4 Open Violations 3 unresolved · 1 paperwork only▸
ECB06/14/2025WORK WITHOUT PERMIT: FSWO ISSUED FOR ALL PLUMBING WORK BEING DONE ON THE RESIDENT. ATOI OBSERVED IN THE INTERIOR NEWLY INSTALLED PLUMBING WORK NO PERMITS WERE FOUND FOR THE SCOPE OF WORK, OBTAIN PERMIT$2K due
ECB06/14/2025NOTED: VIOLATION ISSUED FOR FAILURE TO INSTITUTE/MAINTAIN SAFETY MEASURES NO HANDRAIL. ATOI OBSERVED IN THE INTERIOR NO HANDRAIL SYSTEM ON THE WOODEN STAIRCASE LEADING FROM THE FIRST FLOOR TO THE SECOND FLOOR W$2K due
ECB06/14/2025WORK WITHOUT PERMIT. FSWO ISSUED FOR ALL GENERAL CONSTRUCTION CARPENTRY MASONRY STRUCTURAL WORK BEING DONE ON THE RESIDENT .ATOI OBSERVED A NEWLY BUILT THREE STORY HORIZONTAL AND VERTICAL STRUCTURE CONNECTED TO$2K due
ECB06/16/2025WORK WITHOUT PERMIT: FSWO ISSUED FOR ALL ELECTRICAL WORK BEING DONE ON THE RESIDENT ATOI OBSERVED IN THE INTERIOR NEWLY INSTALLED ELECTRICAL WORK ALSO AT EXPO # 2 THREE MINI SPLIT CONDENSERS WITH THREE ELECTRICHearing held — result not yet published$2K proposed
Two stories - detached, small or mid-size · 5,100 sf lot · 0.39 FAR built · Flood zone X
Locations of Work
No floor-level scope or drawing coverage on file for this building.