| Owner | Filings | Most Recent |
|---|---|---|
| Walter & Samuels | 19 | 06/28/2026 |
| M. Parisi & Son Construction | 13 | 03/21/2026 |
| Nycedc | 7 | 03/21/2026 |
| Amr Services | 2 | 03/21/2026 |
| NYC Department of Housing Preservation and Development | 1 | 03/22/2026 |
| Firm | Filings | Most Recent |
|---|---|---|
| Gulf States Engineering | 2 | 05/28/2026 |
| KA/Aepc | 2 | 09/11/2025 |
| New Age | 1 | 09/10/2025 |
| Gta Architecture | 2 | 05/01/2025 |
| Representative | Filings | Most Recent |
|---|---|---|
| Municipal Building Consultants | 2 | 03/21/2026 |
| Firm | Trade | Roles | Most Recent |
|---|---|---|---|
| Sharp Colors | General Contractor | 3 | 03/21/2026 |
| Kajima Building & Design | General Contractor | 2 | 06/28/2026 |
| Standard Fire Protection | Fire Protection | 1 | 07/08/2026 |
| Standard Plumbing Services | Plumbing | 1 | 07/08/2026 |
| Agency | License # | Filings | Most Recent |
|---|---|---|---|
| Stracar Special Inspectio | 229 | 2 | 05/28/2026 |
| New Age Engineering | 7746 | 1 | 09/10/2025 |
| Source | Work Type | Status | Applicant | Issued |
|---|---|---|---|---|
| DOB NOW | Mechanical Systems | Signed-off | Kajima Building Design | 04/01/2026 |
| DOB NOW | General Construction | Signed-off | Kajima Building Design | 01/23/2026 |
| DOB NOW | Sprinklers | Signed-off | Standard Fire Supp | 09/24/2025 |
| DOB NOW | Plumbing | Signed-off | A&H Plumbing | 09/15/2025 |
| DOB NOW | General Construction | Permit Issued | Sharp Colors | 07/26/2024 |
| BIS | PL | ISSUED | LCS Plumbing & Consulting | 06/08/2017 |
| BIS | OT | ISSUED | B&B Contracting Group | 04/21/2017 |
| BIS | MH | ISSUED | Braumco Mechanical | 04/05/2017 |
| BIS | OT | ISSUED | Braumco Mechanical | 04/04/2017 |
| BIS | MH | ISSUED | Braumco Mechanical | 02/02/2017 |
| BIS | OT | ISSUED | Braumco Mechanical | 02/02/2017 |
| BIS | — | ISSUED | Ultimate Signs & Designs Co | 10/03/2012 |
| BIS | — | ISSUED | Ultimate Signs & Designs Co | 10/03/2012 |
| BIS | — | ISSUED | Ultimate Signs & Designs Co | 10/03/2012 |
| BIS | BL | ISSUED | Mmi Mechanical | 04/17/2012 |
| BIS | SP | ISSUED | Speedway Plumbing | 04/09/2012 |
| BIS | PL | ISSUED | Speedway Plumbing | 03/29/2012 |
| BIS | MH | ISSUED | DO&CO NY Catering | 03/28/2012 |
| BIS | OT | ISSUED | DO&CO NY Catering | 03/28/2012 |
| BIS | PL | ISSUED | Lotus PLG | 02/22/2002 |
| BIS | MH | ISSUED | Lotus PLG | 02/22/2002 |
| BIS | SP | ISSUED | Sirmina Fire Protection | 07/28/1994 |
| BIS | MH | ISSUED | A. International | 05/05/1994 |
| BIS | OT | ISSUED | E.W. Howell Co | 03/16/1994 |
| BIS | MH | ISSUED | E.W. Howell Co | 03/16/1994 |
| BIS | OT | ISSUED | Microwave Satellite TECHNN0O | 01/10/1992 |
| BIS | — | ISSUED | Ace High Cranes | 06/18/1990 |
| BIS | — | ISSUED | Ace High Cranes | 06/18/1990 |
| BIS | — | ISSUED | Ace High Cranes | 06/18/1990 |
| BIS | — | ISSUED | Fleet Mechanical | 02/20/1990 |
| BIS | OT | ISSUED | Fleet Mechanical | 01/17/1990 |
| BIS | OT | ISSUED | Michael Anthony Contracting | 10/24/1989 |
| BIS | — | ISSUED | North Shore Neon Sign Co | 09/06/1989 |
| BIS | — | ISSUED | North Shore Neon Sign Co | 09/06/1989 |
| Filed | Status | Contractor | Scope | Make / Model / Capacity |
|---|---|---|---|---|
| 05/28/2026 | Signed-off | Kajima Building & Design | Heating and Air Conditioning Systems, Refrigeration Systems | Heat / Cool Trane Trane - YSK060A4S0H**D000A1B1A000000000000000000 62,000 BTU · Rooftop Unit ×8 Refrigeration Bohn Bohn BEM0225MS8AMB
* Equipment Capacity is Measured in AWEF Cooler>32 24,000 BTU · Refrigeration Unit ×16 Bohn - BCH0150MDACD *Equipment efficiency is measured in AWEF 153,270 BTU ×8 Bohn - BEM0506MS8AMB *Equipment Efficiency Measured in AWEF Cooler>32 35,000 BTU · Refrigeration Unit ×8 Bohn - BCH0070MDACZ *Equipment Efficiency is measured in AWEF 69,140 BTU · Condensing Unit ×4 |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2025 | Signed-off | Standard Fire Protection | 40 heads |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 09/10/2025 | Signed-off | Standard Plumbing Services | Gas, Storm, Water/Sanitary |
| Filed | Status | Contractor | Scope |
|---|---|---|---|
| 11/25/2025 | Permit Issued | Patriot Electric | General Wiring |
| 07/14/2025 | Permit Issued | Patriot Electric | General Wiring |
| 07/14/2025 | Permit Issued | Patriot Electric | — |
| Date | Type | Result | Report |
|---|---|---|---|
| 03/17/2026 | Pass-Final General Construction Non-Directive 14 | Pass | View ↗ |
| 02/19/2026 | Certified Storm Drainage-ST-Piping-Roughing | Certified | View ↗ |
| 02/19/2026 | Certified Water and Sanitary-WS-Sanitary Piping-Roughing | Certified | View ↗ |
| 01/20/2026 | Certified Sprinkler-SP-Fixtures-Finish | Certified | View ↗ |
| 01/15/2026 | Certified Sprinkler-SP-Piping Dry/Wet-Hydrostatic Test | Certified | View ↗ |
| 01/12/2026 | Pass-Final PL - Up to 3 Requested Floors | Pass | View ↗ |
| 01/05/2026 | No Access-Final PL - Up to 3 Requested Floors | No Access | View ↗ |
| Date | Requirement | Inspector | Role |
|---|---|---|---|
| 06/18/2026 | Final | MIRO Stracar | progress |
| 06/18/2026 | Mechanical Systems | MIRO Stracar | special |
| 05/14/2026 | Final | MIRO Stracar | progress |
| 05/14/2026 | Mechanical Systems | MIRO Stracar | special |
| 10/03/2025 | Structural Steel - High Strength Bolting | — | special |
| 10/03/2025 | Structural Steel - Welding | — | special |
| 10/03/2025 | Fire-Resistant Penetrations and Joints | — | special |
| 08/11/2025 | Final | — | progress |
| 08/11/2025 | Structural Cold-Formed Steel | — | special |
| 08/11/2025 | Structural Steel - Details | — | special |
| 08/07/2025 | Fire-Resistant Penetrations and Joints | Stephen Shishko | special |
| 08/06/2025 | Sprinkler Systems | Stephen Shishko | special |
| 05/06/2025 | Final | George Argiris | progress |
| 04/28/2025 | Final | George Argiris | progress |
| Tenant | Space | Floors | Renovation projects |
|---|---|---|---|
| UPS Supply Chain Solutions | Industrial / Warehouse | Floor 1, Roof | Project Q01266042 |