| BIS | EQ | ISSUED | BBM CONSTRUCTION CORP | 02/13/2018 |
| BIS | — | ISSUED | BBM CONSTRUCTION CORP | 02/13/2018 |
| BIS | OT | ISSUED | BBM CONSTRUCTION CORP | 02/06/2018 |
| BIS | OT | ISSUED | BBM CONSTRUCTION CORP | 10/24/2017 |
| BIS | — | ISSUED | GREENSIDE CORP | 04/16/2008 |
| BIS | EQ | ISSUED | GREENSIDE CORP | 04/16/2008 |
| BIS | — | ISSUED | MYM CONST | 01/16/2007 |
| BIS | EQ | RE-ISSUED | MYM CONST INC | 01/16/2007 |
| BIS | EQ | ISSUED | GREENSIDE CORP | 01/05/2007 |
| BIS | EQ | ISSUED | KE TECH CONST INC | 08/31/1999 |
| BIS | — | ISSUED | KE TECH CONST INC | 08/31/1999 |
| BIS | PL | ISSUED | UNFLAT PEROTTO ASSOC | 01/26/1996 |
| BIS | BL | ISSUED | UNFLAT PEROTTO ASSOC | 01/26/1996 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 04/24/2019 | Complete | HORSEPOWER ELECTRIC.& | General Wiring |
| 03/12/2019 | Complete | R.C.M. ELECTRIC CORP. | General Wiring |
| 01/17/2018 | Complete | OPTIMAL ELECTRIC, INC | — |
| 01/09/2018 | Complete | HORSEPOWER ELECTRIC.& | — |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 01/16/2018 | Final | PAUL BAILEY | progress |